Quarterly Progress Report Summary Details October to December, 2022

Quarterly Progress Report Summary Details October to December, 2022

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2023-16661 (30/01/2023)
Name of the Registered project Ashiana Tarang Phase III Registration No. of the Project RAJ/P/2020/1407
Name of the Promoter Ashiana Housing Limited Name of other Promoter(s) None
Project Address Khasra No./ Plot No.779, 780, 781, 782, 783, 925/829, 927/844, 929/828 , Village- Milakpur Gurjar , Baba Mohan Ram Kholi Marg , Alwar - 301019 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 96
Total Area of Project(In sq. meters) 48,478.88 Phase Area (In sq. meters) 3,284.00
Registration certificate is valid upto 31-07-2024 Registration extended upto Not Applicable
II. Number and type of apartments booked ( October to December, 2022 )
Building Name : B 9 (Block E as per sanction plan)
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2 BHK + 2 Toilets - Magnolia-1 (Corner) 1 70.48 9.76 24 11
2 BHK + 2 Toilets - Magnolia-2 (Middle) 1 68.35 10.37 48 21
3 BHK + 2 Toilets - Lavender-1 1 86.83 10.72 24 14
Total 96 46 60
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( October to December, 2022 )

TABLE - A

Building Name: B 9 (Block E as per sanction plan)
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 0 100.00
3 0 Number of Stilt Floor 100 100.00
4 13 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 56 70.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 3 12.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 100 100.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 55 69.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 8.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 15 15
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 100 100
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 25
13 Electrical meter room, sub-station, receiving station 100 100
Form R1: Date of issue
19/01/2023
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( October to December, 2022 )

TABLE - A

Building Name : B 9 (Block E as per sanction plan)
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 133,819,394.00 133,819,394.40
2 Cost incurred against the estimated cost 91,929,728.00 103,349,216.00
3 Work done (as Percentage of the estimated cost) % 69 77.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 41,889,667.00 30,470,178.40
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 23,682,182.00 23,682,182.00
2 Cost incurred against the estimated cost 12,877,446.00 12,877,446.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 54.00 54.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 10,804,736.00 10,804,736.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
20/01/2023
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( October to December, 2022 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 45,031,663.00 45,031,663.00 45,031,663.00
B. Development Cost/Cost of Construction 183,621,732.00 155,949,288.00 168,999,553.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 200,980,951.00 214,031,216.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 81,810,023.00 97,558,023.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 119,170,928.00 116,473,193.00
Form R3: Date of issue
24/01/2023
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 23
2 Rain Water Harvesting/ Recharging 33
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 21
4 Electrification(Transformer, Solar Energy etc) 23
5 Fire Fighting Provision 35
6 Others 29
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 08/04/2022
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/12/2023

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : B 9 (Block E as per sanction plan) (Apartment : 3 BHK + 2 Toilets - Lavender-1, Block : 1, Carpet Area : 86.83 sq. meters) Number Of Apartments: 24,Booked: 24
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . L1-464 Sold Mrs. Sarika Robby
2 . L1-864 Sold Mr. Swadeep Singh
3 . L1-1264 Sold Mrs. Sangeeta Mahendro
4 . L1-158 Sold Mrs. Priti Yadav
5 . L1-558 Unsold
6 . L1-958 Sold Mr. Alok Kumar
7 . L1-164 Sold Mr. Gyan Prakash Pandey
8 . L1-564 Sold Ms. Vandana Anand
9 . L1-964 Sold Mr. Vikas Sharma
10 . L1-258 Unsold
11 . L1-658 Sold Mrs. Shobha Ringe
12 . L1-1058 Sold Mrs. Sangya Ranjan
13 . L1-264 Sold Mrs. Manisha
14 . L1-664 Sold Ms. Chanchal Sharma
15 . L1-1064 Sold Mrs. Kum Kum Gupta
16 . L1-358 Unsold
17 . L1-758 Sold Mr. Nagendra Singh
18 . L1-1158 Sold Mr. Rohit Singh
19 . L1-364 Sold Mrs. Sapna Verma
20 . L1-764 Sold Mr. Chandan Mishra
21 . L1-1164 Sold Mr. Sanjay Kumar Vatsalya
22 . L1-458 Unsold
23 . L1-858 Sold Mr. Suraj Kumar Singh
24 . L1-1258 Sold Mr. Amit Kumar Jadiya
Building : B 9 (Block E as per sanction plan) (Apartment : 2 BHK + 2 Toilets - Magnolia-1 (Corner), Block : 1, Carpet Area : 70.48 sq. meters) Number Of Apartments: 24,Booked: 21
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . M1-463 Sold Mr. Bikram Verma
2 . M1-863 Sold Mr. Chandan Mishra
3 . M1-1263 Sold Mr. Ajai Kumar Shukla
4 . M1-157 Unsold
5 . M1-557 Unsold
6 . M1-957 Unsold
7 . M1-163 Sold Mr. Pranat Dubey
8 . M1-563 Sold Mr. Shakti Kumar
9 . M1-963 Sold Mr. Rajnish Shrivastav
10 . M1-257 Unsold
11 . M1-657 Sold Mrs. Manoj Kumari
12 . M1-1057 Unsold
13 . M1-263 Sold Mr. Pradeep Kumar Sharma
14 . M1-663 Sold Mr. Abhay Singh
15 . M1-1063 Unsold
16 . M1-357 Sold Mr. Keshav Somani
17 . M1-757 Sold Mr. Himanshu Kumar Pandey
18 . M1-1157 Sold Mrs. Neha Deshmukh
19 . M1-363 Sold Mr. Sandeep Yadav
20 . M1-763 Sold Mrs. Megha Jajoriya
21 . M1-1163 Sold Mr. Vishal Bangia
22 . M1-457 Unsold
23 . M1-857 Unsold
24 . M1-1257 Unsold
Building : B 9 (Block E as per sanction plan) (Apartment : 2 BHK + 2 Toilets - Magnolia-2 (Middle), Block : 1, Carpet Area : 68.35 sq. meters) Number Of Apartments: 48,Booked: 33
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . M2-262 Sold Mrs. Shipra Choudhary
2 . M2-462 Sold Mr. Ranveer Singh Rathore
3 . M2-662 Sold Mr. Manish kumar
4 . M2-862 Sold Ms. Payal Jain
5 . M2-1062 Sold Mr. Rahul
6 . M2-1262 Sold Mr. Paramhans Patel
7 . M2-159 Unsold
8 . M2-359 Unsold
9 . M2-559 Unsold
10 . M2-759 Sold Mr. Nitin Ahuja
11 . M2-959 Unsold
12 . M2-1159 Unsold
13 . M2-160 Unsold
14 . M2-360 Sold Mr. Narendra Kumar
15 . M2-560 Sold Mrs. Kalpana Devi
16 . M2-760 Sold Ms. Tanya Singh
17 . M2-960 Sold Mr. Pramod Kumar Singh
18 . M2-1160 Sold Ms. Priyanka Nagar
19 . M2-161 Unsold
20 . M2-361 Unsold
21 . M2-561 Unsold
22 . M2-761 Unsold
23 . M2-961 Unsold
24 . M2-1161 Unsold
25 . M2-162 Sold Mr. Jitendra Tanwar
26 . M2-362 Sold Mr. Devendra Singh Mawal
27 . M2-562 Sold Mr. Rahul Aggarwal
28 . M2-762 Sold Mr. Shakti Kumar
29 . M2-962 Sold Mr. Vivek Kumar Chahar
30 . M2-1162 Sold Mr. Nitya Nand Pandey
31 . M2-259 Unsold
32 . M2-459 Sold Mr. Manoj Mangal
33 . M2-659 Unsold
34 . M2-859 Unsold
35 . M2-1059 Unsold
36 . M2-1259 Unsold
37 . M2-260 Unsold
38 . M2-460 Sold Mr. Hitendra Dhaka
39 . M2-660 Sold Mr. Gaurav Jain
40 . M2-860 Sold Mr. Barun Kumar Prajapati
41 . M2-1060 Sold Mr. Pavan Kumar
42 . M2-1260 Sold Mrs. Pooja Tanwar
43 . M2-261 Unsold
44 . M2-461 Unsold
45 . M2-661 Sold Mrs. Nikita Lamoria
46 . M2-861 Unsold
47 . M2-1061 Unsold
48 . M2-1261 Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) The QPR is accepted subject to verification. 6/23/2023 Application Approved