Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2024-1299 (6/29/2024)
Project Name JANKI ROYALE Promoter Name RIDHI SIDHI PRIME ESTATE LLP
Project Registration No. RAJ/P/2022/1949 Project Type Group Housing
Estimated Finish Date (in online form) 30-06-2024 Project Registration Valid till
(as per registration certificate)
6/30/2024 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 6/30/2025
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 9/21/2021
Permission/Approval of Building Plan Valid Till 9/20/2028 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
The delay is mainly due to pending finishing works and final touch-ups, which have temporarily affected the overall progress of the Project. The Project is near completion.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 3,86,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 3,84,00,000.00
Form R3
Total Estimated Land Cost ₹ 5,34,80,016.00
Total Cost Incurred on Land ₹ 10,67,056.00
Total Estimated Development Cost ₹ 4,50,27,007.00
Total Cost Incurred on Development ₹ 4,50,57,127.00
Other Documents
Explanatory Note View
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,6/30/2025 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).

Registered Phase Area

Online Phase Area
501.68
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
501.68 ₹ 3,770.00 ₹ 1,255.00 ₹ 2,509.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
CA Akshita Agarwal 9358812008 akshita@rngca.com
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Project extension fees Rs.1260/- Standard fees Rs.2510/- Total Fees Rs.3770/- Deposited by RERA Transaction No.3423 Dated 29.06.2024 for one year extension phase Area 501.68 Sq Mt 7/1/2024 PENDING WITH DEPUTY REGISTRAR
2 Puneet Kapoor (10671) Dear Applicant, Following details need to be addressed in your Online application:- 1.)Clarify and Justify as how so far the “Total Cost Incurred on Land” is showing so less as 2 % wherein on other side Total Cost Incurred on Development is showing in the application as 100.07 %:-How come there is so much difference between Total Cost Incurred on Land and Total Cost Incurred on Development; 2.)In tab of “Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date” nothing is apprised by you. Comply with the same by on or before 10.07.2024 7/3/2024 APPLICATION OBJECTED
3 R.S. Kulhari (9009) The promoter is granted 15 days time to rectify the deficiencies failing which the application shall be considered for rejection. 11/6/2024 PENDING WITH NODAL OFFICER
4 Jitendra Tripathi (10665) Pls find the show cause notice under section 6 and comply with the objections on or before 25.11.2024, or appear for a hearing on 26.11.2024 at 11.00 AM. Otherwise, the application can be rejected without any notice. 11/8/2024 APPLICATION OBJECTED
5 Promoter Respected Sir, 1. In the current project, a joint development agreement was executed between the landowner and the promoter. Up until the quarter considered in this application, only some payment was made to the landowner in line with the agreement's terms. Following that quarter, some more amount was paid to the landowner, and this payment has been included in the incurred costs. 2. In tab of “Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date” is provided and the Explanatory Note has also been uploaded under tab of "Any other document(s) you wish to upload in support of application" User updated this details. 11/13/2024 PENDING WITH NODAL OFFICER
6 Jitendra Tripathi (10665) Application is submitted for kind perusal and decision regarding extension of registration upto 30-06-2025 (12 Months) w.r.t. attached checklist. 11/19/2024 PENDING WITH JOINT REGISTRAR
7 R.S. Kulhari (9009) Submitted for kind perusal and approval, Madam. 11/21/2024 PENDING WITH CHAIRMAN
8 Chairman Rajasthan (1) approved 11/22/2024 Application Approved