QPR Summary

RERA
Quarterly Progress Report Summary Details April to June, 2025

Quarterly Progress Report Summary Details April to June, 2025

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2025-29512 (26/07/2025)
Name of the Registered project MJB ATHULYAM II Registration No. of the Project RAJ/P/2025/3580
Name of the Promoter MJB Build Developers Name of other Promoter(s) None
Project Address Khasra No./ Plot No.Plot No. 4 (Res.) , Village- CHAK KAROL , in scheme :– Shiv Shakti Nagar Vistar (Niji Khatedari) , Jaipur - 302017 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 24
Total Area of Project(In sq. meters) 758.05 Phase Area (In sq. meters) 758.05
Registration certificate is valid upto 31-05-2027 Registration extended upto Not Applicable
II. Number and type of apartments booked ( April to June, 2025 )
Building Name : MJB ATHULYAM II
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
FLAT NO. 101 TO 501 (3 BHK) BLOCK 1 87.24 5.94 5 0
FLAT NO. 102 TO 502 (3 BHK) BLOCK 1 84.63 6.96 5 0
FLAT NO. 103 TO 603 (3 BHK) BLOCK 1 88.07 5.59 6 0
FLAT NO. 104 TO 604 (3 BHK) BLOCK 1 83.80 7.56 6 0
FLAT NO. 601 and Private Terrace T-1 BLOCK 1 87.24 5.94 1 0
FLAT NO. 602 and Private Terrace T-2 BLOCK 1 84.63 6.96 1 0
Private Terrace T3 BLOCK 1 0.00 0.00 0 0
Total 24 0 0
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2025 )

TABLE - A

Building Name: MJB ATHULYAM II
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 0 Number of Basement(s) and Plinth 100 100.00
3 0 Number of Stilt Floor 100 100.00
4 0 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 100 100.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 100 100.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 100 100.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 100 100.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 100 100.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 100 100
3 Sewerage (chamber, lines, Septic Tank STP) 100 100
4 Storm Water Drainss 100 100
5 Landscaping & Tree Planting 90 100
6 Street Lighting 0 0
7 Community Building 100 100
8 Treatment and disposal of sewage and sullage water 100 100
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 90 100
11 Energy management 100 100
12 Fire protection and fire safety requirements 95 100
13 Electrical meter room, sub-station, receiving station 95 100
Form R1: Date of issue
16/04/2025
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2025 )

TABLE - A

Building Name : MJB ATHULYAM II
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 60,000,000.00 60,000,000.00
2 Cost incurred against the estimated cost 60,000,000.00 0.00
3 Work done (as Percentage of the estimated cost) % 100 0.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 0.00 60,000,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 1,400,000.00 0.00
2 Cost incurred against the estimated cost 1,400,000.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 100.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 0.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
18/04/2025
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( April to June, 2025 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 23,512,423.00 8,110,875.00 8,110,875.00
B. Development Cost/Cost of Construction 61,400,000.00 45,167,831.00 45,276,486.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 53,278,706.00 53,387,361.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 0.00 0.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 53,278,706.00 53,387,361.00
Form R3: Date of issue
23/07/2025
Certificate showing no linen or charge on the RERA retention Account :
22/07/2025
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 100
2 Rain Water Harvesting/ Recharging 100
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 100
4 Electrification(Transformer, Solar Energy etc) 100
5 Fire Fighting Provision 100
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 21/05/2024
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 30/09/2025

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
• Date of completion certificate.
18/05/2025
• Has the Completion certificate been uploaded on RERA web portal?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : MJB ATHULYAM II (Apartment : FLAT NO. 101 TO 501 (3 BHK), Block : BLOCK 1, Carpet Area : 87.24 sq. meters) Number Of Apartments: 5,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 301 Unsold
2 . FLAT NO. 401 Unsold
3 . FLAT NO. 501 Unsold
4 . FLAT NO. 201 Unsold
5 . FLAT NO. 101 Unsold
Building : MJB ATHULYAM II (Apartment : FLAT NO. 104 TO 604 (3 BHK), Block : BLOCK 1, Carpet Area : 83.80 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 204 Unsold
2 . FLAT NO. 304 Unsold
3 . FLAT NO. 604 Unsold
4 . FLAT NO. 104 Unsold
5 . FLAT NO. 504 Unsold
6 . FLAT NO. 404 Unsold
Building : MJB ATHULYAM II (Apartment : FLAT NO. 102 TO 502 (3 BHK), Block : BLOCK 1, Carpet Area : 84.63 sq. meters) Number Of Apartments: 5,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 202 Unsold
2 . FLAT NO. 302 Unsold
3 . FLAT NO. 502 Unsold
4 . FLAT NO. 102 Unsold
5 . FLAT NO. 402 Unsold
Building : MJB ATHULYAM II (Apartment : FLAT NO. 103 TO 603 (3 BHK), Block : BLOCK 1, Carpet Area : 88.07 sq. meters) Number Of Apartments: 6,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 103 Unsold
2 . FLAT NO. 503 Unsold
3 . FLAT NO. 203 Unsold
4 . FLAT NO. 603 Unsold
5 . FLAT NO. 403 Unsold
6 . FLAT NO. 303 Unsold
Building : MJB ATHULYAM II (Apartment : FLAT NO. 602 and Private Terrace T-2, Block : BLOCK 1, Carpet Area : 84.63 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 602 and Private Terrace T-2 Unsold
Building : MJB ATHULYAM II (Apartment : FLAT NO. 601 and Private Terrace T-1, Block : BLOCK 1, Carpet Area : 87.24 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . FLAT NO. 601 and Private Terrace T-1 Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) Qpr may be approved subject to verification. 7/29/2025 Application Approved