QPR Summary

RERA
Quarterly Progress Report Summary Details January to March, 2025

Quarterly Progress Report Summary Details January to March, 2025

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2025-30119 (31/07/2025)
Name of the Registered project Unique Apex Towers Phase I Registration No. of the Project RAJ/P/2017/453
Name of the Promoter MANTRA LIFESTYLE HOMES PRIVATE LIMITED Name of other Promoter(s) HIRA REAL ESTATE AND PROPERTIES PVT LTD
Project Address Khasra No./ Plot No.550/1, 550/2, 550/3 , Village- Pal , Pal Road , Jodhpur - 342008 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 210
Total Area of Project(In sq. meters) 19,819.45 Phase Area (In sq. meters) 13,964.82
Registration certificate is valid upto 31-07-2020 Registration extended upto 31-07-2025
II. Number and type of apartments booked ( January to March, 2025 )
Building Name : Unique Apex Towers
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Type -A Block - 1 73.31 8.73 60 57
2BHK Type -B Block - 1 69.26 10.01 30 26
3BHK Block - 1 95.37 12.00 60 50
3BHK+SER+Type-A Block - 1 114.95 11.28 10 10
3BHK+SER+Type-B Block - 1 111.55 12.32 50 40
Total 210 183 210
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( January to March, 2025 )

TABLE - A

Building Name: Unique Apex Towers
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 11 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 80 90.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 66 66.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 60 65.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 58 58.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 35 35.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 45 0
2 Water Supply 20 0
3 Sewerage (chamber, lines, Septic Tank STP) 30 0
4 Storm Water Drainss 20 0
5 Landscaping & Tree Planting 35 0
6 Street Lighting 20 0
7 Community Building 35 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
30/04/2025
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( January to March, 2025 )

TABLE - A

Building Name : Unique Apex Towers
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 397,500,000.00 397,500,000.00
2 Cost incurred against the estimated cost 245,056,250.00 266,564,000.00
3 Work done (as Percentage of the estimated cost) % 62 67.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 152,443,750.00 130,936,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 40,000,000.00 40,000,000.00
2 Cost incurred against the estimated cost 9,296,000.00 9,940,000.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 23.00 25.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 30,704,000.00 30,060,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/04/2025
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( January to March, 2025 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 306,400,000.00 208,286,566.00 208,286,566.00
B. Development Cost/Cost of Construction 437,500,000.00 280,762,121.00 280,835,321.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 489,048,687.00 489,121,887.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 488,651,193.00 489,048,687.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 397,494.00 73,200.00
Form R3: Date of issue
29/04/2025
Certificate showing no linen or charge on the RERA retention Account :
29/07/2025
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 20
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 30
4 Electrification(Transformer, Solar Energy etc) 10
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 09/01/2015
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/07/2026
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/07/2026
If formation/registration of association of allottees is not proposed, explain reasons thereof

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
• What is the likely date of delayed completion?
31/07/2026
• Duration of Delay with reference to estimated finish/extended date.
-6 Years -72 Months
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : Unique Apex Towers (Apartment : 2BHK Type -B, Block : 1, Carpet Area : 69.26 sq. meters) Number Of Apartments: 30,Booked: 26
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . C106 Sold Pawan Pagariya
2 . D906 Sold Anamika Bohra/Rajesh Bohra
3 . C206 Sold Vinod Rathi
4 . C1006 Sold Diva Mehta
5 . B206 Sold Paras Mal Daga
6 . B806 Sold Jagdish Chand Jain
7 . D1006 Unsold
8 . D806 Unsold
9 . B706 Sold Natural Estates Pvt. Ltd.
10 . B306 Sold Shanti Devi
11 . D706 Sold Kamal Kishor Sharma
12 . C806 Sold Parvat Singh Rathore
13 . D206 Sold Bharti Devi Meghnani
14 . B406 Sold Vineet Jain
15 . C906 Sold Nirmala Devi
16 . C306 Sold Ashok Kumar
17 . D606 Sold Urmila Sharma
18 . D306 Sold Amit Daga
19 . C706 Sold Amit Singhal
20 . B906 Sold Vikas Paliwal
21 . B106 Sold Surendra Singh
22 . D506 Unsold
23 . B1006 Sold Raj Mathur
24 . C406 Sold C M M Sharma
25 . B606 Sold Govind Agarwal
26 . D106 Sold Surendra Singh Charan
27 . D406 Unsold
28 . C606 Sold Raja Ram Choudhary
29 . C506 Sold Parmila Goyal
30 . B506 Sold Manisha Pagariya
Building : Unique Apex Towers (Apartment : 3BHK, Block : 1, Carpet Area : 95.37 sq. meters) Number Of Apartments: 60,Booked: 50
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . C401 Sold Girish Kumar Jangid
2 . D601 Unsold
3 . B204 Sold Mukesh Kumar Bishnoi
4 . B101 Sold Rajendra Bhandari
5 . C404 Unsold
6 . C704 Sold Rahul Karwa
7 . B501 Sold Shalini Mehta
8 . D904 Unsold
9 . C1001 Unsold
10 . C304 Sold Umrao Kanwar Devi
11 . B401 Sold Madhu Gandhi / Geetika Gandhi
12 . D801 Unsold
13 . Jagdish Mal Lodha Sold B1004
14 . D301 Sold Sharat Chouhan / Usha Kiran
15 . D901 Unsold
16 . C101 Sold Shrada Choudhary
17 . B601 Sold Palak Singhal / Mayank Agarwal
18 . D204 Sold Arvind Kumar Singh
19 . C901 Sold Bhawani Singh Rathore
20 . B504 Sold Gaurav Bhandari / Teena Jain
21 . D401 Sold Prathana Ojha(Divorce Matter)
22 . D1001 Unsold
23 . C801 Sold Prathvi Singh Rathore
24 . C501 Sold Madhubala Bhandari / Sapna Bhandari
25 . Dr. Prabha Sharma Sold B1001
26 . B201 Sold Alok Kumar Ladhha / Manjulata Ladhha
27 . C201 Sold Vineet Gupta
28 . B604 Sold Sailesh Mohnot
29 . B704 Sold Manju Mehta
30 . D1004 Sold Smita/Dungar Chand Jain
31 . C1004 Unsold
32 . B301 Sold Sunil Kumar
33 . D304 Sold Mamta Agarwal
34 . D704 Sold Hemlata Jain /Pankaj Jain
35 . C104 Sold Nitin Rajvanshi
36 . C701 Sold Vikas Kumar Chandak
37 . B904 Sold Gajender Singh Deval
38 . B104 Sold Laxmi Kant Pitti
39 . B404 Sold Noopur Vyas /Manish Vyas
40 . D501 Unsold
41 . C604 Sold Tulsi Devi
42 . B804 Sold Shanti Chand Abani
43 . B304 Sold KAMAL KISHORE SHARMA
44 . C504 Sold Sangeeta Khicher
45 . C204 Sold Meena Mishra
46 . B801 Sold Kailash Kumar
47 . D804 Sold Jyothi Choudhary
48 . D701 Sold Ganesh Modi
49 . C904 Sold Suraj Kanwar
50 . C301 Sold Om Prakash Soni
51 . D104 Sold Nisha Khalsa / RAGHBIR SINGH KHALSA
52 . C601 Sold Babita Choudhary
53 . B701 Sold Narayan Singh
54 . C804 Sold Hitpal Singh /Kiran Kanwar
55 . D404 Sold Sulochna Choudhary
56 . D201 Unsold
57 . D504 Sold Anita Mohnot
58 . D604 Sold Ravi Prakash / Usha Sharma
59 . B901 Sold Shashi S Phophalia
60 . D101 Sold Namita Mathur
Building : Unique Apex Towers (Apartment : 2BHK Type -A, Block : 1, Carpet Area : 73.31 sq. meters) Number Of Apartments: 60,Booked: 57
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . C205 Sold Dinesh Kumar Bothra / DEEPIKA BOOTHRA
2 . D905 Sold Chota Ram Barupal
3 . D1007 Unsold
4 . B305 Sold Jigyasa Goliya / Akshaya Mehta
5 . B107 Sold Hemant Kumar Garg
6 . D605 Sold Renu Mittal
7 . C1007 Sold Rajendra Kumar Soni
8 . D805 Unsold
9 . C905 Sold Sanjay Shripatrao Mali / Aparna Magar
10 . D407 Sold Jitendra Kumar Garg
11 . D707 Sold Taj Kanwar
12 . C305 Sold Arun Kumar Rao
13 . B707 Sold Anand Bissa
14 . B407 Sold Praveen Soni / VARSHA SONI
15 . B307 Sold Renuka Kumari / Dongarmal Jeengar
16 . B607 Sold Phaulal Songara
17 . B505 Sold Nalini Maheshwari
18 . D807 Sold Leena Chouhan/ Devendra Singh Bhati
19 . D907 Sold Ankur Mathur / Shruti Mathur(legal Case)
20 . B1007 Sold Supriti Chodhary
21 . B705 Sold Anand Raneja
22 . C1005 Sold Tulsaram Patel / Kanaram Patel
23 . D105 Sold Mahendra Ku. Bohra / Aditya Bohra
24 . D205 Sold Suraj Mewara / JAYA MEWARA
25 . C307 Sold Umrao Kanwar Devi
26 . D507 Sold Mayank Bhandari/ Sweta Bhandari
27 . D107 Sold Dr. Swarn Lata / Dr. Praveen K. Anand
28 . B105 Sold Anil Singhvi / Shilpi Singhvi
29 . B605 Sold Shambhu Dayal Mahawar
30 . B205 Sold Dr. Manish Dodwani
31 . B405 Sold Shyam Sunder Bhatter
32 . B807 Sold Om Prakash Mehta
33 . C605 Sold Ajay Rathi
34 . D1005 Unsold
35 . C405 Sold Vikas Rathi
36 . B905 Sold Rajendra Mal Mathur
37 . D207 Sold Unni Raja Sharma / JAYA INDRA
38 . D607 Sold Renu Mittal
39 . B207 Sold Madhu Kothari
40 . C807 Sold Sunil Kumar Singhal
41 . D405 Sold Puneet Sharma/ DEEPIKA SHARMA
42 . C707 Sold Ashok Kumar Jain
43 . C607 Sold U.D. Sharma
44 . C107 Sold Roja Rani Shamith
45 . C207 Sold Satyanarayan Mewara/ Ashok Mewara
46 . C105 Sold Vinod Kumar Agarwal
47 . D705 Sold Dr. Vanka Ram Choudhary / Pravin Chaudhary(cancel)
48 . B907 Sold Mamta Devi
49 . C407 Sold Surendra Kumar Jain
50 . C907 Sold Shilpi Shyamsukha
51 . D307 Sold Abhishek Mehta Abhinav Mehta
52 . B805 Sold R.C. Tayal
53 . B1005 Sold Rajesh Soni
54 . C507 Sold Sukh Ram
55 . D505 Sold Sumit Jain / SHANTI DEVI
56 . D305 Sold Priyanka Chouhan / DILEEP SINGH CHOUHAN
57 . C805 Sold Nandkishore Rathi / Deepak Rathi
58 . C505 Sold Ranjeeta Jain / RAJ KUMAR JAIN
59 . B507 Sold Ramkumar / Vishal Singhal
60 . C705 Sold Dharmendra Sharma / SEEMA SHARMA
Building : Unique Apex Towers (Apartment : 3BHK+SER+Type-B, Block : 1, Carpet Area : 111.55 sq. meters) Number Of Apartments: 50,Booked: 40
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B1002 Sold Sunita Bhandari / RAJEEV BHANDARI
2 . C703 Sold Anil Agarwal
3 . C502 Sold Tanmay Singh / SANVI SINGH
4 . D702 Sold Rakhi Singh
5 . C303 Sold Ravi Sancheti
6 . C202 Sold Khushi Ram Chhatwani
7 . C302 Unsold
8 . B302 Sold Rakesh Rathi
9 . D103 Sold Sumit Sharma
10 . D703 Sold Manisha Lashkari / Tapan
11 . D303 Sold Megha Verma/ Prem Verma
12 . C103 Sold Shakuntala Vyas / Dr. O.P.Vyas
13 . C903 Sold Sangeeta Purohit / Dr. Prashant Purohit
14 . D802 Unsold
15 . C902 Sold Vishweshwar Tiwari
16 . B202 Sold Mohan Singh / HAR KANWAR
17 . D903 Unsold
18 . C603 Sold Vijay Kumari Naruka
19 . C402 Sold N.M. Birla Stone International P.Ltd.
20 . B102 Sold Rajendra Singh Rathore
21 . D503 Sold Kishan Kansara
22 . D102 Sold Ram Singh Rajpurohit / Karan Singh Rajpurohit
23 . B402 Sold Ruchi Singhal
24 . C403 Sold Nand Lal Bhati
25 . B902 Sold Vinita Mathur
26 . D302 Unsold
27 . C802 Sold Dharmendra Patwa
28 . B702 Sold Ankit Jain
29 . D902 Unsold
30 . C702 Sold A.K.Pareek
31 . C1003 Sold Dinesh Mangal / Neetu Mangal
32 . C602 Sold Vinit Agarwal
33 . D402 Sold Ravindra Kumar Jain / Ritu Jain
34 . B802 Sold Raj Rani Saran
35 . D1003 Unsold
36 . C102 Sold Manjeet Kaur Kheda
37 . D403 Sold Meena Bhandari/Puneet Bhandari
38 . D203 Sold Saiyad Yawar Hussain / Ziavi Fatma
39 . D602 Unsold
40 . D803 Unsold
41 . D202 Sold Anita Jain
42 . C803 Sold Sumit Agarwal
43 . C203 Sold Keerti Rathore / Gajendra Singh Rathore
44 . D502 Sold Arun Kumar Charan
45 . C503 Sold Akhil Mehta
46 . B502 Sold Manoj Kumar Hinger (HUF)
47 . D1002 Unsold
48 . C1002 Sold Anil Mittal
49 . D603 Unsold
50 . B602 Sold Bikram Singh Yadav / VAIBHAV YADUVANSHI
Building : Unique Apex Towers (Apartment : 3BHK+SER+Type-A, Block : 1, Carpet Area : 114.95 sq. meters) Number Of Apartments: 10,Booked: 10
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B203 Sold Manish Kumar Bansal
2 . B703 Sold Kirti Jain
3 . B303 Sold Madhu Singhvi
4 . B1003 Sold Yogesh / Prathna Ojha
5 . B603 Sold Shalini Goyal / J.R.Singhvi
6 . B803 Sold Jyoti Pareek
7 . B503 Sold Arpit Kumar
8 . B403 Sold Dr. Rashmi Vyas
9 . B903 Sold Rishabh Pareek
10 . B103 Sold Laxmi Kant Pitti
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Fee 10000.00 Print Receipt QPR Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Rs.10000/- DEPOSITED BY RERA TRANS. NO.2279 DATED 31.07.2025 FOR QPR. 8/4/2025 PENDING WITH NODAL OFFICER
2 Law Officer (27634) "Discrepancy in form R1 TABLE-A R1:Certificate from Architect to be provided as per format in RERA Regulations (complete Tower B, Tower C and Tower D not mentioned). TABLE-B Sr.no.1-Internal Roads & Footpaths-This Percentage figure is not correct. Sr.no.2-Water Supply-This Percentage figure is not correct. Sr.no.3-Sewerage (chamber, lines, Septic Tank STP)-This Percentage figure is not correct. Sr.no.4-Storm Water Drains -This Percentage figure is not correct. Sr.no.5-Landscaping & Tree Planting-This Percentage figure is not correct. Sr.no.6-Street Lighting-This Percentage figure is not correct. Sr.no.7-Community Building-This Percentage figure is not correct. Sr.no.13-Electrical meter room, sub-station, receiving station-This Percentage figure is not correct. Discrepancy in form R2 TABLE-A R2: Tower B, Tower C and Tower D in certificate and portal does not match. TABLE-B Sr.no.1-Total Estimated cost of the Internal and External Development Works including amenities and Facilities-This figure is not correct. Sr.no.4-Balanced Cost to be Incurred (Based on Estimated Cost)-This figure is not correct. Discrepancy in form R3 Sr.no.1 (A) -Land Cost / Incurred Amount Current Quarter-This figure is not correct. (C) -Total project cost(A+B)-Incurred Amount / Current Quarter-This figure is not correct. Sr.no.4-Percentage Completion of construction work (as per Project Engineer's Certificate, R-2)-This Percentage figure is not correct. Sr.no.6-Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost-This Percentage figure is not correct. Sr.no.7-Amount Which can be withdrawn from the separate Account-This figure is not correct. Sr.no.8-Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements-This figure is not correct. Sr.no.9-Net Amount Which can be withdrawn from the Separate bank account under this certificate-This figure is not correct R3: Certificate from CA to be provided as per format in RERA Regulations. R3: Estimation of onsite expenses and statutory expenses to be provided and cost need to be properly bifurcated among all heads instead of merging with construction cost. R3: Certificate is not physically signed and stamped by CA (sign and seal are copy pasted on certificate) Others: The Certificate showing no line or charge on the RERA retention Account is not for the said quarter, the uploaded certificate is of previous quarter. Kindly update " 8/5/2025 APPLICATION OBJECTED