Quarterly Progress Report Summary Details October to December, 2022

Quarterly Progress Report Summary Details October to December, 2022

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2023-16818 (31/01/2023)
Name of the Registered project SHUBHASHRAY UPTOWN PHASE III Registration No. of the Project RAJ/P/2021/1530
Name of the Promoter SUREFIN ADVISORS PRIVATE LIMITED Name of other Promoter(s) PURE AWAS BUILDERS LLP
Project Address Khasra No./ Plot No.Khasra No. 744 to 746, 750 to 760 , Village- DHIRIYAWAS , , Alwar - 303107 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 56
Total Area of Project(In sq. meters) 25,311.73 Phase Area (In sq. meters) 1,200.00
Registration certificate is valid upto 19-02-2026 Registration extended upto Not Applicable
II. Number and type of apartments booked ( October to December, 2022 )
Building Name : TOWER-H
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
Flat No. H-101 to H-114 (2BHK) 1 33.17 2.43 14 14
Flat No. H-201 to H-214 (2BHK) 1 33.17 2.43 14 12
Flat No. H-301 to H-314 (2BHK) 1 33.17 2.43 14 12
Flat No. H-401 to H-414 (2BHK) 1 33.17 2.43 14 13
Total 56 51 55
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( October to December, 2022 )

TABLE - A

Building Name: TOWER-H
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 80 90.00
4 5 Number of Slabs of Super Structure 80 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 40 60.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 30 45.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 20.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 0 0
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
11/01/2023
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( October to December, 2022 )

TABLE - A

Building Name : TOWER-H
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 22,596,000.00 36,031,257.00
2 Cost incurred against the estimated cost 17,817,200.00 22,978,089.00
3 Work done (as Percentage of the estimated cost) % 79 64.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 4,778,800.00 13,053,168.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 3,228,000.00 3,228,000.00
2 Cost incurred against the estimated cost 0.00 0.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 0.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 3,228,000.00 3,228,000.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
30/01/2023
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( October to December, 2022 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 2,697,378.00 2,697,378.00 2,697,378.00
B. Development Cost/Cost of Construction 30,672,438.00 19,041,798.00 24,210,687.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 21,739,176.00 26,908,065.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 19,917,630.00 25,867,224.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 1,821,546.00 1,040,841.00
Form R3: Date of issue
30/01/2023
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0 31/03/2023
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0 31/03/2023
4 Electrification(Transformer, Solar Energy etc) 0 31/03/2023
5 Fire Fighting Provision 0 31/03/2023
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 17/09/2020
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/03/2023
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/03/2023
If formation/registration of association of allottees is not proposed, explain reasons thereof building is underconstruction and possession is not given

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : TOWER-H (Apartment : Flat No. H-101 to H-114 (2BHK), Block : 1, Carpet Area : 33.17 sq. meters) Number Of Apartments: 14,Booked: 14
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . H-106 Sold Sunita
2 . H-114 Sold Roma Sen bba
3 . H-107 Sold Sangeeta Devi
4 . H-101 Sold sunita devi
5 . H-109 Sold abhijeet bhasker
6 . H-102 Sold Amardeep
7 . H-110 Sold krishn kumar rajak
8 . H-103 Sold Sonika
9 . H-111 Sold Rekha
10 . H-108 Sold chetana sharma
11 . H-104 Sold Sukhbir yadav
12 . H-112 Sold Rohit kumar attri
13 . H-105 Sold Rajkumar
14 . H-113 Sold Rajkumar
Building : TOWER-H (Apartment : Flat No. H-201 to H-214 (2BHK), Block : 1, Carpet Area : 33.17 sq. meters) Number Of Apartments: 14,Booked: 14
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . H-208 Sold sunil pal
2 . H-201 Sold Ravindar Prasad
3 . H-209 Sold rachna
4 . H-203 Sold Vinod
5 . H-211 Sold varun vig
6 . H-204 Sold Rohit kumar
7 . H-212 Sold Vikas kumar
8 . H-205 Sold Krishan kumar bba
9 . H-213 Sold Pooja Saluja
10 . H-202 Sold mahender
11 . H-210 Sold Shubhra Sharma
12 . H-206 Sold Nakul Kaushik
13 . H-214 Unsold
14 . H-207 Sold Akanksha
Building : TOWER-H (Apartment : Flat No. H-301 to H-314 (2BHK), Block : 1, Carpet Area : 33.17 sq. meters) Number Of Apartments: 14,Booked: 14
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . H-302 Sold devesh sharma
2 . H-310 Sold Arun Kumar
3 . H-303 Sold Manju
4 . H-311 Sold Asha rani
5 . H-305 Sold Vijay Dalal bba
6 . H-313 Sold Sonika Tiwari
7 . H-306 Sold Vikas juggal
8 . H-314 Sold Ram Ratan Rastogi
9 . H-307 Sold Dinesh Saini
10 . H-304 Sold dev Narayan Mandal
11 . H-312 Sold Hari priya
12 . H-308 Sold Jamuna Devi
13 . H-301 Sold ajay paswan
14 . H-309 Sold neha sharma
Building : TOWER-H (Apartment : Flat No. H-401 to H-414 (2BHK), Block : 1, Carpet Area : 33.17 sq. meters) Number Of Apartments: 14,Booked: 14
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . H-404 Sold shahid
2 . H-412 Sold Heena Chugh
3 . H-405 Sold Pushpa Devi
4 . H-413 Sold Manya suri
5 . H-407 Sold lalita trivedi
6 . H-408 Sold Ram Niwas Sharma
7 . H-401 Sold rohit pall
8 . H-409 Sold nitin/rahul
9 . H-406 Sold Nirmala Devi
10 . H-414 Sold Ravi chauhan
11 . H-402 Sold Ambika Sood
12 . H-410 Sold Reetika Jain
13 . H-403 Sold Himanshu Malhotra
14 . H-411 Sold Ravi Batra
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) The QPR is accepted subject to verification. 6/23/2023 Application Approved