Quarterly Progress Report Summary Details July to September, 2022

Quarterly Progress Report Summary Details July to September, 2022

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2023-17225 (15/02/2023)
Name of the Registered project GOVINDAM PARADISE Registration No. of the Project RAJ/P/2020/1197
Name of the Promoter BRIJHARI BUILDHOME LLP Name of other Promoter(s) None
Project Address Khasra No./ Plot No.92,97/2,98/2 , Village- Sukhiya , Rampura Road, Sanganer , Jaipur - 302020 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 159
Total Area of Project(In sq. meters) 2,922.52 Phase Area (In sq. meters) 2,922.52
Registration certificate is valid upto 23-10-2024 Registration extended upto Not Applicable
II. Number and type of apartments booked ( July to September, 2022 )
Building Name : GOVINDAM PARADISE
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2 BHK-I Block - 1 49.29 5.36 44 0
2 BHK-II Block - 1 48.50 4.85 22 2
2 BHK-III Block - 1 50.20 6.17 11 5
2 BHK-IV Block - 1 50.85 6.47 11 0
3 BHK-I Block - 1 68.71 5.77 11 5
3 BHK-II Block - 1 64.72 5.48 11 4
3 BHK-III Block - 1 67.83 6.26 11 0
3 BHK-IV Block - 1 64.70 4.87 22 2
3 BHK-V Block - 1 70.42 4.48 11 2
Shop I Block - 1 35.68 0.00 1 0
Shop II Block - 1 29.28 0.00 1 0
Shop III Block - 1 28.08 0.00 1 0
Shop IV Block - 1 28.32 0.00 1 0
Shop V Block - 1 26.24 0.00 1 0
Total 159 20 25
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2022 )

TABLE - A

Building Name: GOVINDAM PARADISE
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 2 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 11 Number of Slabs of Super Structure 73 77.27
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 10 20.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 5.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 30 40.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 10.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 0 40
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
10/10/2022
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2022 )

TABLE - A

Building Name : GOVINDAM PARADISE
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 300,000,000.00 300,000,000.00
2 Cost incurred against the estimated cost 254,011,127.00 256,715,689.00
3 Work done (as Percentage of the estimated cost) % 85 86.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 45,988,873.00 43,284,311.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 0.00 0.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 0.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
31/10/2022
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2022 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 60,000,000.00 60,000,000.00 60,000,000.00
B. Development Cost/Cost of Construction 240,000,000.00 176,911,392.00 200,850,451.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 236,911,392.00 260,850,451.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 34,942,958.00 39,482,501.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 201,968,434.00 221,367,950.00
Form R3: Date of issue
13/02/2023
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0 23/10/2024
2 Rain Water Harvesting/ Recharging 0 23/10/2024
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0 23/10/2024
4 Electrification(Transformer, Solar Energy etc) 0 23/10/2024
5 Fire Fighting Provision 0 23/10/2024
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 27/01/2020
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 01/10/2024

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : GOVINDAM PARADISE (Apartment : 3 BHK-V, Block : 1, Carpet Area : 70.42 sq. meters) Number Of Apartments: 11,Booked: 10
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 514 Unsold
2 . 614 Unsold
3 . 814 Unsold
4 . 114 Sold RAGHAV AGARWAL
5 . 914 Unsold
6 . 214 Unsold
7 . 414 Sold MANJU GAUR / DINESH KUMAR GAUR
8 . 1114 Unsold
9 . 1014 Sold PRIYANK MATHUR / MANOJ MATHUR
10 . 314 Sold PRASHANT MISHRA
11 . 714 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-II, Block : 1, Carpet Area : 48.50 sq. meters) Number Of Apartments: 22,Booked: 3
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 1009 Unsold
2 . 309 Unsold
3 . 706 Unsold
4 . 406 Unsold
5 . 709 Unsold
6 . 1106 Unsold
7 . 809 Unsold
8 . 106 Unsold
9 . 506 Sold SHARDA MALI / BHARAT LAL MALI
10 . 109 Unsold
11 . 206 Unsold
12 . 906 Sold C.P JAIN / ANITA JAIN
13 . 509 Unsold
14 . 609 Unsold
15 . 1006 Unsold
16 . 306 Unsold
17 . 606 Unsold
18 . 209 Unsold
19 . 909 Unsold
20 . 806 Sold DIPALI PUNDIR
21 . 1109 Unsold
22 . 409 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-I, Block : 1, Carpet Area : 68.71 sq. meters) Number Of Apartments: 11,Booked: 6
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 301 Unsold
2 . 1001 Unsold
3 . 401 Sold RAJENDRA PRASAD VERMA
4 . 1101 Unsold
5 . 601 Unsold
6 . 701 Sold SUNITA / SUBHASH PARIHAR
7 . 801 Unsold
8 . 901 Sold RENU TIWARI & AJAY SHARMA
9 . 201 Sold NAVIN KUMAR BANSAL
10 . 101 Unsold
11 . 501 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-I, Block : 1, Carpet Area : 49.29 sq. meters) Number Of Apartments: 44,Booked: 3
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 104 Unsold
2 . 1004 Unsold
3 . 805 Sold KAJAL PUNDIR
4 . 1111 Unsold
5 . 410 Unsold
6 . 211 Unsold
7 . 105 Unsold
8 . 304 Unsold
9 . 1005 Unsold
10 . 610 Unsold
11 . 411 Unsold
12 . 505 Unsold
13 . 704 Unsold
14 . 1010 Unsold
15 . 111 Unsold
16 . 811 Unsold
17 . 310 Unsold
18 . 904 Unsold
19 . 705 Sold SHRUTI MUKHERJEE / ANURAG BANERJEE
20 . 1011 Unsold
21 . 204 Unsold
22 . 311 Unsold
23 . 510 Unsold
24 . 905 Unsold
25 . 404 Unsold
26 . 511 Unsold
27 . 205 Unsold
28 . 710 Sold BAISHAKHI CHAKROBORTY / DEBASHISH CHAKRABORTY
29 . 1104 Unsold
30 . 804 Unsold
31 . 1110 Unsold
32 . 911 Unsold
33 . 605 Unsold
34 . 210 Unsold
35 . 604 Unsold
36 . 711 Unsold
37 . 1105 Unsold
38 . 405 Unsold
39 . 910 Unsold
40 . 504 Unsold
41 . 305 Unsold
42 . 810 Unsold
43 . 611 Unsold
44 . 110 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-III, Block : 1, Carpet Area : 50.20 sq. meters) Number Of Apartments: 11,Booked: 5
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 507 Unsold
2 . 607 Sold BRAMHA BANDHAB BANDOPADHYAY / MADHUMITA CHATERJEE
3 . 107 Unsold
4 . 807 Unsold
5 . 907 Unsold
6 . 207 Unsold
7 . 1007 Sold SANJU SAINI / PRADEEP PRAKASH
8 . 1107 Unsold
9 . 407 Unsold
10 . 307 Unsold
11 . 707 Sold MANOJ GUPTA / HEMLATA GUPTA
Building : GOVINDAM PARADISE (Apartment : 3 BHK-IV, Block : 1, Carpet Area : 64.70 sq. meters) Number Of Apartments: 22,Booked: 6
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 313 Unsold
2 . 712 Sold PRARTHANA / TARUN NAMA
3 . 1013 Unsold
4 . 713 Sold MAHENDRA ENKHIA / SUKHDEV GANDER
5 . 1112 Unsold
6 . 412 Unsold
7 . 413 Sold MUKESH KUMAR VERMA / PRIYANKA TUNWAL
8 . 112 Unsold
9 . 113 Unsold
10 . 813 Unsold
11 . 512 Unsold
12 . 212 Unsold
13 . 513 Unsold
14 . 912 Unsold
15 . 1012 Sold RAMINDER KAUR / KARANJEET SINGH
16 . 312 Unsold
17 . 613 Unsold
18 . 913 Unsold
19 . 612 Unsold
20 . 213 Unsold
21 . 1113 Unsold
22 . 812 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-III, Block : 1, Carpet Area : 67.83 sq. meters) Number Of Apartments: 11,Booked: 1
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 1003 Sold AMITA SHARMA / MOHIT SHARMA
2 . 303 Unsold
3 . 503 Unsold
4 . 603 Unsold
5 . 703 Unsold
6 . 903 Unsold
7 . 203 Unsold
8 . 103 Unsold
9 . 803 Unsold
10 . 1103 Unsold
11 . 403 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-II, Block : 1, Carpet Area : 64.72 sq. meters) Number Of Apartments: 11,Booked: 5
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 602 Unsold
2 . 702 Unsold
3 . 902 Unsold
4 . 202 Unsold
5 . 302 Unsold
6 . 1002 Unsold
7 . 402 Sold RANDHIR SINGH / RANJANA SINGH
8 . 1102 Unsold
9 . 502 Sold MAMTA DEVI / HARENDRA SINGH
10 . 802 Unsold
11 . 102 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-IV, Block : 1, Carpet Area : 50.85 sq. meters) Number Of Apartments: 11,Booked: 1
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 808 Sold VISHAL YADUVANSHI
2 . 108 Unsold
3 . 208 Unsold
4 . 908 Unsold
5 . 1108 Unsold
6 . 408 Unsold
7 . 508 Unsold
8 . 608 Unsold
9 . 708 Unsold
10 . 1008 Unsold
11 . 308 Unsold
Building : GOVINDAM PARADISE (Apartment : Shop IV, Block : 1, Carpet Area : 28.32 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-IV Unsold
Building : GOVINDAM PARADISE (Apartment : Shop I, Block : 1, Carpet Area : 35.68 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-I Unsold
Building : GOVINDAM PARADISE (Apartment : Shop III, Block : 1, Carpet Area : 28.08 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-III Unsold
Building : GOVINDAM PARADISE (Apartment : Shop II, Block : 1, Carpet Area : 29.28 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-II Unsold
2 . SHOP-II Unsold
Building : GOVINDAM PARADISE (Apartment : Shop V, Block : 1, Carpet Area : 26.24 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-V Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Fee 5000.00 Print Receipt QPR Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) The QPR may be accepted subject to verification. 7/17/2023 Application Approved