II. Number and type of Plots booked/ allotted/ sold (( January to March, 2020 ))
Plot Area
Plots
Total number of sanctioned plots
Number of Plots booked/ sold/ allotted by the end of last quarter
Cumulative Number of Plots booked/ sold/ allotted by the end of current quarter
92.96
65, 93 to 97, 109 to 116, 119 to 126, 129 to 131, 134 to 137, 140 to 146, 149 to 155, 158 to 162, 165 to 169, 172 to 179, 187 to 192, 195 to 201, 219 to 227, 232 to 238, 241 to 248, 255 to 262, 265 to 272, 279 to 286, 289 to 297
III. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( January to March, 2020 )
TABLE - A
Internal and External Development Works for the entire registered Phase/Project
S.No.
Common areas and Facilities/Amenities
Proposed Yes/No
Percentage of work done
Details if any
By the end of Last Quarter
By the end of Current Quarter
1
Internal Roads & Footpaths
0
100
2
Water Supply
0
100
3
Sewerage (chamber, lines, Septic Tank STP)
0
100
4
Storm Water Drainss
0
0
5
Landscaping & Tree Planting
0
100
6
Street Lighting
0
100
7
Community Building
0
0
8
Treatment and disposal of sewage and sullage water
0
0
9
Solid Waste management & Disposal
0
0
10
Water conservation, Rain water harvesting
0
100
11
Energy management
0
0
12
Fire protection and fire safety requirements
0
0
13
Electrical meter room, sub-station, receiving station
0
0
Form R1: Date of issue
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( January to March, 2020 )
TABLE - A
Internal and External Development Works for the entire registered Phase/Project
S.No.
Particulars
By the end of Last Quarter
By the end of Current Quarter
1
Total Estimated cost of the Internal and External Development Works including amenities and Facilities
₹
0.00
0.00
2
Cost incurred against the estimated cost
₹
0.00
0.00
3
Work done in Percentage (as Percentage of the estimated Cost)
%
0.00
0.00
4
Balanced Cost to be Incurred (Based on Estimated Cost)
₹
0.00
0.00
5
Cost Incurred on Additional/Extra Items not included in the Estimated Cost
₹
0.00
0.00
Form R2: Date of issue
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( January to March, 2020 )
Incurred Amount
S.No..
Particulars
Estimated Amount (as per online details)
By the end of Last Quarter
By the end of Current Quarter
1
A. Land Cost
₹
430,282,940.00
0.00
0.00
B. Development Cost/Cost of Construction
₹
180,000,000.00
0.00
0.00
C. Total project cost(A+B)
₹
In Last Quarter
In Current Quarter
2S.No.
Percentage of total cost incurred on land
%
3
Percentage of total cost incurred on development
%
4
Percentage Completion of construction work (as per Project Engineer's Certificate, R-2)
%
5
Percentage of the Cost incurred on Land Cost to the Total Estimated Cost
%
6
Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost
%
7
Amount Which can be withdrawn from the separate Account
₹
0.00
0.00
8
Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements
₹
0.00
0.00
9
Net Amount Which can be withdrawn from the Separate bank account under this certificate
₹
0.00
0.00
Form R3: Date of issue
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement
for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No.
Common Area And Facilities, Amenities
Proposed
Percentage Of Completion (%)
Drawings uploaded in online Project details or not
If no, Planned date of uploading of these drawings
1
Water Supply
100
No
2
Rain Water Harvesting/ Recharging
100
Yes
No
3
Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
100
Yes
No
4
Electrification(Transformer, Solar Energy etc)
100
Yes
No
5
Fire Fighting Provision
0
Yes
No
6
Others
0
Yes
No
VI. Status of Approvals
A
Noc's/Permission
Present Status
1
NOC for Environment
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
2
NOC for Fire
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
3
Water supply permission
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
4
NOC from Airport Authority of India
• Has the NOC been uploaded on RERA web portal?
• Planned date of uploading NOC
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
As per rules there is no applicability on project
5
Other approval(s) if any,required for the Project
Approval for/of
• Has the NOC/Permission been uploaded on RERA web portal?
• Planned date of uploading NOC/Permission
• Expected date of receipt
• Planned date of application
• Explain why not applicable
Yes
No
B.
Revision of Building Plans
1
Date of approval of latest Building Plans already uploaded on RERA web portal
17/05/2019
2
Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
Yes
No
• Date of approval of revised building plans
• Has already submitted to RERA for uploading these revised building plans?
Yes
No
» (If Yes)Date of application
» (If No)Planned date of application
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and
(ii) construction of the Real Estate Project.
Has the insurance been obtained?
Yes
No
• Planned date of Insurance
31/12/2021
VIII. Details of Real Estate Agents (if any) engaged for the Project
Has any real estate agents been engaged for the Project?
Yes
No
IX. Miscellaneous
1. Is there any change in promoter profile which is not yet updated in online promoter profile?
Yes
No
2. Is there any change in project details which is not yet updated in online project profile?
Yes
No
3. Has the Completion Certificate been obtained?
Yes
No
• Date of completion certificate.
17/02/2020
• Has the Completion certificate been uploaded on RERA web portal?
Yes
No
4. Has the Occupancy Certificate also been obtained?
Yes
No
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from.
I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other
legal purposes this undertaking amy serve.
Payment Details
Comments Details
PARA
Created BY
Comments
Date
Status
Document
1
RUPALSHARMA (20647)
QPR maybe accepted subject to verification.
Submitted for perusal and approval, Please.