Quarterly Progress Report Summary Details July to September, 2024

Quarterly Progress Report Summary Details July to September, 2024

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2024-25349 (15/11/2024)
Name of the Registered project Udhyan Apartment HIG-B (B+S+9) 180 Nos. & MIG-B (B+S+9) 108 Nos. Sec. 21 E, Chopasni Housing Board Jodhpur Registration No. of the Project RAJ/P/2023/2482
Name of the Promoter RAJASTHAN HOUSING BOARD Name of other Promoter(s) None
Project Address Khasra No./ Plot No.Khasra No. 881/1/751 (Part), 883/751 (Part), 853/751 (Part) , Village- Jodhpur , Sector 21 E, CHOPASANI HOUSING BOARD , Jodhpur - 342003 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 288
Total Area of Project(In sq. meters) 18,560.00 Phase Area (In sq. meters) 3,591.68
Registration certificate is valid upto 31-12-2028 Registration extended upto Not Applicable
II. Number and type of apartments booked ( July to September, 2024 )
Building Name : Udhyan Apartment
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
3 BHK (HIG) Block O 107.05 12.80 36 0
3 BHK (HIG) Block P 107.05 12.80 36 0
3 BHK (HIG) Block Q 107.05 12.80 36 0
3 BHK (HIG) Block R 107.05 12.80 36 0
3 BHK (HIG) Block S 107.05 12.80 36 0
3 BHK (MIG-B) Block L 84.83 10.89 36 0
3 BHK (MIG-B) Block M 84.83 10.89 36 0
3 BHK (MIG-B) Block N 84.83 10.86 36 0
Total 288 0 0
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2024 )

TABLE - A

Building Name: Udhyan Apartment
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 0 0.00
2 0 Number of Basement(s) and Plinth 0 0.00
3 0 Number of Stilt Floor 0 0.00
4 1 Number of Slabs of Super Structure 0 0.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 0 0.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 0.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 0 0
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
30/09/2024
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2024 )

TABLE - A

Building Name : Udhyan Apartment
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 1,185,000,000.00 1,185,000,000.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done (as Percentage of the estimated cost) % 0 0.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 1,185,000,000.00 1,185,000,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 250,000,000.00 250,000,000.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 0.00 250,000,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/09/2024
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2024 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 503,630,000.00 503,630,000.00 503,630,000.00
B. Development Cost/Cost of Construction 1,435,000,000.00 0.00 0.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 503,630,000.00 503,630,000.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 0.00 0.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 503,630,000.00 503,630,000.00
Form R3: Date of issue
14/11/2024
Certificate showing no linen or charge on the RERA retention Account :
31/07/2024
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0 31/12/2028
2 Rain Water Harvesting/ Recharging 0 31/12/2028
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0 31/12/2028
4 Electrification(Transformer, Solar Energy etc) 0 31/12/2028
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 17/03/2023
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/12/2028

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block S, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/S-901 Unsold
2 . 21 E/S-902 Unsold
3 . 21 E/S-903 Unsold
4 . 21 E/S-403 Unsold
5 . 21 E/S-201 Unsold
6 . 21 E/S-202 Unsold
7 . 21 E/S-604 Unsold
8 . 21 E/S-602 Unsold
9 . 21 E/S-801 Unsold
10 . 21 E/S-702 Unsold
11 . 21 E/S-401 Unsold
12 . 21 E/S-304 Unsold
13 . 21 E/S-303 Unsold
14 . 21 E/S-803 Unsold
15 . 21 E/S-104 Unsold
16 . 21 E/S-404 Unsold
17 . 21 E/S-701 Unsold
18 . 21 E/S-101 Unsold
19 . 21 E/S-204 Unsold
20 . 21 E/S-804 Unsold
21 . 21 E/S-802 Unsold
22 . 21 E/S-703 Unsold
23 . 21 E/S-504 Unsold
24 . 21 E/S-601 Unsold
25 . 21 E/S-103 Unsold
26 . 21 E/S-704 Unsold
27 . 21 E/S-502 Unsold
28 . 21 E/S-102 Unsold
29 . 21 E/S-301 Unsold
30 . 21 E/S-501 Unsold
31 . 21 E/S-904 Unsold
32 . 21 E/S-203 Unsold
33 . 21 E/S-503 Unsold
34 . 21 E/S-302 Unsold
35 . 21 E/S-603 Unsold
36 . 21 E/S-402 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block L, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/L-802 Unsold
2 . 21 E/L-602 Unsold
3 . 21 E/L-404 Unsold
4 . 21 E/L-201 Unsold
5 . 21 E/L-403 Unsold
6 . 21 E/L-804 Unsold
7 . 21 E/L-904 Unsold
8 . 21 E/L-501 Unsold
9 . 21 E/L-704 Unsold
10 . 21 E/L-601 Unsold
11 . 21 E/L-103 Unsold
12 . 21 E/L-204 Unsold
13 . 21 E/L-801 Unsold
14 . 21 E/L-304 Unsold
15 . 21 E/L-203 Unsold
16 . 21 E/L-803 Unsold
17 . 21 E/L-302 Unsold
18 . 21 E/L-504 Unsold
19 . 21 E/L-903 Unsold
20 . 21 E/L-701 Unsold
21 . 21 E/L-703 Unsold
22 . 21 E/L-303 Unsold
23 . 21 E/L-301 Unsold
24 . 21 E/L-702 Unsold
25 . 21 E/L-202 Unsold
26 . 21 E/L-902 Unsold
27 . 21 E/L-603 Unsold
28 . 21 E/L-502 Unsold
29 . 21 E/L-901 Unsold
30 . 21 E/L-101 Unsold
31 . 21 E/L-104 Unsold
32 . 21 E/L-102 Unsold
33 . 21 E/L-402 Unsold
34 . 21 E/L-401 Unsold
35 . 21 E/L-503 Unsold
36 . 21 E/L-604 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block M, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/M-803 Unsold
2 . 21 E/M-201 Unsold
3 . 21 E/M-203 Unsold
4 . 21 E/L-604 Unsold
5 . 21 E/M-104 Unsold
6 . 21 E/L-204 Unsold
7 . 21 E/L-804 Unsold
8 . 21 E/M-302 Unsold
9 . 21 E/M-301 Unsold
10 . 21 E/M-102 Unsold
11 . 21 E/M-501 Unsold
12 . 21 E/M-603 Unsold
13 . 21 E/M-503 Unsold
14 . 21 E/L-304 Unsold
15 . 21 E/M-101 Unsold
16 . 21 E/M-402 Unsold
17 . 21 E/L-504 Unsold
18 . 21 E/M-602 Unsold
19 . 21 E/M-702 Unsold
20 . 21 E/M-502 Unsold
21 . 21 E/L-704 Unsold
22 . 21 E/M-202 Unsold
23 . 21 E/M-801 Unsold
24 . 21 E/M-901 Unsold
25 . 21 E/M-902 Unsold
26 . 21 E/M-703 Unsold
27 . 21 E/M-403 Unsold
28 . 21 E/M-802 Unsold
29 . 21 E/M-303 Unsold
30 . 21 E/M-103 Unsold
31 . 21 E/M-401 Unsold
32 . 21 E/L-904 Unsold
33 . 21 E/M-701 Unsold
34 . 21 E/M-601 Unsold
35 . 21 E/L-404 Unsold
36 . 21 E/M-903 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block R, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/R-104 Unsold
2 . 21 E/R-601 Unsold
3 . 21 E/R-503 Unsold
4 . 21 E/R-201 Unsold
5 . 21 E/R-103 Unsold
6 . 21 E/R-402 Unsold
7 . 21 E/R-401 Unsold
8 . 21 E/R-704 Unsold
9 . 21 E/R-801 Unsold
10 . 21 E/R-304 Unsold
11 . 21 E/R-504 Unsold
12 . 21 E/R-702 Unsold
13 . 21 E/R-101 Unsold
14 . 21 E/R-204 Unsold
15 . 21 E/R-604 Unsold
16 . 21 E/R-803 Unsold
17 . 21 E/R-301 Unsold
18 . 21 E/R-202 Unsold
19 . 21 E/R-902 Unsold
20 . 21 E/R-501 Unsold
21 . 21 E/R-802 Unsold
22 . 21 E/R-903 Unsold
23 . 21 E/R-302 Unsold
24 . 21 E/R-102 Unsold
25 . 21 E/R-901 Unsold
26 . 21 E/R-203 Unsold
27 . 21 E/R-502 Unsold
28 . 21 E/R-303 Unsold
29 . 21 E/R-602 Unsold
30 . 21 E/R-804 Unsold
31 . 21 E/R-403 Unsold
32 . 21 E/R-404 Unsold
33 . 21 E/R-904 Unsold
34 . 21 E/R-603 Unsold
35 . 21 E/R-703 Unsold
36 . 21 E/R-701 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (MIG-B), Block : Block N, Carpet Area : 84.83 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/N-301 Unsold
2 . 21 E/N-702 Unsold
3 . 21 E/N-402 Unsold
4 . 21 E/N-703 Unsold
5 . 21 E/N-201 Unsold
6 . 21 E/N-704 Unsold
7 . 21 E/N-902 Unsold
8 . 21 E/N-602 Unsold
9 . 21 E/N-603 Unsold
10 . 21 E/N-204 Unsold
11 . 21 E/N-901 Unsold
12 . 21 E/N-903 Unsold
13 . 21 E/N-302 Unsold
14 . 21 E/N-303 Unsold
15 . 21 E/N-203 Unsold
16 . 21 E/N-601 Unsold
17 . 21 E/N-202 Unsold
18 . 21 E/N-904 Unsold
19 . 21 E/N-103 Unsold
20 . 21 E/N-102 Unsold
21 . 21 E/N-801 Unsold
22 . 21 E/N-404 Unsold
23 . 21 E/N-503 Unsold
24 . 21 E/N-804 Unsold
25 . 21 E/N-304 Unsold
26 . 21 E/N-104 Unsold
27 . 21 E/N-802 Unsold
28 . 21 E/N-604 Unsold
29 . 21 E/N-803 Unsold
30 . 21 E/N-101 Unsold
31 . 21 E/N-401 Unsold
32 . 21 E/N-701 Unsold
33 . 21 E/N-403 Unsold
34 . 21 E/N-501 Unsold
35 . 21 E/N-502 Unsold
36 . 21 E/N-504 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block O, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/O-602 Unsold
2 . 21 E/O-403 Unsold
3 . 21 E/O-503 Unsold
4 . 21 E/O-302 Unsold
5 . 21 E/O-404 Unsold
6 . 21 E/O-103 Unsold
7 . 21 E/O-104 Unsold
8 . 21 E/O-904 Unsold
9 . 21 E/O-101 Unsold
10 . 21 E/O-601 Unsold
11 . 21 E/O-903 Unsold
12 . 21 E/O-203 Unsold
13 . 21 E/O-303 Unsold
14 . 21 E/O-501 Unsold
15 . 21 E/O-603 Unsold
16 . 21 E/O-202 Unsold
17 . 21 E/O-801 Unsold
18 . 21 E/O-901 Unsold
19 . 21 E/O-201 Unsold
20 . 21 E/O-402 Unsold
21 . 21 E/O-902 Unsold
22 . 21 E/O-802 Unsold
23 . 21 E/O-704 Unsold
24 . 21 E/O-204 Unsold
25 . 21 E/O-604 Unsold
26 . 21 E/O-702 Unsold
27 . 21 E/O-301 Unsold
28 . 21 E/O-701 Unsold
29 . 21 E/O-703 Unsold
30 . 21 E/O-804 Unsold
31 . 21 E/O-803 Unsold
32 . 21 E/O-102 Unsold
33 . 21 E/O-502 Unsold
34 . 21 E/O-304 Unsold
35 . 21 E/O-504 Unsold
36 . 21 E/O-401 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block P, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/P-601 Unsold
2 . 21 E/P-802 Unsold
3 . 21 E/P-804 Unsold
4 . 21 E/P-602 Unsold
5 . 21 E/P-304 Unsold
6 . 21 E/P-102 Unsold
7 . 21 E/P-803 Unsold
8 . 21 E/P-504 Unsold
9 . 21 E/P-904 Unsold
10 . 21 E/P-902 Unsold
11 . 21 E/P-402 Unsold
12 . 21 E/P-901 Unsold
13 . 21 E/P-104 Unsold
14 . 21 E/P-501 Unsold
15 . 21 E/P-801 Unsold
16 . 21 E/P-604 Unsold
17 . 21 E/P-101 Unsold
18 . 21 E/P-702 Unsold
19 . 21 E/P-201 Unsold
20 . 21 E/P-903 Unsold
21 . 21 E/P-404 Unsold
22 . 21 E/P-303 Unsold
23 . 21 E/P-503 Unsold
24 . 21 E/P-704 Unsold
25 . 21 E/P-401 Unsold
26 . 21 E/P-701 Unsold
27 . 21 E/P-703 Unsold
28 . 21 E/P-502 Unsold
29 . 21 E/P-203 Unsold
30 . 21 E/P-403 Unsold
31 . 21 E/P-204 Unsold
32 . 21 E/P-202 Unsold
33 . 21 E/P-302 Unsold
34 . 21 E/P-603 Unsold
35 . 21 E/P-301 Unsold
36 . 21 E/P-103 Unsold
Building : Udhyan Apartment (Apartment : 3 BHK (HIG), Block : Block Q, Carpet Area : 107.05 sq. meters) Number Of Apartments: 36,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 21 E/Q-801 Unsold
2 . 21 E/Q-604 Unsold
3 . 21 E/Q-502 Unsold
4 . 21 E/Q-204 Unsold
5 . 21 E/Q-501 Unsold
6 . 21 E/Q-901 Unsold
7 . 21 E/Q-203 Unsold
8 . 21 E/Q-602 Unsold
9 . 21 E/Q-301 Unsold
10 . 21 E/Q-402 Unsold
11 . 21 E/Q-804 Unsold
12 . 21 E/Q-704 Unsold
13 . 21 E/Q-703 Unsold
14 . 21 E/Q-101 Unsold
15 . 21 E/Q-403 Unsold
16 . 21 E/Q-103 Unsold
17 . 21 E/Q-903 Unsold
18 . 21 E/Q-603 Unsold
19 . 21 E/Q-302 Unsold
20 . 21 E/Q-702 Unsold
21 . 21 E/Q-102 Unsold
22 . 21 E/Q-802 Unsold
23 . 21 E/Q-104 Unsold
24 . 21 E/Q-201 Unsold
25 . 21 E/Q-904 Unsold
26 . 21 E/Q-404 Unsold
27 . 21 E/Q-701 Unsold
28 . 21 E/Q-401 Unsold
29 . 21 E/Q-503 Unsold
30 . 21 E/Q-304 Unsold
31 . 21 E/Q-803 Unsold
32 . 21 E/Q-902 Unsold
33 . 21 E/Q-601 Unsold
34 . 21 E/Q-303 Unsold
35 . 21 E/Q-202 Unsold
36 . 21 E/Q-504 Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) QPR MAY BE ACCEPTED SUBJECT TO VERIFICATION. 12/8/2024 Application Approved