Quarterly Progress Report Summary Details April to June, 2024

Quarterly Progress Report Summary Details April to June, 2024

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2024-24055 (31/07/2024)
Name of the Registered project SHAGUN Registration No. of the Project RAJ/P/2022/1971
Name of the Promoter VIVANTA CORPORATION Name of other Promoter(s) None
Project Address Khasra No./ Plot No.Khasra No. 436/163 , Village- VILLAGE RAMSINGHPURA URF DHOLAI , JAIPUR RAJASTHAN , Jaipur - 302020 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 71
Total Area of Project(In sq. meters) 1,483.43 Phase Area (In sq. meters) 1,483.43
Registration certificate is valid upto 31-03-2025 Registration extended upto Not Applicable
II. Number and type of apartments booked ( April to June, 2024 )
Building Name : SHAGUN
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2 BHK TYPE 1 1 48.54 4.80 9 8
2 BHK TYPE 2 1 47.88 4.89 9 9
2 BHK TYPE 3 1 47.80 4.40 9 9
2 BHK TYPE 4 1 47.59 4.89 9 8
3 BHK TYPE 1 1 72.68 4.19 8 6
3 BHK TYPE 2 1 74.69 5.48 9 7
3 BHK TYPE 3 1 72.20 4.51 9 8
3 BHK TYPE 4 1 75.32 4.51 9 6
Total 71 61 67
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2024 )

TABLE - A

Building Name: SHAGUN
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 9 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 100 100.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 40 70.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 55 100.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 20 80.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 70 90.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 80 90
2 Water Supply 80 90
3 Sewerage (chamber, lines, Septic Tank STP) 80 90
4 Storm Water Drainss 40 80
5 Landscaping & Tree Planting 80 80
6 Street Lighting 30 80
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 20 60
11 Energy management 0 0
12 Fire protection and fire safety requirements 20 90
13 Electrical meter room, sub-station, receiving station 80 80
Form R1: Date of issue
30/06/2024
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2024 )

TABLE - A

Building Name : SHAGUN
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 164,000,000.00 152,000,000.00
2 Cost incurred against the estimated cost 98,400,000.00 123,120,000.00
3 Work done (as Percentage of the estimated cost) % 60 81.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 65,600,000.00 28,880,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 13,600,000.00 11,600,000.00
2 Cost incurred against the estimated cost 7,072,000.00 6,728,000.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 52.00 58.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 6,528,000.00 4,872,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/06/2024
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( April to June, 2024 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 20,500,000.00 15,295,549.00 15,295,549.00
B. Development Cost/Cost of Construction 190,000,000.00 116,486,811.00 127,074,130.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 131,782,360.00 142,369,679.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 124,374,994.00 142,349,294.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 7,407,366.00 20,385.00
Form R3: Date of issue
29/07/2024
Certificate showing no linen or charge on the RERA retention Account :
26/07/2024
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 90
2 Rain Water Harvesting/ Recharging 60
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 90
4 Electrification(Transformer, Solar Energy etc) 80
5 Fire Fighting Provision 90
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 31/03/2022
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/12/2026
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/12/2024
If formation/registration of association of allottees is not proposed, explain reasons thereof

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : SHAGUN (Apartment : 3 BHK TYPE 3 , Block : 1, Carpet Area : 72.20 sq. meters) Number Of Apartments: 9,Booked: 9
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 406 Sold Vijendra Jain
2 . 106 Sold Rishab Jain
3 . 306 Sold MEGHA & MOHIT JAIN
4 . 506 Sold Ayushi Jain
5 . G-6 Sold gautam chand jain
6 . 206 Sold RAVINDER RANJAN
7 . 806 Sold ANAND SHARMA
8 . 606 Sold Mahendra daga
9 . 706 Sold Surbhi Jain
Building : SHAGUN (Apartment : 2 BHK TYPE 3 , Block : 1, Carpet Area : 47.80 sq. meters) Number Of Apartments: 9,Booked: 9
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 304 Sold PAWAN CHOUHAN
2 . G-4 Sold Omprakash Agarwal
3 . 204 Sold SANJAY SHARMA
4 . 104 Sold Shatrudhan Mittal
5 . 704 Sold KULDEEP GANG
6 . 604 Sold SEPEY HARKESH SINGH
7 . 804 Sold Anand Kanu
8 . 504 Sold Saroj Devi
9 . 404 Sold Janvi Vaishnav
Building : SHAGUN (Apartment : 3 BHK TYPE 1 , Block : 1, Carpet Area : 72.68 sq. meters) Number Of Apartments: 8,Booked: 7
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . G-1 Unsold
2 . 601 Sold SHAMIM ANSARI
3 . 301 Sold CHHAVI
4 . 101 Sold MOHIT SRIMAL
5 . 501 Sold AMAN KUMAR
6 . 401 Sold SUBHAM NATANI & RIYA NATANI
7 . 701 Sold RAVI KUMAR
8 . 201 Sold PRAVEEN KUMAR JAIN
Building : SHAGUN (Apartment : 2 BHK TYPE 2 , Block : 1, Carpet Area : 47.88 sq. meters) Number Of Apartments: 9,Booked: 9
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 603 Sold Nikhil Gupta
2 . 803 Sold Narendra Khatri
3 . 203 Sold MAHESH YADAV
4 . 103 Sold GAURAV Purushwani
5 . 303 Sold Piyush Garg
6 . G-3 Sold Pankaj Moolrajani
7 . 703 Sold Saurabh Mathur
8 . 503 Sold SHAMSHER ALAM
9 . 403 Sold Pushpa Joshi
Building : SHAGUN (Apartment : 2 BHK TYPE 4 , Block : 1, Carpet Area : 47.59 sq. meters) Number Of Apartments: 9,Booked: 8
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 107 Sold HARISH JAIN
2 . 507 Sold GIRISH JAIN
3 . 607 Sold Hasmukh
4 . G-7 Sold Shashank Ashok Kumar
5 . 807 Unsold
6 . 407 Sold KARESH JAIN
7 . 207 Sold Rajendra & Rekha Meena
8 . 707 Sold Manoj Kumar
9 . 307 Sold DHANPAL SAINI
Building : SHAGUN (Apartment : 3 BHK TYPE 2 , Block : 1, Carpet Area : 74.69 sq. meters) Number Of Apartments: 9,Booked: 9
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 505 Sold Ishu Kuhar
2 . 405 Sold gopi ram swami & anurag swami
3 . G-5 Sold HARISH
4 . 105 Sold SUNIL BANKA
5 . 605 Sold MANJU SRI GHOSAL
6 . 705 Sold Manu Bagda
7 . 305 Sold Rashmi & Mahesh Chandra
8 . 805 Sold S AND G POLIMER
9 . 205 Sold BHARTI MANWANI
Building : SHAGUN (Apartment : 3 BHK TYPE 4 , Block : 1, Carpet Area : 75.32 sq. meters) Number Of Apartments: 9,Booked: 8
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 202 Sold Pankaj moolrajani
2 . 302 Sold HARISH GOYAL
3 . 702 Sold ANITA GUPTA
4 . 802 Sold DILIP CHORDIA
5 . 602 Sold MONIKA RANI
6 . 402 Sold MOHD RASHID
7 . 102 Sold SHRUTI GOYAL
8 . G-2 Unsold
9 . 502 Sold Bhism Khatri
Building : SHAGUN (Apartment : 2 BHK TYPE 1 , Block : 1, Carpet Area : 48.54 sq. meters) Number Of Apartments: 9,Booked: 8
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 108 Sold Priyanaka Jain
2 . 708 Unsold
3 . 408 Sold Kavita Dhayani
4 . 808 Sold Aman Jain
5 . 208 Sold SUNENDU
6 . 308 Sold ANIL BANKA
7 . 508 Sold Harsh Jain
8 . 608 Sold Shamim Ansari
9 . G-8 Sold HEMENDRA VERMA
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Twinkle Gupta (24068) QPR MAY BE ACCEPTED, SUBJECT TO VERIFICATION 7/31/2024 Application Approved