II. Number and type of apartments booked ( October to December, 2023 )
Building Name : Udhyan Apartment
Apartment Type
Block Number
Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters)
Area of Exclusive Balcony and Verandah
Total Number of Sanctioned Apartments
Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter
Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
3 BHK (HIG)
Block O
107.05
12.80
36
0
3 BHK (HIG)
Block P
107.05
12.80
36
0
3 BHK (HIG)
Block Q
107.05
12.80
36
0
3 BHK (HIG)
Block R
107.05
12.80
36
0
3 BHK (HIG)
Block S
107.05
12.80
36
0
3 BHK (MIG-B)
Block L
84.83
10.89
36
0
3 BHK (MIG-B)
Block M
84.83
10.89
36
0
3 BHK (MIG-B)
Block N
84.83
10.86
36
0
Total
288
0
0
III. Number of parkings allotted
Type
Total No. of Car parking
Total No. of Two Wheeler parking
Total No. of cycle parking
Total No of Mechanical Car Parking
Total No. of parking allocated at the time of registration or by the end of last quarter
Cumulative No. of parking allocated by the end of current quarter
Location
Car
Two Wheelers
Car
Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( October to December, 2023 )
TABLE - A
Building Name: Udhyan Apartment
S.No.
Task/Activity
Percentage of work done
In Last Quarter
In Current Quarter
1
Excavation
0
0.00
2
0
Number of Basement(s) and Plinth
0
0.00
3
0
Number of Stilt Floor
0
0.00
4
1
Number of Slabs of Super Structure
0
0.00
5
Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises
0
0.00
6
Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises
0
0.00
7
Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks
0
0.00
8
The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing
0
0.00
9
Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment,
Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be required to obtain Occupation/Completion Certificate
0
0.00
TABLE - B
Internal and External Development Works for the entire registered Phase/Project
S.No.
Common areas and Facilities/Amenities
Proposed Yes/No
Percentage of work done
Details if any
By the end of Last Quarter
By the end of Current Quarter
1
Internal Roads & Footpaths
0
0
2
Water Supply
0
0
3
Sewerage (chamber, lines, Septic Tank STP)
0
0
4
Storm Water Drainss
0
0
5
Landscaping & Tree Planting
0
0
6
Street Lighting
0
0
7
Community Building
0
0
8
Treatment and disposal of sewage and sullage water
0
0
9
Solid Waste management & Disposal
0
0
10
Water conservation, Rain water harvesting
0
0
11
Energy management
0
0
12
Fire protection and fire safety requirements
0
0
13
Electrical meter room, sub-station, receiving station
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement
for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No.
Common Area And Facilities, Amenities
Proposed
Percentage Of Completion (%)
Drawings uploaded in online Project details or not
If no, Planned date of uploading of these drawings
1
Water Supply
0
No
2
Rain Water Harvesting/ Recharging
0
Yes
No
3
Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
0
Yes
No
31/03/2024
4
Electrification(Transformer, Solar Energy etc)
0
Yes
No
5
Fire Fighting Provision
0
Yes
No
6
Others
0
Yes
No
VI. Status of Approvals
A
Noc's/Permission
Present Status
1
NOC for Environment
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
2
NOC for Fire
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
3
Water supply permission
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
No seprate permission is required as water supply is done through borewell
4
NOC from Airport Authority of India
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
5
Other approval(s) if any,required for the Project
Approval for/of
• Has the NOC/Permission been uploaded on RERA web portal?
• Planned date of uploading NOC/Permission
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
B.
Revision of Building Plans
1
Date of approval of latest Building Plans already uploaded on RERA web portal
29/12/2014
2
Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
Yes
No
• Date of approval of revised building plans
• Has already submitted to RERA for uploading these revised building plans?
Yes
No
» (If Yes)Date of application
» (If No)Planned date of application
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and
(ii) construction of the Real Estate Project.
Has the insurance been obtained?
Yes
No
• Planned date of Insurance
31/03/2024
VIII. Details of Real Estate Agents (if any) engaged for the Project
Has any real estate agents been engaged for the Project?
Yes
No
IX. Miscellaneous
1. Is there any change in promoter profile which is not yet updated in online promoter profile?
Yes
No
2. Is there any change in project details which is not yet updated in online project profile?
Yes
No
3. Has the Completion Certificate been obtained?
Yes
No
•
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
Yes
No
4. Has the Occupancy Certificate also been obtained?
Yes
No
Allottee Details
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block L, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/L-401
Unsold
2 .
21 E/L-701
Unsold
3 .
21 E/L-303
Unsold
4 .
21 E/L-203
Unsold
5 .
21 E/L-801
Unsold
6 .
21 E/L-704
Unsold
7 .
21 E/L-101
Unsold
8 .
21 E/L-604
Unsold
9 .
21 E/L-904
Unsold
10 .
21 E/L-902
Unsold
11 .
21 E/L-103
Unsold
12 .
21 E/L-403
Unsold
13 .
21 E/L-503
Unsold
14 .
21 E/L-802
Unsold
15 .
21 E/L-502
Unsold
16 .
21 E/L-402
Unsold
17 .
21 E/L-202
Unsold
18 .
21 E/L-102
Unsold
19 .
21 E/L-903
Unsold
20 .
21 E/L-304
Unsold
21 .
21 E/L-404
Unsold
22 .
21 E/L-603
Unsold
23 .
21 E/L-804
Unsold
24 .
21 E/L-601
Unsold
25 .
21 E/L-501
Unsold
26 .
21 E/L-301
Unsold
27 .
21 E/L-504
Unsold
28 .
21 E/L-201
Unsold
29 .
21 E/L-204
Unsold
30 .
21 E/L-104
Unsold
31 .
21 E/L-803
Unsold
32 .
21 E/L-703
Unsold
33 .
21 E/L-302
Unsold
34 .
21 E/L-602
Unsold
35 .
21 E/L-702
Unsold
36 .
21 E/L-901
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block N, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/N-102
Unsold
2 .
21 E/N-402
Unsold
3 .
21 E/N-104
Unsold
4 .
21 E/N-903
Unsold
5 .
21 E/N-502
Unsold
6 .
21 E/N-701
Unsold
7 .
21 E/N-703
Unsold
8 .
21 E/N-603
Unsold
9 .
21 E/N-803
Unsold
10 .
21 E/N-503
Unsold
11 .
21 E/N-203
Unsold
12 .
21 E/N-103
Unsold
13 .
21 E/N-802
Unsold
14 .
21 E/N-702
Unsold
15 .
21 E/N-504
Unsold
16 .
21 E/N-401
Unsold
17 .
21 E/N-804
Unsold
18 .
21 E/N-301
Unsold
19 .
21 E/N-904
Unsold
20 .
21 E/N-101
Unsold
21 .
21 E/N-204
Unsold
22 .
21 E/N-302
Unsold
23 .
21 E/N-202
Unsold
24 .
21 E/N-901
Unsold
25 .
21 E/N-801
Unsold
26 .
21 E/N-201
Unsold
27 .
21 E/N-704
Unsold
28 .
21 E/N-501
Unsold
29 .
21 E/N-604
Unsold
30 .
21 E/N-601
Unsold
31 .
21 E/N-404
Unsold
32 .
21 E/N-902
Unsold
33 .
21 E/N-303
Unsold
34 .
21 E/N-403
Unsold
35 .
21 E/N-602
Unsold
36 .
21 E/N-304
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block O, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/O-504
Unsold
2 .
21 E/O-201
Unsold
3 .
21 E/O-804
Unsold
4 .
21 E/O-101
Unsold
5 .
21 E/O-702
Unsold
6 .
21 E/O-203
Unsold
7 .
21 E/O-904
Unsold
8 .
21 E/O-204
Unsold
9 .
21 E/O-303
Unsold
10 .
21 E/O-402
Unsold
11 .
21 E/O-103
Unsold
12 .
21 E/O-802
Unsold
13 .
21 E/O-602
Unsold
14 .
21 E/O-502
Unsold
15 .
21 E/O-801
Unsold
16 .
21 E/O-202
Unsold
17 .
21 E/O-302
Unsold
18 .
21 E/O-501
Unsold
19 .
21 E/O-903
Unsold
20 .
21 E/O-803
Unsold
21 .
21 E/O-603
Unsold
22 .
21 E/O-503
Unsold
23 .
21 E/O-704
Unsold
24 .
21 E/O-301
Unsold
25 .
21 E/O-604
Unsold
26 .
21 E/O-401
Unsold
27 .
21 E/O-404
Unsold
28 .
21 E/O-304
Unsold
29 .
21 E/O-703
Unsold
30 .
21 E/O-902
Unsold
31 .
21 E/O-104
Unsold
32 .
21 E/O-403
Unsold
33 .
21 E/O-102
Unsold
34 .
21 E/O-901
Unsold
35 .
21 E/O-701
Unsold
36 .
21 E/O-601
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block Q, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/Q-603
Unsold
2 .
21 E/Q-903
Unsold
3 .
21 E/Q-801
Unsold
4 .
21 E/Q-202
Unsold
5 .
21 E/Q-104
Unsold
6 .
21 E/Q-303
Unsold
7 .
21 E/Q-302
Unsold
8 .
21 E/Q-501
Unsold
9 .
21 E/Q-102
Unsold
10 .
21 E/Q-901
Unsold
11 .
21 E/Q-701
Unsold
12 .
21 E/Q-704
Unsold
13 .
21 E/Q-301
Unsold
14 .
21 E/Q-604
Unsold
15 .
21 E/Q-401
Unsold
16 .
21 E/Q-404
Unsold
17 .
21 E/Q-902
Unsold
18 .
21 E/Q-802
Unsold
19 .
21 E/Q-602
Unsold
20 .
21 E/Q-803
Unsold
21 .
21 E/Q-703
Unsold
22 .
21 E/Q-503
Unsold
23 .
21 E/Q-702
Unsold
24 .
21 E/Q-103
Unsold
25 .
21 E/Q-203
Unsold
26 .
21 E/Q-402
Unsold
27 .
21 E/Q-504
Unsold
28 .
21 E/Q-201
Unsold
29 .
21 E/Q-804
Unsold
30 .
21 E/Q-101
Unsold
31 .
21 E/Q-904
Unsold
32 .
21 E/Q-204
Unsold
33 .
21 E/Q-601
Unsold
34 .
21 E/Q-502
Unsold
35 .
21 E/Q-403
Unsold
36 .
21 E/Q-304
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block S, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/S-702
Unsold
2 .
21 E/S-103
Unsold
3 .
21 E/S-704
Unsold
4 .
21 E/S-301
Unsold
5 .
21 E/S-203
Unsold
6 .
21 E/S-402
Unsold
7 .
21 E/S-604
Unsold
8 .
21 E/S-401
Unsold
9 .
21 E/S-404
Unsold
10 .
21 E/S-504
Unsold
11 .
21 E/S-201
Unsold
12 .
21 E/S-804
Unsold
13 .
21 E/S-101
Unsold
14 .
21 E/S-904
Unsold
15 .
21 E/S-204
Unsold
16 .
21 E/S-803
Unsold
17 .
21 E/S-703
Unsold
18 .
21 E/S-503
Unsold
19 .
21 E/S-102
Unsold
20 .
21 E/S-901
Unsold
21 .
21 E/S-701
Unsold
22 .
21 E/S-902
Unsold
23 .
21 E/S-802
Unsold
24 .
21 E/S-602
Unsold
25 .
21 E/S-801
Unsold
26 .
21 E/S-202
Unsold
27 .
21 E/S-302
Unsold
28 .
21 E/S-501
Unsold
29 .
21 E/S-603
Unsold
30 .
21 E/S-903
Unsold
31 .
21 E/S-104
Unsold
32 .
21 E/S-303
Unsold
33 .
21 E/S-601
Unsold
34 .
21 E/S-502
Unsold
35 .
21 E/S-403
Unsold
36 .
21 E/S-304
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block M, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/M-201
Unsold
2 .
21 E/M-101
Unsold
3 .
21 E/M-702
Unsold
4 .
21 E/M-103
Unsold
5 .
21 E/L-804
Unsold
6 .
21 E/L-704
Unsold
7 .
21 E/M-203
Unsold
8 .
21 E/M-402
Unsold
9 .
21 E/M-902
Unsold
10 .
21 E/M-503
Unsold
11 .
21 E/M-802
Unsold
12 .
21 E/M-603
Unsold
13 .
21 E/M-602
Unsold
14 .
21 E/M-502
Unsold
15 .
21 E/M-801
Unsold
16 .
21 E/M-202
Unsold
17 .
21 E/M-302
Unsold
18 .
21 E/M-501
Unsold
19 .
21 E/M-104
Unsold
20 .
21 E/L-404
Unsold
21 .
21 E/L-504
Unsold
22 .
21 E/M-703
Unsold
23 .
21 E/M-403
Unsold
24 .
21 E/L-904
Unsold
25 .
21 E/M-301
Unsold
26 .
21 E/M-401
Unsold
27 .
21 E/L-604
Unsold
28 .
21 E/L-304
Unsold
29 .
21 E/L-204
Unsold
30 .
21 E/M-903
Unsold
31 .
21 E/M-303
Unsold
32 .
21 E/M-803
Unsold
33 .
21 E/M-102
Unsold
34 .
21 E/M-901
Unsold
35 .
21 E/M-701
Unsold
36 .
21 E/M-601
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block P, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/P-304
Unsold
2 .
21 E/P-204
Unsold
3 .
21 E/P-502
Unsold
4 .
21 E/P-402
Unsold
5 .
21 E/P-903
Unsold
6 .
21 E/P-202
Unsold
7 .
21 E/P-102
Unsold
8 .
21 E/P-302
Unsold
9 .
21 E/P-602
Unsold
10 .
21 E/P-702
Unsold
11 .
21 E/P-901
Unsold
12 .
21 E/P-904
Unsold
13 .
21 E/P-601
Unsold
14 .
21 E/P-501
Unsold
15 .
21 E/P-301
Unsold
16 .
21 E/P-604
Unsold
17 .
21 E/P-201
Unsold
18 .
21 E/P-203
Unsold
19 .
21 E/P-503
Unsold
20 .
21 E/P-603
Unsold
21 .
21 E/P-802
Unsold
22 .
21 E/P-104
Unsold
23 .
21 E/P-404
Unsold
24 .
21 E/P-504
Unsold
25 .
21 E/P-703
Unsold
26 .
21 E/P-403
Unsold
27 .
21 E/P-303
Unsold
28 .
21 E/P-103
Unsold
29 .
21 E/P-902
Unsold
30 .
21 E/P-401
Unsold
31 .
21 E/P-701
Unsold
32 .
21 E/P-801
Unsold
33 .
21 E/P-804
Unsold
34 .
21 E/P-101
Unsold
35 .
21 E/P-803
Unsold
36 .
21 E/P-704
Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block R, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
21 E/R-403
Unsold
2 .
21 E/R-904
Unsold
3 .
21 E/R-601
Unsold
4 .
21 E/R-501
Unsold
5 .
21 E/R-303
Unsold
6 .
21 E/R-103
Unsold
7 .
21 E/R-301
Unsold
8 .
21 E/R-604
Unsold
9 .
21 E/R-401
Unsold
10 .
21 E/R-701
Unsold
11 .
21 E/R-801
Unsold
12 .
21 E/R-804
Unsold
13 .
21 E/R-101
Unsold
14 .
21 E/R-104
Unsold
15 .
21 E/R-404
Unsold
16 .
21 E/R-504
Unsold
17 .
21 E/R-703
Unsold
18 .
21 E/R-302
Unsold
19 .
21 E/R-602
Unsold
20 .
21 E/R-702
Unsold
21 .
21 E/R-901
Unsold
22 .
21 E/R-203
Unsold
23 .
21 E/R-503
Unsold
24 .
21 E/R-603
Unsold
25 .
21 E/R-802
Unsold
26 .
21 E/R-502
Unsold
27 .
21 E/R-402
Unsold
28 .
21 E/R-202
Unsold
29 .
21 E/R-304
Unsold
30 .
21 E/R-204
Unsold
31 .
21 E/R-903
Unsold
32 .
21 E/R-902
Unsold
33 .
21 E/R-704
Unsold
34 .
21 E/R-201
Unsold
35 .
21 E/R-102
Unsold
36 .
21 E/R-803
Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from.
I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other
legal purposes this undertaking amy serve.