Quarterly Progress Report Summary Details April to June, 2023

Quarterly Progress Report Summary Details April to June, 2023

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2024-23374 (27/06/2024)
Name of the Registered project GOVINDAM PARADISE Registration No. of the Project RAJ/P/2020/1197
Name of the Promoter BRIJHARI BUILDHOME LLP Name of other Promoter(s) None
Project Address Khasra No./ Plot No.92,97/2,98/2 , Village- Sukhiya , Rampura Road, Sanganer , Jaipur - 302020 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 159
Total Area of Project(In sq. meters) 2,922.52 Phase Area (In sq. meters) 2,922.52
Registration certificate is valid upto 23-10-2024 Registration extended upto Not Applicable
II. Number and type of apartments booked ( April to June, 2023 )
Building Name : GOVINDAM PARADISE
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2 BHK-I Block - 1 49.29 5.36 44 3
2 BHK-II Block - 1 48.50 4.85 22 3
2 BHK-III Block - 1 50.20 6.17 11 5
2 BHK-IV Block - 1 50.85 6.47 11 1
3 BHK-I Block - 1 68.71 5.77 11 4
3 BHK-II Block - 1 64.72 5.48 11 3
3 BHK-III Block - 1 67.83 6.26 11 1
3 BHK-IV Block - 1 64.70 4.87 22 5
3 BHK-V Block - 1 70.42 4.48 11 7
Shop I Block - 1 35.68 0.00 1 0
Shop II Block - 1 29.28 0.00 1 0
Shop III Block - 1 28.08 0.00 1 0
Shop IV Block - 1 28.32 0.00 1 0
Shop V Block - 1 26.24 0.00 1 0
Total 159 32 34
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 )

TABLE - A

Building Name: GOVINDAM PARADISE
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 2 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 11 Number of Slabs of Super Structure 82 81.81
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 30 30.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 10 10.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 50 50.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 20 20.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 40 40
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
30/06/2023
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 )

TABLE - A

Building Name : GOVINDAM PARADISE
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 300,000,000.00 300,000,000.00
2 Cost incurred against the estimated cost 267,289,715.00 267,289,715.00
3 Work done (as Percentage of the estimated cost) % 89 89.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 32,710,285.00 32,710,285.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 0.00 0.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 0.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/06/2023
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( April to June, 2023 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 60,000,000.00 60,000,000.00 60,000,000.00
B. Development Cost/Cost of Construction 240,000,000.00 221,198,148.00 239,953,706.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 281,198,148.00 299,953,706.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 55,436,616.00 57,360,287.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 225,761,532.00 242,593,419.00
Form R3: Date of issue
17/06/2024
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0 23/10/2024
2 Rain Water Harvesting/ Recharging 0 23/10/2024
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 40 23/10/2024
4 Electrification(Transformer, Solar Energy etc) 0 23/10/2024
5 Fire Fighting Provision 0 23/10/2024
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 27/01/2020
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 01/10/2024

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : GOVINDAM PARADISE (Apartment : 3 BHK-V, Block : 1, Carpet Area : 70.42 sq. meters) Number Of Apartments: 11,Booked: 10
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 214 Sold ASHUTOSH SHRIVASTAV & ANURADHA SHRIVASTAV
2 . 914 Unsold
3 . 514 Unsold
4 . 1014 Sold PRIYANK MATHUR / MANOJ MATHUR
5 . 314 Sold PRASHANT MISHRA
6 . 614 Sold KAMLESH GUPTA & VIKAS GUPTA
7 . 714 Sold RUPA SHARMA / NEELKANTH SHARMA
8 . 114 Sold RAGHAV AGARWAL
9 . 814 Unsold
10 . 414 Sold MANJU GAUR / DINESH KUMAR GAUR
11 . 1114 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-II, Block : 1, Carpet Area : 48.50 sq. meters) Number Of Apartments: 22,Booked: 3
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 606 Unsold
2 . 209 Unsold
3 . 206 Unsold
4 . 909 Unsold
5 . 406 Unsold
6 . 1106 Unsold
7 . 709 Unsold
8 . 1006 Unsold
9 . 306 Unsold
10 . 609 Unsold
11 . 106 Unsold
12 . 806 Sold DIPALI PUNDIR
13 . 1109 Unsold
14 . 409 Unsold
15 . 109 Unsold
16 . 506 Sold SHARDA MALI / BHARAT LAL MALI
17 . 809 Unsold
18 . 509 Unsold
19 . 906 Sold C.P JAIN / ANITA JAIN
20 . 706 Unsold
21 . 309 Unsold
22 . 1009 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-I, Block : 1, Carpet Area : 68.71 sq. meters) Number Of Apartments: 11,Booked: 6
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 801 Unsold
2 . 701 Sold SUNITA / SUBHASH PARIHAR
3 . 301 Unsold
4 . 1001 Unsold
5 . 101 Sold JOLLY GEORGE
6 . 1101 Unsold
7 . 401 Sold RAJENDRA PRASAD VERMA
8 . 501 Unsold
9 . 601 Unsold
10 . 901 Sold RENU TIWARI & AJAY SHARMA
11 . 201 Sold NAVIN KUMAR BANSAL
Building : GOVINDAM PARADISE (Apartment : 2 BHK-I, Block : 1, Carpet Area : 49.29 sq. meters) Number Of Apartments: 44,Booked: 3
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 205 Unsold
2 . 404 Unsold
3 . 710 Sold BAISHAKHI CHAKROBORTY / DEBASHISH CHAKRABORTY
4 . 1004 Unsold
5 . 905 Unsold
6 . 511 Unsold
7 . 204 Unsold
8 . 510 Unsold
9 . 904 Unsold
10 . 705 Sold SHRUTI MUKHERJEE / ANURAG BANERJEE
11 . 311 Unsold
12 . 1011 Unsold
13 . 1004 Unsold
14 . 410 Unsold
15 . 805 Sold KAJAL PUNDIR
16 . 104 Unsold
17 . 1111 Unsold
18 . 211 Unsold
19 . 405 Unsold
20 . 604 Unsold
21 . 910 Unsold
22 . 1005 Unsold
23 . 711 Unsold
24 . 610 Unsold
25 . 1005 Unsold
26 . 304 Unsold
27 . 105 Unsold
28 . 411 Unsold
29 . 810 Unsold
30 . 110 Unsold
31 . 504 Unsold
32 . 305 Unsold
33 . 611 Unsold
34 . 1010 Unsold
35 . 310 Unsold
36 . 704 Unsold
37 . 505 Unsold
38 . 111 Unsold
39 . 811 Unsold
40 . 210 Unsold
41 . 804 Unsold
42 . 605 Unsold
43 . 1010 Unsold
44 . 911 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-III, Block : 1, Carpet Area : 50.20 sq. meters) Number Of Apartments: 11,Booked: 5
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 407 Sold RAJKUMAR GUPTA / VINDO KUMAR GUPTA
2 . 1107 Unsold
3 . 307 Unsold
4 . 1007 Sold SANJU SAINI / PRADEEP PRAKASH
5 . 607 Sold BRAMHA BANDHAB BANDOPADHYAY / MADHUMITA CHATERJEE
6 . 707 Sold MANOJ GUPTA / HEMLATA GUPTA
7 . 107 Unsold
8 . 807 Unsold
9 . 907 Sold MOUSAM DIN
10 . 207 Unsold
11 . 507 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-II, Block : 1, Carpet Area : 64.72 sq. meters) Number Of Apartments: 11,Booked: 5
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 402 Sold RANDHIR SINGH / RANJANA SINGH
2 . 1102 Unsold
3 . 1002 Unsold
4 . 302 Sold SURYAPAL SINGH SOLANKI / RITU SOLANKI
5 . 602 Unsold
6 . 502 Sold MAMTA DEVI / HARENDRA SINGH
7 . 702 Unsold
8 . 802 Unsold
9 . 102 Sold SIJO N SAM
10 . 202 Unsold
11 . 902 Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-III, Block : 1, Carpet Area : 67.83 sq. meters) Number Of Apartments: 11,Booked: 1
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 703 Unsold
2 . 603 Unsold
3 . 1003 Sold AMITA SHARMA / MOHIT SHARMA
4 . 103 Unsold
5 . 803 Unsold
6 . 303 Unsold
7 . 1103 Unsold
8 . 403 Unsold
9 . 503 Unsold
10 . 903 Unsold
11 . 203 Unsold
Building : GOVINDAM PARADISE (Apartment : Shop III, Block : 1, Carpet Area : 28.08 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-III Unsold
Building : GOVINDAM PARADISE (Apartment : 3 BHK-IV, Block : 1, Carpet Area : 64.70 sq. meters) Number Of Apartments: 22,Booked: 6
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 513 Unsold
2 . 212 Unsold
3 . 912 Unsold
4 . 813 Unsold
5 . 113 Unsold
6 . 512 Unsold
7 . 313 Unsold
8 . 1013 Unsold
9 . 712 Sold PRARTHANA / TARUN NAMA
10 . 213 Unsold
11 . 913 Unsold
12 . 612 Unsold
13 . 412 Sold VARSHA KABRA / MEGHRAJ KABRA
14 . 713 Sold MAHENDRA ENKHIA / SUKHDEV GANDER
15 . 1112 Unsold
16 . 812 Unsold
17 . 1113 Unsold
18 . 413 Sold MUKESH KUMAR VERMA / PRIYANKA TUNWAL
19 . 112 Unsold
20 . 613 Unsold
21 . 1012 Sold RAMINDER KAUR / KARANJEET SINGH
22 . 312 Unsold
Building : GOVINDAM PARADISE (Apartment : 2 BHK-IV, Block : 1, Carpet Area : 50.85 sq. meters) Number Of Apartments: 11,Booked: 1
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . 708 Unsold
2 . 608 Unsold
3 . 208 Unsold
4 . 108 Unsold
5 . 808 Sold VISHAL YADUVANSHI
6 . 1008 Unsold
7 . 308 Unsold
8 . 408 Unsold
9 . 1108 Unsold
10 . 508 Unsold
11 . 908 Unsold
Building : GOVINDAM PARADISE (Apartment : Shop II, Block : 1, Carpet Area : 29.28 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-II Unsold
Building : GOVINDAM PARADISE (Apartment : Shop IV, Block : 1, Carpet Area : 28.32 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-IV Unsold
Building : GOVINDAM PARADISE (Apartment : Shop I, Block : 1, Carpet Area : 35.68 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-I Unsold
Building : GOVINDAM PARADISE (Apartment : Shop V, Block : 1, Carpet Area : 26.24 sq. meters) Number Of Apartments: 1,Booked: 0
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . SHOP-V Unsold
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Fee 5000.00 Print Receipt QPR Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
0 (10373) QPR Pulled by promoter for edit. 6/27/2024 PENDING WITH PROMOTER
1 Veer Bahadur Gurjar (10678) RS.5000/- DEPOSITED BY RERA TRANS. NO.3337 DATED 27.06.2024 FOR QPR QPR MAY BE ACCEPTED, SUBJECT TO VERIFICATION. 6/28/2024 Application Approved