QPR Summary

RERA
Quarterly Progress Report Summary Details July to September, 2022

Quarterly Progress Report Summary Details July to September, 2022

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2022-15885 (31/10/2022)
Name of the Registered project MANGLAM AADHAR VAISHALI ESTATE Registration No. of the Project RAJ/P/2017/341
Name of the Promoter MANGLAMHOME CONSTRUCTION COMPANY LLP Name of other Promoter(s) None
Project Address Khasra No./ Plot No.2123, 2124, 2133, 2134, 2135, 2136, 2137, 2138, 2140, 117/1, 119, 120, 120/1, 121, 121/1 , Village- SIRSI AND BHANKROTA , VAISHALI ESTATE , Jaipur - 302021 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 1148
Total Area of Project(In sq. meters) 18,410.20 Phase Area (In sq. meters) 18,410.20
Registration certificate is valid upto 30-09-2021 Registration extended upto 30-09-2022
II. Number and type of apartments booked ( July to September, 2022 )
Building Name : MANGLAM AADHAR VAISHALI ESTATE
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
SHOP 1 17.93 0.00 2 1
SHOP 1 13.66 0.00 2 0
SHOP 1 16.26 0.00 2 0
SHOP 1 20.53 0.00 4 0
SHOP 1 15.61 0.00 4 0
SHOP 1 20.25 0.00 2 0
SHOP 5 25.64 0.00 1 0
SHOP 5 13.01 0.00 1 0
SHOP 5 20.53 0.00 3 0
SHOP 5 16.07 0.00 1 0
SHOP 5 17.56 0.00 2 0
SHOP 5 20.25 0.00 2 0
SHOP 5 15.14 0.00 1 0
SHOP 5 15.61 0.00 1 0
SHOP 5 14.86 0.00 2 0
SHOP 5 20.72 0.00 1 0
SHOP 5 29.73 0.00 1 0
2 BHK Block - 1 41.85 2.70 144 130
2 BHK Block - 2 41.84 2.70 168 134
2 BHK Block - 3 59.94 12.39 120 120
2 BHK Block - 4 41.85 2.70 144 130
2 BHK Block - 5 41.85 2.70 144 132
2 BHK Block - 6 57.47 0.00 168 163
1 BHK Block - 7 29.95 0.00 228 123
Total 1148 933 960
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2022 )

TABLE - A

Building Name: MANGLAM AADHAR VAISHALI ESTATE
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 0 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 12 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 94 95.71
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 64 83.57
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 97 97.14
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 100 100.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 50 74.28

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 60 90
2 Water Supply 70 100
3 Sewerage (chamber, lines, Septic Tank STP) 90 80
4 Storm Water Drainss 85 100
5 Landscaping & Tree Planting 50 100
6 Street Lighting 90 100
7 Community Building 90 80
8 Treatment and disposal of sewage and sullage water 70 50
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 95 100
11 Energy management 70 60
12 Fire protection and fire safety requirements 50 90
13 Electrical meter room, sub-station, receiving station 50 95
Form R1: Date of issue
17/10/2022
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2022 )

TABLE - A

Building Name : MANGLAM AADHAR VAISHALI ESTATE
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 795,595,617.00 795,575,617.00
2 Cost incurred against the estimated cost 728,277,887.00 781,955,922.00
3 Work done (as Percentage of the estimated cost) % 92 98.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 67,317,730.00 13,619,695.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 59,424,383.00 59,424,383.00
2 Cost incurred against the estimated cost 53,908,182.00 57,047,407.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 91.00 96.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 5,516,201.00 2,376,976.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/09/2022
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2022 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 90,000,000.00 90,000,000.00 90,000,000.00
B. Development Cost/Cost of Construction 900,000,000.00 952,116,551.00 1,053,328,280.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 1,042,116,551.00 1,143,328,280.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 831,643,985.00 958,309,318.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 210,472,565.00 185,018,962.00
Form R3: Date of issue
30/10/2022
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 100 31/12/2022
2 Rain Water Harvesting/ Recharging 100
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 51
4 Electrification(Transformer, Solar Energy etc) 50
5 Fire Fighting Provision 50
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 25/10/2018
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/12/2022
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/12/2022
If formation/registration of association of allottees is not proposed, explain reasons thereof

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
• Date of completion certificate.
29/09/2022
• Has the Completion certificate been uploaded on RERA web portal?
4. Has the Occupancy Certificate also been obtained?
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) The QPR is accepted subject to verification. 7/18/2023 Application Approved