II. Number and type of apartments booked ( April to June, 2023 )
Building Name : B-3
Apartment Type
Block Number
Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters)
Area of Exclusive Balcony and Verandah
Total Number of Sanctioned Apartments
Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter
Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
1BHK
1
51.19
8.22
20
20
1BHK+Powder Room
1
55.80
11.70
2
2
2BHK
1
78.20
11.70
18
18
3BHK
1
98.30
12.15
40
36
Total
80
76
1
II. Number and type of apartments booked ( April to June, 2023 )
Building Name : B-7
Apartment Type
Block Number
Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters)
Area of Exclusive Balcony and Verandah
Total Number of Sanctioned Apartments
Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter
Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK
1
78.20
11.70
20
19
3BHK
1
98.30
12.15
40
27
3BHK Large
1
108.92
8.64
10
10
Shop
1
45.95
0.00
1
0
Total
71
56
0
III. Number of parkings allotted
Type
Total No. of Car parking
Total No. of Two Wheeler parking
Total No. of cycle parking
Total No of Mechanical Car Parking
Total No. of parking allocated at the time of registration or by the end of last quarter
Cumulative No. of parking allocated by the end of current quarter
Location
Car
Two Wheelers
Car
Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 )
TABLE - A
Building Name: B-3
S.No.
Task/Activity
Percentage of work done
In Last Quarter
In Current Quarter
1
Excavation
100
100.00
2
1
Number of Basement(s) and Plinth
100
100.00
3
1
Number of Stilt Floor
100
100.00
4
11
Number of Slabs of Super Structure
100
100.00
5
Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises
72
92.00
6
Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises
17
41.00
7
Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks
0
80.00
8
The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing
60
89.00
9
Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment,
Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be required to obtain Occupation/Completion Certificate
0
10.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 )
Building Name: B-7
S.No.
Task/Activity
Percentage of work done
In Last Quarter
In Current Quarter
1
Excavation
100
100.00
2
1
Number of Basement(s) and Plinth
100
100.00
3
1
Number of Stilt Floor
100
100.00
4
1
Number of Slabs of Super Structure
100
100.00
5
Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises
76
95.00
6
Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises
21
45.00
7
Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks
0
85.00
8
The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing
64
91.00
9
Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment,
Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be required to obtain Occupation/Completion Certificate
0
10.00
TABLE - B
Internal and External Development Works for the entire registered Phase/Project
S.No.
Common areas and Facilities/Amenities
Proposed Yes/No
Percentage of work done
Details if any
By the end of Last Quarter
By the end of Current Quarter
1
Internal Roads & Footpaths
0
0
2
Water Supply
0
0
3
Sewerage (chamber, lines, Septic Tank STP)
0
0
4
Storm Water Drainss
1
60
5
Landscaping & Tree Planting
0
0
6
Street Lighting
0
50
7
Community Building
100
100
8
Treatment and disposal of sewage and sullage water
100
100
9
Solid Waste management & Disposal
100
100
10
Water conservation, Rain water harvesting
0
66
11
Energy management
0
0
12
Fire protection and fire safety requirements
0
0
13
Electrical meter room, sub-station, receiving station
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement
for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No.
Common Area And Facilities, Amenities
Proposed
Percentage Of Completion (%)
Drawings uploaded in online Project details or not
If no, Planned date of uploading of these drawings
1
Water Supply
95
No
2
Rain Water Harvesting/ Recharging
86
Yes
No
3
Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
85
Yes
No
4
Electrification(Transformer, Solar Energy etc)
75
Yes
No
5
Fire Fighting Provision
88
Yes
No
6
Others
0
Yes
No
VI. Status of Approvals
A
Noc's/Permission
Present Status
1
NOC for Environment
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
2
NOC for Fire
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
3
Water supply permission
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
4
NOC from Airport Authority of India
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
No Airport in the surrounding
5
Other approval(s) if any,required for the Project
Approval for/of
• Has the NOC/Permission been uploaded on RERA web portal?
• Planned date of uploading NOC/Permission
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
B.
Revision of Building Plans
1
Date of approval of latest Building Plans already uploaded on RERA web portal
15/01/2018
2
Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
Yes
No
• Date of approval of revised building plans
• Has already submitted to RERA for uploading these revised building plans?
Yes
No
» (If Yes)Date of application
» (If No)Planned date of application
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and
(ii) construction of the Real Estate Project.
Has the insurance been obtained?
Yes
No
• Planned date of Insurance
31/12/2024
VIII. Details of Real Estate Agents (if any) engaged for the Project
Has any real estate agents been engaged for the Project?
Yes
No
Sr. No.
Name of real estate agent
Rera registration no. of the real estate agent
No. of units booked
Unit No(s)
1.
Mrs. Neeta Munishwar Kumar
RAJ/P/2021/1554
1
T2-254
IX. Miscellaneous
1. Is there any change in promoter profile which is not yet updated in online promoter profile?
Yes
No
2. Is there any change in project details which is not yet updated in online project profile?
Yes
No
3. Has the Completion Certificate been obtained?
Yes
No
•
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
Yes
No
4. Has the Occupancy Certificate also been obtained?
Yes
No
Allottee Details
Building : B-3 (Apartment : 2BHK, Block : 1, Carpet Area : 78.20 sq. meters) Number Of Apartments: 18,Booked: 18
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
M2-421
Sold
Mrs. Kamlesh Yadav
2 .
M2-319
Sold
Mrs. Rekha Gupta
3 .
M2-821
Sold
Mrs. Gita Kalra
4 .
M2-719
Sold
Mr. Brij Lal Agarwal
5 .
M2-221
Sold
Mrs. Simrat Kaur Narula
6 .
M2-621
Sold
Ms. Ambica Uppal
7 .
M2-921
Sold
Mr. Alak Bihari Sahu
8 .
M2-819
Sold
Mrs. Shalini Bhardwaj
9 .
M2-219
Sold
Mr. Preet Mohan Singh
10 .
M2-519
Sold
Ms. Vinod Bala
11 .
M2-1021
Sold
Mrs. Shobha Bhushan
12 .
M2-1019
Sold
Mrs. Sushma Singh
13 .
M2-721
Sold
Ms. Aanchal Panwar
14 .
M2-521
Sold
Ms. Deepika Sharma
15 .
M2-419
Sold
Mrs. Ruplekha Khullar
16 .
M2-619
Sold
Ms. Naumita Rishi
17 .
M2-919
Sold
Mr. Ashok Kumar Agarwal
18 .
M2-321
Sold
Mr. Vijay Kumar Nishchal
Building : B-7 (Apartment : 3BHK, Block : 1, Carpet Area : 98.30 sq. meters) Number Of Apartments: 40,Booked: 28
Building : B-3 (Apartment : 3BHK, Block : 1, Carpet Area : 98.30 sq. meters) Number Of Apartments: 40,Booked: 38
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
T2-517
Sold
Mrs. Archana
2 .
T2-623
Sold
Mr. Satendra Nath Chaudhry
3 .
T2-918
Sold
Mr. Sharad Chandra Kapoor
4 .
T2-324
Sold
Mr. Pravin Kumar Gupta
5 .
T2-717
Sold
Mr. Abhay Kumar Mittra
6 .
T2-224
Sold
Mrs. Mohini Goel
7 .
T2-823
Sold
Mr. Basant Kumar Kulshreshtha
8 .
T2-217
Sold
Mrs. Shobha Munjal
9 .
T2-524
Sold
Mr. Piyush Jain
10 .
T2-917
Sold
Mr. Gurjeet Singh Talwar
11 .
T2-424
Sold
Mr. Pramod Kumar Gupta
12 .
T2-1023
Sold
Mrs. Anita Saxena
13 .
T2-417
Sold
Mrs. Shobha Singhal
14 .
T2-724
Sold
Mrs. Sunita Kumar
15 .
T2-1018
Sold
Mrs. Deepa Bharani
16 .
T2-317
Sold
Mrs. Jhuma Bose
17 .
T2-923
Sold
Mr. Bhupinder Raj Singh
18 .
T2-423
Sold
Mr. Sudeep Raj Singh Batra
19 .
T2-718
Sold
Mrs. Anita Gupta
20 .
T2-124
Unsold
21 .
T2-218
Unsold
22 .
T2-624
Sold
Mr. Satendra Nath Chaudhry
23 .
T2-123
Sold
Mrs. Nishi Misra Manglik
24 .
T2-617
Sold
Mrs. Sunita Singh
25 .
T2-924
Sold
Mr. Tej Anand
26 .
T2-618
Sold
Mr. Anil Asthana
27 .
T2-1024
Sold
Mrs. Indu Sanghi
28 .
T2-523
Sold
Mr. Ashok Dhar
29 .
T2-1017
Sold
Mrs. Sushma Singh
30 .
T2-318
Unsold
31 .
T2-818
Sold
Mr. Sharad Bhasin
32 .
T2-117
Sold
Mr. Sree Kumar
33 .
T2-723
Sold
Mr. Udai Upendra
34 .
T2-223
Sold
Mr. Aseem Goyal
35 .
T2-518
Sold
Mrs. Lakshmi Prabha Gureja /Mr. Yoginder Pal Gureja
36 .
T2-418
Sold
Mr. Virendra Prasad Goel
37 .
T2-824
Sold
Mr. Suman Ratanlal Gupta
38 .
T2-323
Sold
Mrs. Preeti Khullar
39 .
T2-817
Sold
Mrs. Ayesha Misra
40 .
T2-118
Unsold
Building : B-7 (Apartment : Shop, Block : 1, Carpet Area : 45.95 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
1
Unsold
Building : B-7 (Apartment : 3BHK Large, Block : 1, Carpet Area : 108.92 sq. meters) Number Of Apartments: 10,Booked: 10
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
T3-451
Sold
Mr. Madan Gopal Goel
2 .
T3-1051
Sold
Mrs. Neelam Prasad
3 .
T3-751
Sold
Mr. Vinod Kumar Jain
4 .
T3-351
Sold
Mr. Anand Murti Sharma
5 .
T3-251
Sold
Mrs. Janak Saluja
6 .
T3-851
Sold
Mr. Subhash Kumar Bajaj
7 .
T3-951
Sold
Mr. Surendra Prasad Agarwal
8 .
T3-651
Sold
Mr. Ravindra Joshi
9 .
T3-551
Sold
Mr. Rajiv Arora
10 .
T3-151
Sold
Mr. Yeshwant Singh Thakur
Building : B-3 (Apartment : 1BHK, Block : 1, Carpet Area : 51.19 sq. meters) Number Of Apartments: 20,Booked: 20
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
V2-322
Sold
Mr. Satyapal Singh
2 .
V2-220
Sold
Mrs. Harinder Bali
3 .
V2-922
Sold
Mr. Dharam Pal Singh
4 .
V2-722
Sold
Mrs. Nalini Sinha Patwari
5 .
V2-620
Sold
Ms. Kiran Misra
6 .
V2-222
Sold
Ms. Nirmala Gupta
7 .
V2-120
Sold
Mr. Siddharth Aga
8 .
V2-1020
Sold
Mr. Manohar Lal Chugh
9 .
V2-820
Sold
Ms. Mukulika Ghosh
10 .
V2-522
Sold
Mrs. Sarita Narang
11 .
V2-622
Sold
Mrs. Ravinder Sahi
12 .
V2-520
Sold
Mr. Khadak Singh Thakur
13 .
V2-320
Sold
Dr. Nidhi Sinha
14 .
V2-822
Sold
Mr. Bir Singh Chauhan
15 .
V2-420
Sold
Mrs. Hema Buttan
16 .
V2-720
Sold
Mr. Tarun Thakur
17 .
V2-122
Sold
Mr. Harshal Sood
18 .
V2-1022
Sold
Ms. Amrita Ahluwalia
19 .
V2-920
Sold
Mrs. Reshma Mathur
20 .
V2-422
Sold
Mr. Narender Vashisht
Building : B-7 (Apartment : 2BHK, Block : 1, Carpet Area : 78.20 sq. meters) Number Of Apartments: 20,Booked: 20
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
M2-452
Sold
Mrs. Promila Yadava
2 .
M2-253
Sold
Ms. Raakhee Kharbanda
3 .
M2-1052
Cancelled
4 .
M2-852
Sold
Mr. Ashok Kumar Seth
5 .
M2-653
Sold
Mrs. Clara Droza
6 .
M2-352
Sold
Ms. Anju Mohan
7 .
M2-153
Sold
Mr. Ish Kumar Malhotra
8 .
M2-1053
Sold
Mrs. Anita Arora
9 .
M2-853
Sold
Mr. Arvind Gupta
10 .
M2-652
Sold
Mr. Arun Kumar Jain
11 .
M2-752
Sold
Mrs. Rama Agrawal
12 .
M2-553
Sold
Mrs. Neeru Chopra
13 .
M2-152
Sold
Mr. Mahesh Kumar Gupta
14 .
M2-353
Sold
Ms. Gulshan Gera
15 .
M2-952
Sold
Mrs. Shalini Pant
16 .
M2-453
Sold
Mrs. Usha Kiran
17 .
M2-753
Sold
Mr. Ajoy Kedia
18 .
M2-252
Sold
Mrs. Sangeeta Dhawan Misra
19 .
M2-953
Sold
Mr. Navin Sabharwal
20 .
M2-552
Sold
Mr. Hasmukh Champaklal Mehta
Building : B-3 (Apartment : 1BHK+Powder Room, Block : 1, Carpet Area : 55.80 sq. meters) Number Of Apartments: 2,Booked: 2
Sr.No.
Unit/Flat Detail
Booking Status
Allottee Name
1 .
V3-121
Sold
Ms. Sujata Tat
2 .
V3-119
Sold
Mrs. Saras Gupta
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from.
I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other
legal purposes this undertaking amy serve.