QPR Summary

RERA
Quarterly Progress Report Summary Details July to September, 2023

Quarterly Progress Report Summary Details July to September, 2023

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2023-20634 (31/10/2023)
Name of the Registered project The Hills Phase-II Registration No. of the Project RAJ/P/2023/2378
Name of the Promoter INDRAPAL SINGH Name of other Promoter(s) None
Project Address Khasra No./ Plot No.170 , Village- Gholeta , , Alwar - 301001 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 112
Total Area of Project(In sq. meters) 7,700.00 Phase Area (In sq. meters) 3,157.00
Registration certificate is valid upto 31-03-2029 Registration extended upto Not Applicable
II. Number and type of apartments booked ( July to September, 2023 )
Building Name : The Hills Phase-II
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
LIG 2BHK 1 46.96 6.96 28 0
LIG 2BHK 2 46.96 6.96 56 0
MIG 3BHK 1 64.56 3.60 28 0
Total 112 0 0
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2023 )

TABLE - A

Building Name: The Hills Phase-II
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 0 0.00
2 1 Number of Basement(s) and Plinth 0 0.00
3 1 Number of Stilt Floor 0 0.00
4 7 Number of Slabs of Super Structure 0 0.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 0 0.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 0.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 0 0
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
31/10/2023
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2023 )

TABLE - A

Building Name : The Hills Phase-II
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 167,500,000.00 0.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done (as Percentage of the estimated cost) % 0 0.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 167,500,000.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 15,000,000.00 0.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 15,000,000.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
31/10/2023
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2023 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 2,740,550.00 2,740,550.00 2,740,550.00
B. Development Cost/Cost of Construction 182,500,000.00 251,900.00 251,900.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 2,992,450.00 2,992,450.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 0.00 0.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 2,992,450.00 2,992,450.00
Form R3: Date of issue
31/10/2023
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0
4 Electrification(Transformer, Solar Energy etc) 0
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 30/03/2022
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/03/2029

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : The Hills Phase-II (Apartment : MIG 3BHK, Block : 1, Carpet Area : 64.56 sq. meters) Number Of Apartments: 28,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B-702 Unsold
2 . B-703 Unsold
3 . B-104 Unsold
4 . B-202 Unsold
5 . B-301 Unsold
6 . B-103 Unsold
7 . B-404 Unsold
8 . B-201 Unsold
9 . B-403 Unsold
10 . B-204 Unsold
11 . B-203 Unsold
12 . B-101 Unsold
13 . B-503 Unsold
14 . B-502 Unsold
15 . B-704 Unsold
16 . B-102 Unsold
17 . B-501 Unsold
18 . B-604 Unsold
19 . B-304 Unsold
20 . B-401 Unsold
21 . B-303 Unsold
22 . B-402 Unsold
23 . B-601 Unsold
24 . B-504 Unsold
25 . B-603 Unsold
26 . B-701 Unsold
27 . B-602 Unsold
28 . B-302 Unsold
Building : The Hills Phase-II (Apartment : LIG 2BHK, Block : 2, Carpet Area : 46.96 sq. meters) Number Of Apartments: 56,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . D-506 Unsold
2 . D-601 Unsold
3 . D-403 Unsold
4 . D-505 Unsold
5 . D-402 Unsold
6 . D-504 Unsold
7 . D-507 Unsold
8 . D-502 Unsold
9 . D-605 Unsold
10 . D-606 Unsold
11 . D-608 Unsold
12 . D-607 Unsold
13 . D-701 Unsold
14 . D-503 Unsold
15 . D-707 Unsold
16 . D-602 Unsold
17 . D-604 Unsold
18 . D-706 Unsold
19 . D-603 Unsold
20 . D-705 Unsold
21 . D-708 Unsold
22 . D-208 Unsold
23 . D-104 Unsold
24 . D-207 Unsold
25 . D-103 Unsold
26 . D-201 Unsold
27 . D-102 Unsold
28 . D-105 Unsold
29 . D-703 Unsold
30 . D-108 Unsold
31 . D-702 Unsold
32 . D-107 Unsold
33 . D-106 Unsold
34 . D-704 Unsold
35 . D-101 Unsold
36 . D-404 Unsold
37 . D-405 Unsold
38 . D-407 Unsold
39 . D-501 Unsold
40 . D-406 Unsold
41 . D-508 Unsold
42 . D-302 Unsold
43 . D-206 Unsold
44 . D-204 Unsold
45 . D-203 Unsold
46 . D-308 Unsold
47 . D-301 Unsold
48 . D-205 Unsold
49 . D-307 Unsold
50 . D-401 Unsold
51 . D-408 Unsold
52 . D-202 Unsold
53 . D-305 Unsold
54 . D-304 Unsold
55 . D-303 Unsold
56 . D-306 Unsold
Building : The Hills Phase-II (Apartment : LIG 2BHK, Block : 1, Carpet Area : 46.96 sq. meters) Number Of Apartments: 28,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B-305 Unsold
2 . B-306 Unsold
3 . B-308 Unsold
4 . B-307 Unsold
5 . B-405 Unsold
6 . B-507 Unsold
7 . B-206 Unsold
8 . B-208 Unsold
9 . B-506 Unsold
10 . B-207 Unsold
11 . B-505 Unsold
12 . B-508 Unsold
13 . B-407 Unsold
14 . B-706 Unsold
15 . B-707 Unsold
16 . B-605 Unsold
17 . B-406 Unsold
18 . B-708 Unsold
19 . B-408 Unsold
20 . B-607 Unsold
21 . B-705 Unsold
22 . B-606 Unsold
23 . B-608 Unsold
24 . B-205 Unsold
25 . B-106 Unsold
26 . B-105 Unsold
27 . B-107 Unsold
28 . B-108 Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Twinkle Gupta (24068) QPR MAY BE ACCEPTED, SUBJECT TO VERIFICATION. 1/3/2024 Application Approved