Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2023-1150 (8/26/2023)
Project Name Mahima's Shubh Nilay Phase-II "Villas" Promoter Name GREEN BUILDESTATE PRIVATE LIMITED
Project Registration No. RAJ/P/2020/1319 Project Type Group Housing
Estimated Finish Date (in online form) 31-12-2023 Project Registration Valid till
(as per registration certificate)
12/31/2023 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 6/30/2024
Duration of extension being sought 6 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 8/10/2020
Permission/Approval of Building Plan Valid Till 7/31/2027 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Project was impacted by several reasons such as bad economic conditions, impact of second wave of COVID etc. as also elaborated in the explanatory note attached, thus extension of timelines required.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 36,16,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 25,33,00,000.00
Form R3
Total Estimated Land Cost ₹ 5,19,88,421.31
Total Cost Incurred on Land ₹ 5,31,88,161.00
Total Estimated Development Cost ₹ 42,00,00,000.00
Total Cost Incurred on Development ₹ 25,97,60,559.00
Additional Information
Project was impacted by several reasons such as bad economic conditions, impact of second wave of COVID etc. and also elaborated in the explanatory note attached, thus extension of timelines required.
Other Documents
Explanatory Note View
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,6/30/2024 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).

Registered Phase Area

Online Phase Area
24044.62
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
24044.62 ₹ 1,20,230.00 ₹ 1,20,224.00 ₹ 0.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
Digvijay Singh 9928806456 legal@mahimagroup.org
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Project extension fees Rs.120230/- Deposited by rera transaction No.962 Dated 26.08.2023 for project extension 8/28/2023 PENDING WITH NODAL OFFICER
2 Rishabh Sharma (10665) The order dated 13.05.2020 from the authority does not apply to your case. Therefore, change the reason for the extension other than force majeure and include an explanatory note that it is unrelated to the coronavirus pandemic. Comply with the direction on or before 07.09.2023. 8/31/2023 APPLICATION OBJECTED
3 Promoter Dear Sir, In regards to the objection raised by you, the grounds of extension is changed from Force Majeure to Other than Force Majeure and also the explanatory note is attached for elaborating the same. In light of the same, it is requested to kindly proceed with our request of extension in the Project. User updated this details. 9/1/2023 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) Explanatory note is not attached. Comply with the direction on or before 11.09.2023. 9/4/2023 APPLICATION OBJECTED
5 Promoter Sir, the file is attached again in the any other documents to support the application section and in the comment section for your perusal. User updated this details. 9/4/2023 PENDING WITH NODAL OFFICER
6 Rishabh Sharma (10665) Application is submitted for kind perusal and approval regarding extension of registration under section 6, i.e., upto 30-06-2024 (06 Months) w.r.t. attached checklist. 9/4/2023 PENDING WITH JOINT REGISTRAR
7 Arpit Sancheti (10683) Submitted for kind perusal and further orders regarding extension pls. 9/7/2023 PENDING WITH REGISTRAR
8 Ramesh Sharma (9009) Submitted for perusal and approval,sir. 9/7/2023 PENDING WITH MEMBER
9 Salvinder Sohata (27667) An application prior to expiry of validity of registration scheduled on 31-12-2023, submitted for seeking extension upto 40-05-2024 is filed under proviso of section 6 of the Act. The application on ground of without force meajure is moved . For consideration to approval 9/7/2023 PENDING WITH CHAIRMAN
10 Chairman Rajasthan (1) Approved with the following special conditions, (i) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, (ii) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30.09.2023; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; (iii) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and (iv) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan submitted by the promoter. 9/12/2023 Application Approved