Project Details

Real Estate Project Detail


Promoter Details


General Information
Information Type Firm / Company / Associates Etc
Organization
Organization Name KISAAN PRIME ESTATE PRIVATE LIMITED Organization Type
Address Details
State Rajasthan District Jaipur
Tehsil Sanganer Village/ Town/ City JAIPUR
Plot / Khasra No 32 Ward No
Street/ Locality Sohan Nagar, Manayawas, Mansarovar Pin Code 302020
Organization Contact Details
Office Number 9928113308 Website URL

Partner / Director Details

Name Designation Photo
PHOOL CHAND SAINI DIRECTOR View Photo
DEVI NARAYAN SAINI DIRECTOR View Photo

Past Executed / Ongoing Project Experience In Last Five Years

Project Name Project Type Address Land Area(In Sq. meters) Number of Buildings/Plots Number of Apartments/Plots/Shops/etc. Original Proposed Date of Completion Actual Completion Date
Record Not Found

Past Executed / Ongoing Status of all Registered Projects of the Promoter in Rajasthan

Project Name Registration No. Type Status Estimated Completion Date Actual CompletionDate
ROYAL AANGAN BLOCK-A RAJ/P/2018/775 (22/06/2018) Plotted Development LAPSED 30/04/2019
ROYAL AANGAN BLOCK-D RAJ/P/2018/777 (22/06/2018) Plotted Development LAPSED 30/04/2019
ROYAL AANGAN BLOCK-D RAJ/P/2018/777 (22/06/2018) Plotted Development LAPSED 30/04/2019
GOKUL PRANGAN RAJ/P/2019/910 (15/03/2019) Plotted Development LAPSED 31/12/2020
HAPPY PRANGAN RAJ/P/2019/998 (13/05/2019) Plotted Development LAPSED 31/12/2020
ABHIMANYU RESIDENCY BLOCK-A RAJ/P/2020/1403 (26/11/2020) Plotted Development COMPLETED 30/06/2022 01/03/2021
THE PLEASURE GARDEN RAJ/P/2021/1445 (03/02/2021) Plotted Development COMPLETED 31/12/2022
THE PLEASURE GARDEN RAJ/P/2021/1445 (03/02/2021) Plotted Development COMPLETED 31/12/2022 18/02/2022
KISAAN GREEN RESIDENCY RAJ/P/2021/1573 (03/07/2021) Plotted Development COMPLETED 30/06/2023 18/02/2022
KISAAN GREEN RESIDENCY RAJ/P/2021/1573 (03/07/2021) Plotted Development COMPLETED 30/06/2023
KISAAN GREEN RESIDENCY RAJ/P/2021/1573 (03/07/2021) Plotted Development COMPLETED 30/06/2023
KASLI ENCLAVE BLOCK-A RAJ/P/2021/1774 (20/12/2021) Plotted Development LAPSED 30/06/2023
SHREE KRISHNAM RESIDENCY RAJ/P/2022/1920 (05/04/2022) Plotted Development COMPLETED 30/09/2023 13/07/2022

Project Details


Project Status :- New Project
Project Name SHREE KRISHNAM RESIDENCY Project Type Plotted Development
Estimated Commencement Date 4/1/2022 Estimated Finish Date 9/30/2023
Actual Commencement Date 4/1/2022 Litigation related to registering project No
Project Registration Certificate View
Land Usage -
Project Extension Details
No Records Found.
Land Details Of Registering Project
Plot No. / Khasra No. 156/381, 162, 162/382, 163, 428/161 Total Area Of Project (In sq. meters) 14900.86
Phase Area (In sq. meters) 14900.86 Fees to be paid to RAJ RERA In (INR) 149010.00
Open Area(In sq. meters) 7600.99 Number Of Apartments / Plots 77
Proposed But Not Sanctioned Number Of Apartments / Plots 0 Sanctioned Number Of Apartments / Plots 77
Total built up area / saleable area
Total built up area / saleable area (in sq. meters) 7299.87
LOCATION OF PROJECT
State Rajasthan District Jaipur
Tehsil Sanganer Village/ Town/ City HASAMPURA WAS BHANKROTA
Plot / Khasra No 156/381, 162, 162/382, 163, 428/161 Ward No
Street/ Locality Post Office
Pincode 302026
DETAIL OF SEPARATE BANK ACCOUNT AS PER SECTION 4(2)(1)(D) OF THE ACT
Bank Name ICICI BANK Branch Name JAIPUR RHB MANSAROVAR
IFSC Code ICIC0006776 Bank A/C Number 677605601049
Name Of Bank Account Holder KISAAN PRIME ESTATE PVT LTD Bank Address RAJ. HSG. BOARD, DIV. 10, AGARWAL FARM, MANSAROVAR, JAIPUR
Remark About Project
As per Township Policy 2010, 5 Plots (Plot No. 26, 43, 44, 48, 56) having Total area of 946.71 Sq. Mtrs equaling to 12.5% have been kept mortgage. These plots would be allotted after the internal development work is completed and development charges are deposited with Jaipur Development Authority. 2 The Total Open Area 7600.99 Square meters and the area related with Park 803.35 Sq. Mtr + S.W.M 50.00 Square meter + Mobile Tower area 20.00 Sq. Meter + Gas Line area 2083.87 + Road 4643.77 Sq. Meter 3. Since it is a plotted development project there is no parking details are required. 4. THE TOTAL AREA (IN HECT.) IN 90-A ORDER OF JDA DATED 06.12.2021 WAS 1.6 HECT. WHICH WAS NOT PROPER AND THE ORIGINAL AREA (IN HECT.) IS 1.49 WHICH IS MENTIONED IN THE AMENDED 90-A ORDER OF JDA DATED 22.03.2022. 5. Total 05 Plots which have been kept under mortgaged category have been released by the JDA vide letter no. JDA/DC/Zone-12/2022/D-2203 dated 05-08-2022.

PROJECT COST DETAIL

Sr. No Particular Estimated Total amount(in INR)
1 Land cost as per rule 5(1) 65373188.00
For the purposes of sub-clause (D) of clause (l) of sub-section (2) of section 4, the land cost shall be the cost incurred by the promoter whether as an outright purchase, lease charges etc. and includes-
Revenue or area share given to land owner in lieu of land under any kind of agreement such as Joint Venture, Joint Development etc, in case the Promoter is not the owner of the land.
Amount paid to land owner.
Incidental costs related to acquisition of land such as stamp duty, brokerage, settlement costs of litigation, premiums paid to government authorities related to land.
Interest on finance for purchase of land.
Litigation costs incurred for land acquisition.
Property and other taxes, fees, premiums paid.
2 Development cost as per rule 5(2) 40000000.00
For the purposes of sub-clause (D) of clause (l) of sub-section (2) of section 4, the construction cost shall be the total cost incurred by the promoter, towards the on-site expenditure for the physical development of the project and includes fees payable to the architects, consultants, project managers/staff including engineers, marketing agents etc. fees/charges/security deposit payable to various departments/authorities, Labor Cess, VAT which are incurred during the development of the project.

PROJECT RELATED COMMON AREA DETAILS - Parking Details

Type Total No. of Cars Total No. of Two Wheelers No. of Cycles Mechanical Car Parking No. of Visitors Parking No. of Parking Allocated
Location Car Two Wheelers Car Two Wheelers
Open Area 0 0 0 0 0 0 0 0
Stilt Floor 0 0 0 0 0 0 0 0
Basement 0 0 0 0 0 0 0 0
Any Other Floor 0 0 0 0 0 0 0 0

PROJECT COMMON AREA DETAILS - Development Work For Whole Project

Common Area And Facilities, Amenities Proposed Percentage Of Completion (if project is ongoing or completed) View
Water Supply No 0 Not Uploaded
Rain Water Harvesting/ Recharging Not Available 0 Not Uploaded
Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) Not Available 0 Not Uploaded
Electrification(Transformer, Solar Energy etc) Not Available 0 Not Uploaded
Fire Fighting Provision Not Applicable 0 Not Uploaded
Others Yes 0 view

PLOT DETAILS

Sanctioned units

Plot Area Plots Total Plots No. of plots Booked/Allotted/Sold
222.29 1 1 0
139.37 2 TO 7 6 0
92.96 8 TO 15, 18 TO 25, 27 TO 33, 36 TO 42, 50, 53, 54 33 0
159.78 16, 17 2 0
117.08 26 1 0
116.65 34, 35 2 0
101.60 43 1 0
153.72 44 1 0
183.50 45 1 0
190.34 46 1 0
191.02 47 1 0
256.25 48 1 0
165.88 49 1 0
194.99 51 1 0
192.22 52 1 0
175.48 55 1 0
318.06 56 1 0
6 S-1 TO S-21 21 0
Total : 77 0
Site Plan : View

Proposed but not Sanctioned units

Plot Area Plots Total Plots No. of Plots Booked/Allotted/Sold
No Record Found
Site Plan : View

Proposed Encumbrance Details


Bank/ Financier Loan (Rs.) Document
No Record Found
PROJECT RELATED - LEGAL DOCUMENT
Document Name Proposed Date View
Copy of the legal title report for project land Yes 01/04/2022 View
Detail of encumbrances for project Yes 01/04/2022 View
Signed Proforma of the allotment letter and agreement for sale for project (As per RAJ-RERA Rules and FORM G) Yes 01/04/2022 View
Declaration in FORM B (As per RAJ-RERA Rules) Yes 01/04/2022 View
PROJECT RELATED - APPROVAL DOCUMENT
Document Name Proposed Date View
Copy of layout approval(in Case of plotted) and Building Plan Approval(GH/COMM/COMM+GH) Yes 01/04/2022 View
NOC For Environment Not Applicable 01/04/2022 Not Uploaded
NOC for Fire Not Applicable 01/04/2022 Not Uploaded
Water supply permission Not Available 01/04/2022 Not Uploaded
NOC from Airport Authority of India Not Applicable 01/04/2022 Not Uploaded
Other approvals as may be required and obtained for the project Yes 01/04/2022 View
PROJECT RELATED - COMMON DOCUMENT
Document Name Proposed Date View
Location with Demarcation (Map/Plan) Yes 01/04/2022 View
Copy Of Approved Site Plan Yes 01/04/2022 View
Copy Of Approved Site Plan Yes 23/09/2024 View

OTHER PROMOTERS

Other Promoter Name Email Contact Number Address
No Record Found