QPR Summary

RERA
Quarterly Progress Report Summary Details January to March, 2025

Quarterly Progress Report Summary Details January to March, 2025

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2025-30119 (31/07/2025)
Name of the Registered project Unique Apex Towers Phase I Registration No. of the Project RAJ/P/2017/453
Name of the Promoter MANTRA LIFESTYLE HOMES PRIVATE LIMITED Name of other Promoter(s) HIRA REAL ESTATE AND PROPERTIES PVT LTD
Project Address Khasra No./ Plot No.550/1, 550/2, 550/3 , Village- Pal , Pal Road , Jodhpur - 342008 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 210
Total Area of Project(In sq. meters) 19,819.45 Phase Area (In sq. meters) 13,964.82
Registration certificate is valid upto 31-07-2020 Registration extended upto 31-07-2025
II. Number and type of apartments booked ( January to March, 2025 )
Building Name : Unique Apex Towers
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Type -A Block - 1 73.31 8.73 60 57
2BHK Type -B Block - 1 69.26 10.01 30 26
3BHK Block - 1 95.37 12.00 60 50
3BHK+SER+Type-A Block - 1 114.95 11.28 10 10
3BHK+SER+Type-B Block - 1 111.55 12.32 50 40
Total 210 183 210
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( January to March, 2025 )

TABLE - A

Building Name: Unique Apex Towers
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 11 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 80 90.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 66 66.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 60 65.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 58 58.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 35 35.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 45 0
2 Water Supply 20 0
3 Sewerage (chamber, lines, Septic Tank STP) 30 0
4 Storm Water Drainss 20 0
5 Landscaping & Tree Planting 35 0
6 Street Lighting 20 0
7 Community Building 35 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
30/04/2025
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( January to March, 2025 )

TABLE - A

Building Name : Unique Apex Towers
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 397,500,000.00 397,500,000.00
2 Cost incurred against the estimated cost 245,056,250.00 266,564,000.00
3 Work done (as Percentage of the estimated cost) % 62 67.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 152,443,750.00 130,936,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 40,000,000.00 40,000,000.00
2 Cost incurred against the estimated cost 9,296,000.00 9,940,000.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 23.00 25.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 30,704,000.00 30,060,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/04/2025
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( January to March, 2025 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 306,400,000.00 208,286,566.00 208,286,566.00
B. Development Cost/Cost of Construction 437,500,000.00 280,762,121.00 280,835,321.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 489,048,687.00 489,121,887.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 488,651,193.00 489,048,687.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 397,494.00 73,200.00
Form R3: Date of issue
29/04/2025
Certificate showing no linen or charge on the RERA retention Account :
29/07/2025
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 20
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 30
4 Electrification(Transformer, Solar Energy etc) 10
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 09/01/2015
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/07/2026
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/07/2026
If formation/registration of association of allottees is not proposed, explain reasons thereof

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
• What is the likely date of delayed completion?
31/07/2026
• Duration of Delay with reference to estimated finish/extended date.
-6 Years -72 Months
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : Unique Apex Towers (Apartment : 3BHK, Block : 1, Carpet Area : 95.37 sq. meters) Number Of Apartments: 60,Booked: 50
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B104 Sold Laxmi Kant Pitti
2 . B404 Sold Noopur Vyas /Manish Vyas
3 . D501 Unsold
4 . C604 Sold Tulsi Devi
5 . B304 Sold KAMAL KISHORE SHARMA
6 . B804 Sold Shanti Chand Abani
7 . B904 Sold Gajender Singh Deval
8 . C701 Sold Vikas Kumar Chandak
9 . C504 Sold Sangeeta Khicher
10 . B704 Sold Manju Mehta
11 . C201 Sold Vineet Gupta
12 . B604 Sold Sailesh Mohnot
13 . B201 Sold Alok Kumar Ladhha / Manjulata Ladhha
14 . D1004 Sold Smita/Dungar Chand Jain
15 . D804 Sold Jyothi Choudhary
16 . D701 Sold Ganesh Modi
17 . C904 Sold Suraj Kanwar
18 . B801 Sold Kailash Kumar
19 . C204 Sold Meena Mishra
20 . C301 Sold Om Prakash Soni
21 . D304 Sold Mamta Agarwal
22 . D704 Sold Hemlata Jain /Pankaj Jain
23 . B301 Sold Sunil Kumar
24 . C1004 Unsold
25 . C104 Sold Nitin Rajvanshi
26 . C901 Sold Bhawani Singh Rathore
27 . D401 Sold Prathana Ojha(Divorce Matter)
28 . B504 Sold Gaurav Bhandari / Teena Jain
29 . B601 Sold Palak Singhal / Mayank Agarwal
30 . D204 Sold Arvind Kumar Singh
31 . D301 Sold Sharat Chouhan / Usha Kiran
32 . D901 Unsold
33 . C101 Sold Shrada Choudhary
34 . D1001 Unsold
35 . C801 Sold Prathvi Singh Rathore
36 . C501 Sold Madhubala Bhandari / Sapna Bhandari
37 . D104 Sold Nisha Khalsa / RAGHBIR SINGH KHALSA
38 . Dr. Prabha Sharma Sold B1001
39 . D404 Sold Sulochna Choudhary
40 . D201 Unsold
41 . D504 Sold Anita Mohnot
42 . D604 Sold Ravi Prakash / Usha Sharma
43 . B701 Sold Narayan Singh
44 . C804 Sold Hitpal Singh /Kiran Kanwar
45 . C601 Sold Babita Choudhary
46 . B901 Sold Shashi S Phophalia
47 . D101 Sold Namita Mathur
48 . B101 Sold Rajendra Bhandari
49 . C404 Unsold
50 . C401 Sold Girish Kumar Jangid
51 . D601 Unsold
52 . B204 Sold Mukesh Kumar Bishnoi
53 . D904 Unsold
54 . B401 Sold Madhu Gandhi / Geetika Gandhi
55 . C1001 Unsold
56 . C304 Sold Umrao Kanwar Devi
57 . B501 Sold Shalini Mehta
58 . C704 Sold Rahul Karwa
59 . D801 Unsold
60 . Jagdish Mal Lodha Sold B1004
Building : Unique Apex Towers (Apartment : 3BHK+SER+Type-B, Block : 1, Carpet Area : 111.55 sq. meters) Number Of Apartments: 50,Booked: 40
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . D402 Sold Ravindra Kumar Jain / Ritu Jain
2 . B802 Sold Raj Rani Saran
3 . D1003 Unsold
4 . C602 Sold Vinit Agarwal
5 . C102 Sold Manjeet Kaur Kheda
6 . C403 Sold Nand Lal Bhati
7 . B902 Sold Vinita Mathur
8 . B402 Sold Ruchi Singhal
9 . D302 Unsold
10 . D203 Sold Saiyad Yawar Hussain / Ziavi Fatma
11 . D602 Unsold
12 . D803 Unsold
13 . C803 Sold Sumit Agarwal
14 . C203 Sold Keerti Rathore / Gajendra Singh Rathore
15 . D202 Sold Anita Jain
16 . D403 Sold Meena Bhandari/Puneet Bhandari
17 . D502 Sold Arun Kumar Charan
18 . C503 Sold Akhil Mehta
19 . C702 Sold A.K.Pareek
20 . D902 Unsold
21 . C802 Sold Dharmendra Patwa
22 . B702 Sold Ankit Jain
23 . C1003 Sold Dinesh Mangal / Neetu Mangal
24 . D903 Unsold
25 . C603 Sold Vijay Kumari Naruka
26 . C902 Sold Vishweshwar Tiwari
27 . B202 Sold Mohan Singh / HAR KANWAR
28 . D503 Sold Kishan Kansara
29 . C402 Sold N.M. Birla Stone International P.Ltd.
30 . B102 Sold Rajendra Singh Rathore
31 . D802 Unsold
32 . B502 Sold Manoj Kumar Hinger (HUF)
33 . C1002 Sold Anil Mittal
34 . D1002 Unsold
35 . D603 Unsold
36 . B602 Sold Bikram Singh Yadav / VAIBHAV YADUVANSHI
37 . D702 Sold Rakhi Singh
38 . C303 Sold Ravi Sancheti
39 . C202 Sold Khushi Ram Chhatwani
40 . B1002 Sold Sunita Bhandari / RAJEEV BHANDARI
41 . C703 Sold Anil Agarwal
42 . C502 Sold Tanmay Singh / SANVI SINGH
43 . C302 Unsold
44 . B302 Sold Rakesh Rathi
45 . D103 Sold Sumit Sharma
46 . D102 Sold Ram Singh Rajpurohit / Karan Singh Rajpurohit
47 . C103 Sold Shakuntala Vyas / Dr. O.P.Vyas
48 . D303 Sold Megha Verma/ Prem Verma
49 . D703 Sold Manisha Lashkari / Tapan
50 . C903 Sold Sangeeta Purohit / Dr. Prashant Purohit
Building : Unique Apex Towers (Apartment : 2BHK Type -A, Block : 1, Carpet Area : 73.31 sq. meters) Number Of Apartments: 60,Booked: 57
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B207 Sold Madhu Kothari
2 . D405 Sold Puneet Sharma/ DEEPIKA SHARMA
3 . C807 Sold Sunil Kumar Singhal
4 . D207 Sold Unni Raja Sharma / JAYA INDRA
5 . D607 Sold Renu Mittal
6 . C405 Sold Vikas Rathi
7 . B905 Sold Rajendra Mal Mathur
8 . C707 Sold Ashok Kumar Jain
9 . C607 Sold U.D. Sharma
10 . C107 Sold Roja Rani Shamith
11 . D907 Sold Ankur Mathur / Shruti Mathur(legal Case)
12 . B1007 Sold Supriti Chodhary
13 . D105 Sold Mahendra Ku. Bohra / Aditya Bohra
14 . D205 Sold Suraj Mewara / JAYA MEWARA
15 . B705 Sold Anand Raneja
16 . C1005 Sold Tulsaram Patel / Kanaram Patel
17 . D807 Sold Leena Chouhan/ Devendra Singh Bhati
18 . C307 Sold Umrao Kanwar Devi
19 . D507 Sold Mayank Bhandari/ Sweta Bhandari
20 . D107 Sold Dr. Swarn Lata / Dr. Praveen K. Anand
21 . D705 Sold Dr. Vanka Ram Choudhary / Pravin Chaudhary(cancel)
22 . C907 Sold Shilpi Shyamsukha
23 . B907 Sold Mamta Devi
24 . C407 Sold Surendra Kumar Jain
25 . C105 Sold Vinod Kumar Agarwal
26 . D307 Sold Abhishek Mehta Abhinav Mehta
27 . B405 Sold Shyam Sunder Bhatter
28 . B105 Sold Anil Singhvi / Shilpi Singhvi
29 . B605 Sold Shambhu Dayal Mahawar
30 . B205 Sold Dr. Manish Dodwani
31 . B807 Sold Om Prakash Mehta
32 . C605 Sold Ajay Rathi
33 . D1005 Unsold
34 . C207 Sold Satyanarayan Mewara/ Ashok Mewara
35 . B307 Sold Renuka Kumari / Dongarmal Jeengar
36 . B607 Sold Phaulal Songara
37 . D505 Sold Sumit Jain / SHANTI DEVI
38 . D305 Sold Priyanka Chouhan / DILEEP SINGH CHOUHAN
39 . C505 Sold Ranjeeta Jain / RAJ KUMAR JAIN
40 . C805 Sold Nandkishore Rathi / Deepak Rathi
41 . C507 Sold Sukh Ram
42 . B805 Sold R.C. Tayal
43 . B1005 Sold Rajesh Soni
44 . B507 Sold Ramkumar / Vishal Singhal
45 . C705 Sold Dharmendra Sharma / SEEMA SHARMA
46 . D905 Sold Chota Ram Barupal
47 . D1007 Unsold
48 . B305 Sold Jigyasa Goliya / Akshaya Mehta
49 . C205 Sold Dinesh Kumar Bothra / DEEPIKA BOOTHRA
50 . B107 Sold Hemant Kumar Garg
51 . D605 Sold Renu Mittal
52 . C905 Sold Sanjay Shripatrao Mali / Aparna Magar
53 . D407 Sold Jitendra Kumar Garg
54 . D707 Sold Taj Kanwar
55 . C305 Sold Arun Kumar Rao
56 . D805 Unsold
57 . C1007 Sold Rajendra Kumar Soni
58 . B707 Sold Anand Bissa
59 . B407 Sold Praveen Soni / VARSHA SONI
60 . B505 Sold Nalini Maheshwari
Building : Unique Apex Towers (Apartment : 3BHK+SER+Type-A, Block : 1, Carpet Area : 114.95 sq. meters) Number Of Apartments: 10,Booked: 10
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B503 Sold Arpit Kumar
2 . B403 Sold Dr. Rashmi Vyas
3 . B303 Sold Madhu Singhvi
4 . B1003 Sold Yogesh / Prathna Ojha
5 . B603 Sold Shalini Goyal / J.R.Singhvi
6 . B803 Sold Jyoti Pareek
7 . B903 Sold Rishabh Pareek
8 . B103 Sold Laxmi Kant Pitti
9 . B203 Sold Manish Kumar Bansal
10 . B703 Sold Kirti Jain
Building : Unique Apex Towers (Apartment : 2BHK Type -B, Block : 1, Carpet Area : 69.26 sq. meters) Number Of Apartments: 30,Booked: 26
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . C906 Sold Nirmala Devi
2 . C306 Sold Ashok Kumar
3 . D606 Sold Urmila Sharma
4 . B406 Sold Vineet Jain
5 . D406 Unsold
6 . B606 Sold Govind Agarwal
7 . D106 Sold Surendra Singh Charan
8 . C606 Sold Raja Ram Choudhary
9 . D306 Sold Amit Daga
10 . C706 Sold Amit Singhal
11 . B106 Sold Surendra Singh
12 . B906 Sold Vikas Paliwal
13 . D506 Unsold
14 . B1006 Sold Raj Mathur
15 . C406 Sold C M M Sharma
16 . D706 Sold Kamal Kishor Sharma
17 . C806 Sold Parvat Singh Rathore
18 . B306 Sold Shanti Devi
19 . D206 Sold Bharti Devi Meghnani
20 . C506 Sold Parmila Goyal
21 . B506 Sold Manisha Pagariya
22 . D906 Sold Anamika Bohra/Rajesh Bohra
23 . B206 Sold Paras Mal Daga
24 . C206 Sold Vinod Rathi
25 . C1006 Sold Diva Mehta
26 . C106 Sold Pawan Pagariya
27 . B806 Sold Jagdish Chand Jain
28 . D1006 Unsold
29 . D806 Unsold
30 . B706 Sold Natural Estates Pvt. Ltd.
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Fee 10000.00 Print Receipt QPR Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Rs.10000/- DEPOSITED BY RERA TRANS. NO.2279 DATED 31.07.2025 FOR QPR. 8/4/2025 PENDING WITH NODAL OFFICER
2 Law Officer (27634) "Discrepancy in form R1 TABLE-A R1:Certificate from Architect to be provided as per format in RERA Regulations (complete Tower B, Tower C and Tower D not mentioned). TABLE-B Sr.no.1-Internal Roads & Footpaths-This Percentage figure is not correct. Sr.no.2-Water Supply-This Percentage figure is not correct. Sr.no.3-Sewerage (chamber, lines, Septic Tank STP)-This Percentage figure is not correct. Sr.no.4-Storm Water Drains -This Percentage figure is not correct. Sr.no.5-Landscaping & Tree Planting-This Percentage figure is not correct. Sr.no.6-Street Lighting-This Percentage figure is not correct. Sr.no.7-Community Building-This Percentage figure is not correct. Sr.no.13-Electrical meter room, sub-station, receiving station-This Percentage figure is not correct. Discrepancy in form R2 TABLE-A R2: Tower B, Tower C and Tower D in certificate and portal does not match. TABLE-B Sr.no.1-Total Estimated cost of the Internal and External Development Works including amenities and Facilities-This figure is not correct. Sr.no.4-Balanced Cost to be Incurred (Based on Estimated Cost)-This figure is not correct. Discrepancy in form R3 Sr.no.1 (A) -Land Cost / Incurred Amount Current Quarter-This figure is not correct. (C) -Total project cost(A+B)-Incurred Amount / Current Quarter-This figure is not correct. Sr.no.4-Percentage Completion of construction work (as per Project Engineer's Certificate, R-2)-This Percentage figure is not correct. Sr.no.6-Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost-This Percentage figure is not correct. Sr.no.7-Amount Which can be withdrawn from the separate Account-This figure is not correct. Sr.no.8-Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements-This figure is not correct. Sr.no.9-Net Amount Which can be withdrawn from the Separate bank account under this certificate-This figure is not correct R3: Certificate from CA to be provided as per format in RERA Regulations. R3: Estimation of onsite expenses and statutory expenses to be provided and cost need to be properly bifurcated among all heads instead of merging with construction cost. R3: Certificate is not physically signed and stamped by CA (sign and seal are copy pasted on certificate) Others: The Certificate showing no line or charge on the RERA retention Account is not for the said quarter, the uploaded certificate is of previous quarter. Kindly update " 8/5/2025 APPLICATION OBJECTED