1 |
Rishabh Sharma (10665) |
Verify the fee deposited. |
11/18/2022 |
PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER |
|
2 |
Madan Pareek (16059) |
Rs. 123180/- deposited by Rera Trans. No. 561 dated 09.11.2022 for extension of registration ( other than corona pandemic ). |
11/21/2022 |
PENDING WITH NODAL OFFICER |
|
3 |
Rishabh Sharma (10665) |
In the said case, promoters applied for an extension of his registration 4th time, and the last extension w.r.t. the Authority's order dated 22.05.2022 was approved with some of the special conditions and one of them is that "The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain a completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 19-11-2022;". But to date as per the last QPR physical development on site is approx. 45% and now the promoter applied for an incomplete extension application for an extension of registration of one more year. Therefore, application is hereby submitted for kind perusal and further orders on whether to deal with the said application or not, or else we may process the Revocation of registration w.r.t. the special conditions mentioned in Form F issued for the period 20-11-2021 to 19-11-2022. |
11/22/2022 |
PENDING WITH JOINT REGISTRAR |
|
4 |
Arpit Sancheti (10683) |
Submitted for further orders in reference to para 3/N. |
11/22/2022 |
PENDING WITH REGISTRAR |
|
5 |
Ramesh Sharma (9009) |
In my opinion possession of this project should be taken over by the authority and to be handed over to third party after hearing the promoter. |
11/22/2022 |
PENDING WITH CHAIRMAN |
|
6 |
NIHAL CHAND GOEL (1) |
Issue notice of rejection of this application u/s 6, with date of hearing given as 12.12.2022. |
11/26/2022 |
PENDING WITH REGISTRAR |
|
7 |
Ramesh Sharma (9009) |
Process for rejection of the application. |
11/26/2022 |
PENDING WITH JOINT REGISTRAR |
|
8 |
Arpit Sancheti (10683) |
Comply as directed. |
11/26/2022 |
PENDING WITH NODAL OFFICER |
|
9 |
Rishabh Sharma (10665) |
Find the show cause notice under section 6 and appear on hearing on 12.12.2022. |
12/1/2022 |
APPLICATION OBJECTED |
|
10 |
Ramesh Sharma (9009) |
Inform promoter as directed by the Hon'ble Chairman in the project file. |
1/5/2023 |
PENDING WITH NODAL OFFICER |
|
11 |
Rishabh Sharma (10665) |
In reference to the attached notesheet, submit a detailed statement, showing the action taken on each of the special conditions of the last extension subjected to; and reasons for non-compliance, wherever applicable. Comply with the directions on or before 12.01.2023. |
1/5/2023 |
APPLICATION OBJECTED |
|
12 |
Promoter |
Dear Sir, As directed by the Hon'ble Chairman Sir, we are hereby submitting the clarification of the special conditions mentioned in the last extension approved on the date 24.01.2022 User updated this details. |
1/6/2023 |
PENDING WITH NODAL OFFICER |
|
13 |
Rishabh Sharma (10665) |
In reference to the attached notesheet in para 11/N, promoter has submitted a reply at para 12/N with the attachment. Therefore, application is submitted for kind perusal and if found appropriate then approval regarding extension process. |
1/6/2023 |
PENDING WITH JOINT REGISTRAR |
|
14 |
Arpit Sancheti (10683) |
Submitted for further orders pls. |
1/6/2023 |
PENDING WITH REGISTRAR |
|
15 |
Ramesh Sharma (9009) |
Submitted for perusal and decision, Sir. |
1/6/2023 |
PENDING WITH CHAIRMAN |
|
16 |
NIHAL CHAND GOEL (1) |
Are any complaints pending or decided in relation to this project, in earlier name or present name of the project? If yes, submit details. If no, we may ask the promoter to submit a detailed construction and development plan, showing as to what works are pending and what progress will be made in each quarter so as to achieve completion of all works within the proposed extended period. |
1/7/2023 |
PENDING WITH REGISTRAR |
|
17 |
Ramesh Sharma (9009) |
Comply with the directions of honourable chairman. |
1/7/2023 |
PENDING WITH JOINT REGISTRAR |
|
18 |
Arpit Sancheti (10683) |
Comply as directed. |
1/7/2023 |
PENDING WITH NODAL OFFICER |
|
19 |
Rishabh Sharma (10665) |
Refer to para 16/N, and give the details of Complaints, if any, and also provide the development plan as per the direction of Hon'ble Chairman Sir. Comply with the directions on or before 16.01.2023. |
1/9/2023 |
APPLICATION OBJECTED |
|
20 |
Promoter |
Dear sir, as directed by the kind Hon’ble authority, we are hereby submitting the detailed construction and development plan and the same has been uploaded under the tab "other documents". Kindly accept our humble submission and oblige us. User updated this details. |
1/17/2023 |
PENDING WITH NODAL OFFICER |
|
21 |
Rishabh Sharma (10665) |
In reference to para 16/N, it is hereby submitted that a total of 8 complaints is filed again the project or promoter as of date, list of complaints is attached for reference and the promoter has also attached that work status plan in the Other Document tab. Therefore, if allowed, promoter may ask to submit the present status of all 8 Complaints filed against him w.r.t. para 16/N. Submitted for further orders, please. |
1/18/2023 |
PENDING WITH JOINT REGISTRAR |
|
22 |
Arpit Sancheti (10683) |
Kindly peruse para 21/N, Submitted for decision pls. |
1/18/2023 |
PENDING WITH REGISTRAR |
|
23 |
Ramesh Sharma (9009) |
ARP should check present status and also ask promoter to submit present status. |
1/19/2023 |
PENDING WITH JOINT REGISTRAR |
|
24 |
Arpit Sancheti (10683) |
Comply as directed. |
1/19/2023 |
PENDING WITH NODAL OFFICER |
|
25 |
Rishabh Sharma (10665) |
In reference to para 16-23/N, submit the present status of all 8 Complaints filed against you, list of complaints is attached. Comply with the directions on or before 27.01.2023 |
1/19/2023 |
APPLICATION OBJECTED |
|
26 |
Promoter |
Dear Sir, as directed by the kind authority we have uploaded the present status of all the 8 complaints filed by the allottees against us under the tab "Any other document". Kindly accept our humble submission and oblige us. User updated this details. |
1/27/2023 |
PENDING WITH NODAL OFFICER |
|
27 |
Rishabh Sharma (10665) |
In reference to para 26/N, no such documents are uploaded. Kindly check and update the application on or before 06.02.2023. |
1/30/2023 |
APPLICATION OBJECTED |
|
28 |
Promoter |
Dear sir, earlier due to some technical error file was not uploaded. Now we are again uploading the complaints Status under the tab "Any other document(s) you wish to upload in support of application" User updated this details. |
1/31/2023 |
PENDING WITH NODAL OFFICER |
|
29 |
Rishabh Sharma (10665) |
In reference to para 23/N, kindly find the compliant status in the Other Documents tab. Application is now hereby submitted for kind perusal and further orders w.r.t. para 11-16/N on whether to deal with the said application or not or else we may process the Revocation of registration w.r.t. the special conditions mentioned in Form F issued for the period 20-11-2021 to 19-11-2022. |
2/1/2023 |
PENDING WITH JOINT REGISTRAR |
|
30 |
Arpit Sancheti (10683) |
Submitted for further orders pls. |
2/1/2023 |
PENDING WITH REGISTRAR |
|
31 |
Ramesh Sharma (9009) |
Submitted for perusal and decision, Sir. |
2/1/2023 |
PENDING WITH CHAIRMAN |
|
32 |
NIHAL CHAND GOEL (1) |
All the complaints must get settled/withdrawn before we can consider proceeding with this application, otherwise it will amount to accepting violation of our another condition that the extension must not cause prejudice to the rights of allotttees. Therefore, let us give the promoter a month's time to settle all the complaints at his level, failing which this application may be rejected. |
2/2/2023 |
PENDING WITH REGISTRAR |
|
33 |
Ramesh Sharma (9009) |
inform the promoter to comply with the directions of honourable chairman |
2/2/2023 |
PENDING WITH JOINT REGISTRAR |
|
34 |
Arpit Sancheti (10683) |
Comply as directed. |
2/2/2023 |
PENDING WITH NODAL OFFICER |
|
35 |
Rishabh Sharma (10665) |
In reference to para 32/N, comply with the directions on or before 03.03.2023. |
2/2/2023 |
APPLICATION OBJECTED |
|
36 |
Promoter |
Dear Sir, it is submitted that the person authorized by Pranay Infra Build P L, Mr. Neeraj Suwalka has met with an accident and hospitalized. This is the humble request from the kind authority to grant some more time to clear the pendency. Kindly accept our humble submission and oblige us. User updated this details. |
3/1/2023 |
PENDING WITH NODAL OFFICER |
|
37 |
Rishabh Sharma (10665) |
In reference to para 32/N, the promoter has requested some more time at para 36/N. Therefore, the application is submitted for your kind perusal and further orders, please. |
3/2/2023 |
PENDING WITH JOINT REGISTRAR |
|
38 |
Arpit Sancheti (10683) |
Submitted for further orders in reference to para 36/N. |
3/2/2023 |
PENDING WITH REGISTRAR |
|
39 |
Ramesh Sharma (9009) |
Ten days time is given to clear the pendencies. |
3/2/2023 |
PENDING WITH JOINT REGISTRAR |
|
40 |
Arpit Sancheti (10683) |
Comply as directed. |
3/2/2023 |
PENDING WITH NODAL OFFICER |
|
41 |
Rishabh Sharma (10665) |
comply with the earlier objections on or before 20.03.2023. |
3/8/2023 |
APPLICATION OBJECTED |
|
42 |
Promoter |
Dear Sir, Promoter humbly submits to the kind authority that there has been 8 complaints against us, 4 of which are dismissed, 2 complaints are sub-judice before the Hon’ble authority and we shall comply with the directions accordingly. Further the 1 complaint having no. RAJ-RERA-C-N-2020-3711, Hon’ble authority has directed the order for the possession which we shall comply once the project is completed. We are hereby attaching the complaints status for your kind pursual. Kindly accept our humble submission and oblige us. User updated this details. |
3/15/2023 |
PENDING WITH NODAL OFFICER |
|
43 |
Rishabh Sharma (10665) |
In reference to para 32/N, kindly peruse the promoter reply at para 42/N and the attachment related to the status of complaints against the promoter. Application is submitted for kind perusal and further orders regarding extension, please. |
3/16/2023 |
PENDING WITH JOINT REGISTRAR |
|
44 |
Arpit Sancheti (10683) |
Submitted for further orders in reference to para 42/N. |
3/16/2023 |
PENDING WITH REGISTRAR |
|
45 |
Ramesh Sharma (9009) |
Submitted for perusal and decision, Sir. |
3/16/2023 |
PENDING WITH CHAIRMAN |
|
46 |
NIHAL CHAND GOEL (1) |
Process for rejection as the promoter is not complying with the special conditions of the last extension granted. Issue notice. |
3/17/2023 |
PENDING WITH REGISTRAR |
|
47 |
Ramesh Sharma (9009) |
Comply with the directions of honourable chairman. |
3/17/2023 |
PENDING WITH JOINT REGISTRAR |
|
48 |
Arpit Sancheti (10683) |
Comply as directed. |
3/20/2023 |
PENDING WITH NODAL OFFICER |
|
49 |
Rishabh Sharma (10665) |
Reply w.r.t. the special conditions as directed by the Hon'ble Chairman by today. |
4/12/2023 |
APPLICATION OBJECTED |
|
50 |
Promoter |
Respected sir, the Promoter has amended the application for extension and is now requesting for a period till Aug 2023 which is approximately Four months from now. The humble Promoter begs the kind Authority to consider the revised submission and kindly accept the application. User updated this details. |
4/12/2023 |
PENDING WITH NODAL OFFICER |
|
51 |
Rishabh Sharma (10665) |
Kindly give the details/consent of allottees for seeking this extension. |
4/12/2023 |
APPLICATION OBJECTED |
|
52 |
Promoter |
Dear Sir, we have filled the details of all the allottees. Kindly accept our humble submission and oblige us. User updated this details. |
4/12/2023 |
PENDING WITH NODAL OFFICER |
|
53 |
Rishabh Sharma (10665) |
Promoter has submitted the said application for the extension in accordance with the Authority’s order dated 22.05.2020 i.e., giving the Exceptional and compelling circumstances and reasons along with the contact details of 178 allottees.
Therefore, application is submitted for kind perusal and decision to schedule the date of hearing so that the notices may be issued to the promoter and the allottees (as per contact details submitted by the promoter) regarding extension of registration beyond 1 year i.e. 31.08.2023 (9 Months 12 Days) w.r.t. the attached checklist.
|
4/13/2023 |
PENDING WITH JOINT REGISTRAR |
|
54 |
Ramesh Sharma (9009) |
Notice issued for hearing, put up on 18.04.2023 at 11 AM. |
4/13/2023 |
PENDING WITH NODAL OFFICER |
|
55 |
Rishabh Sharma (10665) |
In reference to the attached note sheet, application is submitted for kind perusal and approval of the extension while mentioning the special conditions in Form F as follows:
(i) The allottee Shri Chandra Prakash Suwalka or any other allottees of Block C seek transfer of his unit to Block A or , the promoter shall allow such transfer
(ii) The promoter shall prepare and provide by 30.04.2023, a detailed construction and development plan to achieve completion of all the remaining development works by 31.08.2023, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it;
(iii) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 31.08.2023;
(iv) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30.04.2023; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration;
(v) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and
(vi) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 30.04.2023.
|
4/18/2023 |
PENDING WITH JOINT REGISTRAR |
|
56 |
Arpit Sancheti (10683) |
Submitted for kind perusal and further orders in reference to para 55/N. |
4/18/2023 |
PENDING WITH REGISTRAR |
|
57 |
Ramesh Sharma (9009) |
Submitted for perusal and approval, Sir. |
4/18/2023 |
PENDING WITH CHAIRMAN |
|
58 |
NIHAL CHAND GOEL (1) |
Approved with special conditions as follows: (i) The allottee Shri Chandra Prakash Suwalka or any other allottee of Block C can seek transfer of his unit to Block A or B and the promoter shall allow such transfer; (ii) The promoter shall prepare and provide by 30.04.2023, a detailed construction and development plan to achieve completion of all the remaining development works by 31.08.2023, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it; (iii) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 31.08.2023; (iv) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30.04.2023; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; (v) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and (vi) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 30.04.2023. |
4/19/2023 |
Application Approved |
|