Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2024-1266 (4/24/2024)
Project Name STAR PINNACLE Promoter Name M/s Bardawat Builders And Contractors
Project Registration No. RAJ/P/2022/1810 Project Type Group Housing
Estimated Finish Date (in online form) 16-05-2024 Project Registration Valid till
(as per registration certificate)
5/16/2024 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 5/16/2025
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 11/17/2021
Permission/Approval of Building Plan Valid Till 11/17/2028 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Major work is completed i.e. Structure is 100% completed, Internal and External Development Works are also completed only, Minute work has to be done.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 6,00,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 2,60,81,537.00
Form R3
Total Estimated Land Cost ₹ 9,00,00,000.00
Total Cost Incurred on Land ₹ 10,44,000.00
Total Estimated Development Cost ₹ 6,00,00,000.00
Total Cost Incurred on Development ₹ 2,51,34,326.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,5/16/2025 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 11/17/2028; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 5/16/2025 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
742.50
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
742.50 ₹ 5,570.00 ₹ 1,857.00 ₹ 3,713.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
TEJKARAN VERMA 9414010089 opthekda@gmail.com
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Project extension fees Rs.1857/- Standard fees Rs.3713/- Total Fees Rs.5570/- Deposited by RERA Transaction No.1064 Dated 24.04.2024 for phase Area742.50 SQ MT 4/25/2024 PENDING WITH NODAL OFFICER
2 Rishabh Sharma (10665) Date of approval and validity of building plans were incorrectly filled out in the application. Please update the attributes based on the uploaded approval letter and also upload the approval letter for the revised building plans from the empanelled architect. Comply with the directions on or before 06.05.2024 4/29/2024 APPLICATION OBJECTED
3 Promoter Sir, we have corrected the date of approval and validity of building plans as per the first approval letter and uploaded approval letter for the revised building plans from the empanelled architect. Kindly accept our humble submission and oblige us. User updated this details. 4/29/2024 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) Application is submitted for kind perusal and approval regarding extension of registration under section 6, i.e., upto 16-05-2025 (12 Months) w.r.t. the attached checklist. 5/1/2024 PENDING WITH JOINT REGISTRAR
5 Ramesh Sharma (9009) Submitted for approval, Madam. 5/2/2024 PENDING WITH CHAIRMAN
6 Chairman Rajasthan (1) approved 5/3/2024 Application Approved