Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2021-570 (7/27/2021)
Project Name SAMBHAVNATH COMPLEX Promoter Name SAMBHAVNATH COMPLEX LIMITED
Project Registration No. RAJ/P/2018/652 Project Type Group Housing
Estimated Finish Date (in online form) 16-09-2020 Project Registration Valid till
(as per registration certificate)
12/31/2019 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 12/31/2021
Duration of extension being sought 3 Months 15 Days
Project Building Plan Details
First Approval Date of Building Plan 10/30/2013
Permission/Approval of Building Plan Valid Till 9/16/2020 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
As directed by the authority we are applying for the extension up to 31.12.2021.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 40,00,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 39,68,00,000.00
Form R3
Total Estimated Land Cost ₹ 44,69,100.00
Total Cost Incurred on Land ₹ 1,40,19,000.00
Total Estimated Development Cost ₹ 40,00,00,000.00
Total Cost Incurred on Development ₹ 55,68,12,000.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,12/31/2021 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 9/16/2020; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 12/31/2021 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
12780.95
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
12780.95 ₹ 1,91,715.00 ₹ 63,905.00 ₹ 1,27,810.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Rishabh Sharma (10665) Please verify the fee deposited. 7/27/2021 PENDING WITH PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER
2 Madan Pareek (16059) Rs. 191715/- deposited by RERA Trans. No. 13224 dated 27.07.2021 for extension of registration (Other than Corona Pandemic) 7/28/2021 PENDING WITH NODAL OFFICER
3 Rishabh Sharma (10665) 1. As in the said case extension under section 6 of the Act was given only for 8 Months 16 Days, therefore, firstly you have to modify/update the said application of extension for the remaining time period i.e. up to 31.12.2021, and then after if needed you can take the extension of registration beyond 1 year in reference to the Authority's order dated 22.05.2021; 2. Please correct the date of first approval of building plans as 30.10.2013 and check/update the validity of building plans in online application as per the last issued approval letter dated 16.09.2019; 3. Please upload the Form R2 with the seal of Engineer instead of any construction consultant; 4. Cost incurred on Land and Development is very much then the estimated cost, therefore, please update the cost details in online application through General modification module. 7/28/2021 APPLICATION OBJECTED
3 Promoter Reply in relation to objection raised in our application for extension is uploaded for your kind perusal. User updated this details. 9/2/2021 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) In reference to your reply, please update the date of extension being sought as 31.12.2021 and get the application approved. And, after that, if still more extension may be required then please submit application in accordance with the Authority's order dated 22.05.2020 9/3/2021 APPLICATION OBJECTED
4 Promoter As directed by you, we have updated the date of extension being sought upto 31.12.2021. We request you to kindly approve the extension. User updated this details. 11/20/2021 PENDING WITH NODAL OFFICER
5 Rishabh Sharma (10665) Application is submitted for kind perusal and decision regarding Extension of Registration of Project upto 31-12-2021 w.r.t. that attached checklist. 11/25/2021 PENDING WITH JOINT REGISTRAR
6 Arpit Sancheti (10683) Submitted for kind perusal and further orders pls. 11/25/2021 PENDING WITH REGISTRAR
7 Ramesh Sharma (9009) Submitted for perusal and decision, Sir. 11/25/2021 PENDING WITH CHAIRMAN
8 NIHAL CHAND GOEL (1) Approved with special condition. 11/25/2021 Application Approved