II. Number and type of apartments booked ( January to March, 2025 )
Building Name : Park View Apartments By Soni's
Apartment Type
Block Number
Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters)
Area of Exclusive Balcony and Verandah
Total Number of Sanctioned Apartments
Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter
Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2 BHK Flat No. 105, 205, 305, 405, 505, 605
Block-1
82.25
16.04
6
0
2 BHK Flat No. 106, 206, 306, 406, 506, 606
Block-1
70.78
11.94
6
0
3 BHK Flat No. 101, 201, 301, 401, 501, 601
Block-1
103.58
10.79
6
0
3 BHK Flat No. 102, 202, 302, 402, 502, 602
Block-1
103.25
10.78
6
0
3 BHK Flat No. 103, 203, 303, 403, 503, 603
Block-1
94.05
16.85
6
0
3 BHK Flat No. 104, 204, 304, 404, 504, 604
Block-1
92.13
16.44
6
0
Store
Block-1
298.00
0.00
1
0
Total
37
0
0
III. Number of parkings allotted
Type
Total No. of Car parking
Total No. of Two Wheeler parking
Total No. of cycle parking
Total No of Mechanical Car Parking
Total No. of parking allocated at the time of registration or by the end of last quarter
Cumulative No. of parking allocated by the end of current quarter
Location
Car
Two Wheelers
Car
Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( January to March, 2025 )
TABLE - A
Building Name: Park View Apartments By Soni's
S.No.
Task/Activity
Percentage of work done
In Last Quarter
In Current Quarter
1
Excavation
100
100.00
2
1
Number of Basement(s) and Plinth
100
100.00
3
1
Number of Stilt Floor
100
100.00
4
6
Number of Slabs of Super Structure
0
15.00
5
Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises
0
5.00
6
Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises
0
5.00
7
Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks
0
0.00
8
The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing
0
0.00
9
Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment,
Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be required to obtain Occupation/Completion Certificate
0
0.00
TABLE - B
Internal and External Development Works for the entire registered Phase/Project
S.No.
Common areas and Facilities/Amenities
Proposed Yes/No
Percentage of work done
Details if any
By the end of Last Quarter
By the end of Current Quarter
1
Internal Roads & Footpaths
0
0
2
Water Supply
0
0
3
Sewerage (chamber, lines, Septic Tank STP)
0
0
4
Storm Water Drainss
0
0
5
Landscaping & Tree Planting
0
0
6
Street Lighting
0
0
7
Community Building
0
0
8
Treatment and disposal of sewage and sullage water
0
0
9
Solid Waste management & Disposal
0
0
10
Water conservation, Rain water harvesting
0
0
11
Energy management
0
0
12
Fire protection and fire safety requirements
0
0
13
Electrical meter room, sub-station, receiving station
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement
for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
Milestones
Committed date of achievement
Date on which achieved or likely to be achieved
Excavation
15/09/2024
15/09/2024
Plinth
30/10/2024
30/10/2024
(B+S+G+5 ) Slabs of Super Structure
30/06/2025
30/06/2025
Internal walls, Flats/Premises, Doors, Internal and External Plaster, Windows to Floorings each within of the flat, premises
30/10/2025
30/10/2025
Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises.
30/11/2025
30/11/2025
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks
30/11/2025
30/11/2025
The external plumbing and external plaster, elevation. Completion of terraces with waterproofing of the Building/Wing.
30/12/2025
30/12/2025
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, compliance to conditions of environment/CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation/Completion Certificate
30/12/2025
30/12/2025
Final Completion and Possession (Estimated Finish Date)
31/05/2026
31/05/2026
V. Project Common Area Details- Development Work For Whole Project
S. No.
Common Area And Facilities, Amenities
Proposed
Percentage Of Completion (%)
Drawings uploaded in online Project details or not
If no, Planned date of uploading of these drawings
1
Water Supply
0
No
2
Rain Water Harvesting/ Recharging
0
Yes
No
3
Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
0
Yes
No
4
Electrification(Transformer, Solar Energy etc)
0
Yes
No
5
Fire Fighting Provision
0
Yes
No
6
Others
0
Yes
No
VI. Status of Approvals
A
Noc's/Permission
Present Status
1
NOC for Environment
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
Built up Area is less than 20000 Sq. Mtr. , Environment NOC is Not Applicable
2
NOC for Fire
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
01/05/2026
3
Water supply permission
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
No separate permission is required as Water Supply is done through Borewell
4
NOC from Airport Authority of India
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
Not Applicable, As per Color Coded Zoning Map
5
Other approval(s) if any,required for the Project
Approval for/of
• Has the NOC/Permission been uploaded on RERA web portal?
• Planned date of uploading NOC/Permission
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
B.
Revision of Building Plans
1
Date of approval of latest Building Plans already uploaded on RERA web portal
05/06/2024
2
Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
Yes
No
• Date of approval of revised building plans
• Has already submitted to RERA for uploading these revised building plans?
Yes
No
» (If Yes)Date of application
» (If No)Planned date of application
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and
(ii) construction of the Real Estate Project.
Has the insurance been obtained?
Yes
No
• Planned date of Insurance
01/05/2026
VIII. Details of Real Estate Agents (if any) engaged for the Project
Has any real estate agents been engaged for the Project?
Yes
No
IX. Miscellaneous
1. Is there any change in promoter profile which is not yet updated in online promoter profile?
Yes
No
2. Is there any change in project details which is not yet updated in online project profile?
Yes
No
3. Has the Completion Certificate been obtained?
Yes
No
•
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
Yes
No
4. Has the Occupancy Certificate also been obtained?
Yes
No
Allottee Details
Building : Park View Apartments By Soni's (Apartment : 3 BHK Flat No. 102, 202, 302, 402, 502, 602, Block : Block-1, Carpet Area : 103.25 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 502
Unsold
2 .
Flat No. 102
Unsold
3 .
Flat No. 202
Unsold
4 .
Flat No. 602
Unsold
5 .
Flat No. 402
Unsold
6 .
Flat No. 302
Unsold
Building : Park View Apartments By Soni's (Apartment : 2 BHK Flat No. 106, 206, 306, 406, 506, 606, Block : Block-1, Carpet Area : 70.78 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 506
Unsold
2 .
Flat No. 606
Unsold
3 .
Flat No. 306
Unsold
4 .
Flat No. 206
Unsold
5 .
Flat No. 406
Unsold
6 .
Flat No. 106
Unsold
Building : Park View Apartments By Soni's (Apartment : 2 BHK Flat No. 105, 205, 305, 405, 505, 605, Block : Block-1, Carpet Area : 82.25 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 505
Unsold
2 .
Flat No. 205
Unsold
3 .
Flat No. 105
Unsold
4 .
Flat No. 605
Unsold
5 .
Flat No. 405
Unsold
6 .
Flat No. 305
Unsold
Building : Park View Apartments By Soni's (Apartment : 3 BHK Flat No. 104, 204, 304, 404, 504, 604, Block : Block-1, Carpet Area : 92.13 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 104
Unsold
2 .
Flat No. 304
Unsold
3 .
Flat No. 404
Unsold
4 .
Flat No. 204
Unsold
5 .
Flat No. 604
Unsold
6 .
Flat No. 504
Unsold
Building : Park View Apartments By Soni's (Apartment : 3 BHK Flat No. 103, 203, 303, 403, 503, 603, Block : Block-1, Carpet Area : 94.05 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 303
Unsold
2 .
Flat No. 203
Unsold
3 .
Flat No. 103
Unsold
4 .
Flat No. 403
Unsold
5 .
Flat No. 603
Unsold
6 .
Flat No. 503
Unsold
Building : Park View Apartments By Soni's (Apartment : 3 BHK Flat No. 101, 201, 301, 401, 501, 601, Block : Block-1, Carpet Area : 103.58 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Flat No. 501
Unsold
2 .
Flat No. 301
Unsold
3 .
Flat No. 201
Unsold
4 .
Flat No. 101
Unsold
5 .
Flat No. 601
Unsold
6 .
Flat No. 401
Unsold
Building : Park View Apartments By Soni's (Apartment : Store, Block : Block-1, Carpet Area : 298.00 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
Store
Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from.
I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other
legal purposes this undertaking amy serve.