Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2024-1232 (2/5/2024)
Project Name RANGOLI AASHIYANA Promoter Name RANGOLI AASHIYANA
Project Registration No. RAJ/P/2019/974 Project Type Group Housing
Estimated Finish Date (in online form) 13-03-2022 Project Registration Valid till
(as per registration certificate)
3/13/2022 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 3/13/2025
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 4/8/2019
Permission/Approval of Building Plan Valid Till 4/8/2024 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
PDF ATTACHED
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
In case of extension beyond one year (on grounds other than force majeure/corona pandemic)
State clearly the exceptional and compelling circumstances and reasons due to which the project could not be completed even with in the extended period of one year PDF ATTACHED View
RWA Constituted or not
Total no. of units 450
No.of units sold booked/alloted/sold as per RC/latest QPR 310
No.of units sold booked/alloted/sold till date 310
Number of allottees, if any, who have consented or have no objection to the prposed extension being granted 0 View
No.of allottees, who need to be given a notice by the Authority to ascertain if they have any objection to the proposed extension being granted 310
Form R2
Estimated Construction Cost (Table A+B) ₹ 45,00,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 34,17,54,975.00
Form R3
Total Estimated Land Cost ₹ 12,00,00,000.00
Total Cost Incurred on Land ₹ 5,48,34,746.00
Total Estimated Development Cost ₹ 45,00,00,000.00
Total Cost Incurred on Development ₹ 34,69,58,653.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,3/13/2025 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 4/8/2024; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 3/13/2025 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
8570.07
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
8570.07 ₹ 1,28,560.00 ₹ 42,851.00 ₹ 85,701.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
RASBIHARI SHARMA 9166875955 rangoliaashiyana@gmail.com
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Project extension fees Rs.42855/- And Standard fees Rs.85705/- Total Fees Rs.128560/- Deposited by RERA Transaction No.490 Dated 05.02.2024 For project extension. 2/6/2024 PENDING WITH NODAL OFFICER
2 Rishabh Sharma (10665) 1. What is the reason for the extension of 12 months18 days, instead of 12 months, why are 18 more days required; 2. Kindly update the validity of building plans w.r.t. the UDH order dated 29.09.2023; 3. Select the particular of "Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic" tab as YES instead of NO, and accordingly update the exceptional and compelling circumstances for the seeking extension with the details construction and development plan along with the contact/consent details of 100% allottees. Comply with the directions on or before 13.02.2024. 2/6/2024 APPLICATION OBJECTED
3 Promoter Sir, 1. We have corrected the date of extension being sought upto. 2. We have taken validity of building plans w.r.t. the UDH order dated 29.09.2023. 3. Selected the particular of "Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic" tab as YES instead of NO and updated the reasons along with the contact details of 100% allottees. Kindly Accept our humble submission and oblige us. User updated this details. 2/20/2024 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) There are still a few pendnecies to the said extension application 1. Correct the validity of building plans for 5 years instead of the 6 years; 2. Remove the Addhar No. of all the allottees from the address column; 3. As per the uploaded development plan if all the work is under process and even the structure will be complete on 30.09.2024, then how the project is approx. 76% completed as per Form R2 and R3. Kindly upload a detailed development plan specifying the work completed and in progress. Comply with the directions on or before 06.03.2024. 2/28/2024 APPLICATION OBJECTED
5 Promoter Sir, 1. As directed, we have changed validity of building plans for 5 years instead of the 6 years. 2. Aadhar No. of all the allottees from the address column has been removed. 3. We have now uploaded detailed development plan. Kindly accept our humble submission and oblige us. User updated this details. 3/7/2024 PENDING WITH NODAL OFFICER
6 Rishabh Sharma (10665) Promoter has submitted the said application for the extension in accordance with the Authority’s order dated 22.05.2020 i.e., giving the Exceptional and compelling circumstances and reasons and the contact details of 310 allottees (Postal address). Therefore, application is submitted for kind perusal and decision to schedule the date of hearing so that the notices may be issued to the promoter and the allottees (as per contact details submitted by the promoter) regarding extension of registration beyond 1 year i.e. 13-03-2025 (12 months) w.r.t.the attached checklist. 3/20/2024 PENDING WITH JOINT REGISTRAR
7 Ramesh Sharma (9009) Submitted for fixing the date and time of hearing, madam 3/22/2024 PENDING WITH CHAIRMAN
8 Chairman Rajasthan (1) 16.4.24 at 11.30 am 3/22/2024 PENDING WITH REGISTRAR
9 Ramesh Sharma (9009) Notices issued, put up on date of hearing. Also send notice to the promoter and allottees via speed post. 3/22/2024 PENDING WITH NODAL OFFICER
10 Rishabh Sharma (10665) Application is submitted for kind perusal and approval of the extension of registration w.r.t. the attached note sheet, while mentioning the special conditions in Form F, as follows: (i) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 13-03-2025; (ii) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30-04-2024; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; (iii) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and (iv) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan submitted by the promoter. 4/16/2024 PENDING WITH JOINT REGISTRAR
11 Ramesh Sharma (9009) Submitted for approval,madam. 4/16/2024 PENDING WITH CHAIRMAN
12 Chairman Rajasthan (1) extension granted with the following conditions: (i) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 13-03-2025; (ii) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30-04-2024; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; (iii) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and (iv) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan submitted by the promoter. 4/18/2024 Application Approved