Quarterly Progress Report Summary Details July to September, 2025

Quarterly Progress Report Summary Details July to September, 2025

I. Particulars of the Project 213
Application No. : RAJ-RERA-APP-QPR-2025-31109 (26/11/2025)
Name of the Registered project EMPIRE 1ST Registration No. of the Project RAJ/P/2025/3912
Name of the Promoter BHUMIJA REALSQUARE LLP Name of other Promoter(s) None
Project Address Khasra No./ Plot No.1927/593, 594 , Village- Khorashyamdas , , Jaipur - 303704 (Rajasthan)
Type of Project Plotted Development Number of Sanctioned Apartments/Plots 98
Total Area of Project(In sq. meters) 19,300.00 Phase Area (In sq. meters) 19,300.00
Registration certificate is valid upto 31-10-2026 Registration extended upto Not Applicable
II. Number and type of Plots booked/ allotted/ sold (( July to September, 2025 ))
Plot Area Plots Total number of sanctioned plots Number of Plots booked/ sold/ allotted by the end of last quarter Cumulative Number of Plots booked/ sold/ allotted by the end of current quarter
124.55 Plot No 1 1 0
124.74 Plot No 2 1 0
124.85 Plot No 3 1 0
124.39 Plot No 4 1 0
122.99 Plot No 5 1 0
121.64 Plot No 6 1 0
121.94 Plot No 7 1 0
120.56 Plot No 8 1 0
134.79 Plot No 9, 34, 35, 60, 61, 82, 83, 106 8 2
92.96 Plot No 10 to 18, 23 to 33, 36 to 46, 49 to 59, 62 to 71, 74 to 81, 84 to 91 68 10
153.51 Plot No 21 1 0
134.77 Plot No 48 1 0
177.11 Plot No 73 1 0
55.38 Plot No 94 1 0
71.44 Plot No 95 1 0
79.51 Plot No 96 1 0
121.34 Plot No 97 1 0
58.11 Plot No 98 1 0
65.92 Plot No 99 1 0
74.35 Plot No 103, 104 2 0
106.91 Plot No 105 1 1
267.36 Infromal 1 0
III. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2025 )

TABLE - A

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 22 52
2 Water Supply 15 48
3 Sewerage (chamber, lines, Septic Tank STP) 10 60
4 Storm Water Drainss 6 70
5 Landscaping & Tree Planting 0 10
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 13 32
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
10/09/2025
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2025 )

TABLE - A

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 150,000,000.00 150,000,000.00
2 Cost incurred against the estimated cost 14,815,200.00 62,015,000.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 10.00 41.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 135,184,800.00 87,985,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Form R2: Date of issue
10/09/2025
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2025 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 51,562,496.00 51,562,496.00 51,562,496.00
B. Development Cost/Cost of Construction 150,000,000.00 14,815,200.00 62,015,000.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 66,377,696.00 113,577,496.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 0.00 68,077,814.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 66,377,696.00 45,499,682.00
Form R3: Date of issue
10/09/2025
Certificate showing no linen or charge on the RERA retention Account :
25/11/2025
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 52
2 Rain Water Harvesting/ Recharging 48
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 60
4 Electrification(Transformer, Solar Energy etc) 50
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 19/05/2025
2 Has there been any further Modification, Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/12/2025

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

X. Allottee Details

Plot Type: Plot No 1Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 1 Unsold
Plot Type: Plot No 2Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 2 Sold Virendra Singh Shekhawat
Plot Type: Plot No 3Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 3 Unsold
Plot Type: Plot No 4Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 4 Unsold
Plot Type: Plot No 5Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 5 Sold Prem Lata
Plot Type: Plot No 6Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 6 Sold Prem Lata
Plot Type: Plot No 7Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 7 Sold Rekha Knwar
Plot Type: Plot No 8Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 8 Unsold
Plot Type: Plot No 9, 34, 35, 60, 61, 82, 83, 106Number Of Plots: 8,Booked/alloted/sold: 4
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 9 Unsold
2 . Plot No 34 Unsold
3 . Plot No 35 Unsold
4 . Plot No 60 Sold 60 Tara Shankar Pareek
5 . Plot No 61 Sold Umrav Kumar Pareek
6 . Plot No 85 Unsold
7 . Plot No 83 Sold Deepika Rathore
8 . Plot No 106 Sold Anita Meena
Plot Type: Plot No 10 to 18, 23 to 33, 36 to 46, 49 to 59, 62 to 71, 74 to 81, 84 to 91Number Of Plots: 68,Booked/alloted/sold: 63
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 10 Sold Anjana Meena
2 . Plot No 11 Sold Mahesh kumar
3 . Plot No 12 Sold Bhagirath Prasad Prajapat
4 . Plot No 13 Unsold
5 . Plot No 14 Sold Virendra Singh Rao
6 . Plot No 15 Sold Pinky Bhati
7 . Plot No 16 Sold Ram Naresh Rao
8 . Plot No 17 Sold Govind Ram Saini
9 . Plot No 18 Sold kuldeep
10 . Plot No 23 Sold Manish Kumar
11 . Plot No 24 Sold Mahendra Kumar Kumawat
12 . Plot No 25 Sold Om Prakash Saini & Sarita Saini
13 . Plot No 26 Sold Pooja Sharma
14 . Plot No 27 Sold Ram Singh Dewanda
15 . Plot No 28 Sold Kamlesh Kumawat
16 . Plot No 29 Sold Suresh Kumar Sharma
17 . Plot No 30 Sold Pooja Sharma
18 . Plot No 31 Sold Mukesh Kanwar
19 . Plot No 32 Sold Suman Kumari
20 . Plot No 33 Sold Subhash Chandra Mishra
21 . Plot No 36 Sold Rekha Jayesh Pujari
22 . Plot No 37 Sold Sampat Saini
23 . Plot No 38 Unsold
24 . Plot No 39 Sold Bajrang Lal Sharma
25 . Plot No 40 Sold Monika Sharma
26 . Plot No 41 Sold Uma Tailor
27 . Plot No 42 Sold Mahendar Shantav
28 . Plot No 43 Sold Jyoti Kanwar
29 . Plot No 44 Sold Archna Kumari
30 . Plot No 45 Sold Sushila Andana
31 . Plot No 46 Sold Narendar
32 . Plot No 49 Sold Priyanka
33 . Plot No 50 Sold Shiksha Vati
34 . Plot No 51 Sold Pinki Kumawat
35 . Plot No 52 Sold Daulat Singh Meena
36 . Plot No 53 Sold Jyoti Meena
37 . Plot No 54 Sold Meenakshi Sabal
38 . Plot No 55 Sold pawan Kumar
39 . Plot No 56 Sold Rakesh Kuamr Maharda
40 . Plot No 57 Sold Abhilasha Sakunia
41 . Plot No 58 Unsold
42 . Plot No 59 Sold Lal Chand Yadav
43 . Plot No 62 Sold Naveen Kuamr saini
44 . Plot No 63 Sold manju Devi
45 . Plot No 64 Unsold
46 . Plot No 65 Sold Sushma Agarwal
47 . Plot No 66 Sold Prithviraj Saini
48 . Plot No 67 Sold Sunita Meena
49 . Plot No 68 Sold Shankar Lal Bakoliya
50 . Plot No 69 Sold Devendra Kumar
51 . Plot No 70 Sold Neha
52 . Plot No 71 Sold Pankaj Kumar
53 . Plot No 74 Sold Dinesh Singh
54 . Plot No 75 Sold Madhu Sudan Tailor
55 . Plot No 76 Sold Satyavir Singh
56 . Plot No 77 Sold Om Kanwar
57 . Plot No 78 Sold Manju
58 . Plot No 79 Sold Mohan Singh
59 . Plot No 80 Sold Sachiva Gupta
60 . Plot No 81 Sold Budha Ram Meena
61 . Plot No 84 Sold Ramesh Kuamr & Amandeep meena
62 . Plot No 85 Sold Jai Shri Gaur
63 . Plot No 86 Sold Rajendra Prasad Bobasya
64 . Plot No 87 Sold Jyoti Yadav
65 . Plot No 88 Unsold
66 . Plot No 89 Sold Anil Kumar
67 . Plot No 90 Sold Priyanka Kumari Maan
68 . Plot No 91 Sold Pramod Kumar
Plot Type: Plot No 21Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 21 Unsold
Plot Type: Plot No 47Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 47 Not yet approved for construction/sale
Plot Type: Plot No 48Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 48 Sold Mukesh Kumar Sabal
Plot Type: Plot No 73Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 73 Unsold
Plot Type: Plot No 94Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 94 Unsold
Plot Type: Plot No 95Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 95 Sold Pankaj Kumar Mundotiya
Plot Type: Plot No 96Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 96 Sold Chandra Prakash Saini
Plot Type: Plot No 97Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 97 Unsold
Plot Type: Plot No 98Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 98 Sold Sharmila
Plot Type: Plot No 99Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 99 Sold Tara Chand Sharma
Plot Type: Plot No 103, 104Number Of Plots: 2,Booked/alloted/sold: 2
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 103 Sold Mahesh Kumar Sharma
2 . Plot No 104 Sold Getaraj
Plot Type: Plot No 105Number Of Plots: 1,Booked/alloted/sold: 1
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 105 Sold Rajani Devi
Plot Type: InfromalNumber Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Infromal Unsold
Plot Type: Plot No 19, 20, 107, 108, 109Number Of Plots: 5,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 19 Mortgage
2 . Plot No 20 Mortgage
3 . Plot No 107 Mortgage
4 . Plot No 108 Mortgage
5 . Plot No 109 Mortgage
Plot Type: Plot No 22Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 22 Mortgage
Plot Type: Plot No 72Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 72 Mortgage
Plot Type: Plot No 92Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 92 Mortgage
Plot Type: Plot No 93Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 93 Mortgage
Plot Type: Plot No 100Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 100 Mortgage
Plot Type: Plot No 101Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 101 Mortgage
Plot Type: Plot No 102Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 102 Mortgage
Plot Type: Plot No 110Number Of Plots: 1,Booked/alloted/sold: 0
Sr.No. Plot No. Booking Status Allottee Name
1 . Plot No 110 Mortgage
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details