Extension Application No. : RAJ-RERA-APP-PE-2021-712 (12/28/2021)
Project Name SAMBHAVNATH COMPLEX Promoter Name SAMBHAVNATH COMPLEX LIMITED
Project Registration No. RAJ/P/2018/652 Project Type Group Housing
Estimated Finish Date (in online form) 16-09-2020 Project Registration Valid till
(as per registration certificate)
12/31/2019 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 12/31/2022
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 10/30/2013
Permission/Approval of Building Plan Valid Till 9/16/2020 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Explanatory Note is uploaded.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
In case of extension beyond one year (on grounds other than force majeure/corona pandemic)
State clearly the exceptional and compelling circumstances and reasons due to which the project could not be completed even with in the extended period of one year Explanatory Note is uploaded. View
RWA Constituted or not
Total no. of units 200
No.of units sold booked/alloted/sold as per RC/latest QPR 109
No.of units sold booked/alloted/sold till date 118
Number of allottees, if any, who have consented or have no objection to the prposed extension being granted 0 View
No.of allottees, who need to be given a notice by the Authority to ascertain if they have any objection to the proposed extension being granted 118
Form R2
Estimated Construction Cost (Table A+B) ₹ 40,00,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 35,80,00,000.00
Form R3
Total Estimated Land Cost ₹ 44,69,100.00
Total Cost Incurred on Land ₹ 1,40,19,000.00
Total Estimated Development Cost ₹ 40,00,00,000.00
Total Cost Incurred on Development ₹ 48,40,19,000.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,12/31/2022 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 9/16/2020; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 12/31/2022 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
12780.95
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
12780.95 ₹ 1,91,720.00 ₹ 63,905.00 ₹ 1,27,810.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
na 1234567890 na@gmail.com
Comments Details
PARA Created BY Comments Date Status Document
1 Rishabh Sharma (10665) Verify the fee deposited. 12/29/2021 PENDING WITH PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER
2 Madan Pareek (16059) Rs. 191720/- deposited by RERA Transaction No. 18283 dated 28.12.2021 for extension of registration (other than corona pandemic). 12/30/2021 PENDING WITH NODAL OFFICER
3 Rishabh Sharma (10665) 1. First Approval Date of Building Plan was 30.10.2013, kindly update the same accordingly; 2. Clarify how you have considered the validity of building plans as 07.08.2020; 3. If the cost incurred on land is approx. 3 times more than the estimated cost then apply for the change of land cost through project profile modification; 4. Along with uploading the details of allottees, fill in the details in the application also. Comply with said direction on or before 06.01.2022. 12/30/2021 APPLICATION OBJECTED
3 Promoter 1. We have corrected the date of approval of building plan and validity of building plans. 2. We have applied for the updation of land and development cost vide application no. RAJ-RERA-APP-SPM-2022-145. 3. Details of allottees are now updated. User updated this details. 1/6/2022 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) Clarify how you have considered the validity of building plans as 16-09-2020. 1/6/2022 APPLICATION OBJECTED
4 Promoter Permission of the Building Plan is valid till 16.09.2020 which has been considered from sheet 1 of the approved map where it is clearly noted by the local body that the Approved Building Plan is valid till 1 year. User updated this details. 1/7/2022 PENDING WITH NODAL OFFICER
5 Rishabh Sharma (10665) Promoter has submitted the said application for the extension in accordance with the Authority’s order dated 22.05.2020 i.e., giving the Exceptional and compelling circumstances and reasons and the contact details of 118 allottees. Therefore, application is submitted for kind perusal and decision to schedule the date of hearing so that the notices may be issued to the promoter and the allottees (as per contact details submitted by the promoter) regarding extension of registration beyond 1 year i.e. 31-12-2022 (12 months) w.r.t. the attached checklist. 1/7/2022 PENDING WITH JOINT REGISTRAR
6 Ramesh Sharma (9009) Submitted for fixing the date of hearing. 1/7/2022 PENDING WITH CHAIRMAN
7 NIHAL CHAND GOEL (1) ISSUE NOTICES FOR HEARING ON 07.02.2022. 1/8/2022 PENDING WITH REGISTRAR
8 Ramesh Sharma (9009) Put up notices for hearing for 07-02-2022 1/8/2022 PENDING WITH JOINT REGISTRAR
9 Ramesh Sharma (9009) Put up notices 1/9/2022 PENDING WITH NODAL OFFICER
10 Ramesh Sharma (9009) Notices issued, Put up on date of hearing. 1/11/2022 PENDING WITH NODAL OFFICER
11 Rishabh Sharma (10665) Application is submitted for the approval of extension w.r.t. the attached note sheet while mentioning special conditions in Form F as follows: (i) The promoter shall prepare and provide by 28.02.2022, a detailed construction and development plan to achieve completion of all the remaining development works by 31.12.2022, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it; (ii) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 31.12.2022; (iii) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 28.02.2022; and shall submit regularly the QPRs and APRs as will fall due during the extended period of registration; (iv) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand refund or interest/compensation for the period of delay in delivering possession of the allotted flat; and (v) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 28.02.2022. 2/10/2022 PENDING WITH JOINT REGISTRAR
12 Arpit Sancheti (10683) Submitted for kind perusal and further orders pls. 2/10/2022 PENDING WITH REGISTRAR
13 Ramesh Sharma (9009) Submitted for perusal and approval, Sir. 2/10/2022 PENDING WITH CHAIRMAN
14 NIHAL CHAND GOEL (1) Approved with special conditions as follows: (i) The promoter shall prepare and provide by 28.02.2022, a detailed construction and development plan to achieve completion of all the remaining development works by 31.12.2022, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it; (ii) The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 31.12.2022; (iii) The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 28.02.2022; and shall submit regularly the QPRs and APRs as will fall due during the extended period of registration; (iv) This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand refund or interest/compensation for the period of delay in delivering possession of the allotted flat; and (v) The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 28.02.2022. 2/12/2022 Application Approved