I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2024-20964 (24/01/2024)
Name of the Registered project Dream Homz Registration No. of the Project RAJ/P/2020/1259
Name of the Promoter G S DREAMHOME LLP Name of other Promoter(s) None
Project Address Khasra No./ Plot No.1296 & 1306 , Village- MAKARWALI , Pushkar Bypass , Ajmer - 305004 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 325
Total Area of Project(In sq. meters) 11,352.55 Phase Area (In sq. meters) 11,352.55
Registration certificate is valid upto 31-05-2024 Registration extended upto Not Applicable
II. Number and type of apartments booked ( October to December, 2023 )
Building Name : Dream Homz
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
Block-A-LIG-3BHK 54.85 16.50 95 22
Block-B-LIG-3BHK 54.85 16.50 90 85
Block-C-LIG-2BHK 39.89 11.36 70 70
Block-D-EWS-1BHK 27.90 8.02 70 27
Total 325 204 219
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( October to December, 2023 )

TABLE - A

Building Name: Dream Homz
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 4 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 95 96.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 85 86.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 95 96.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 95 96.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 92 96.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 90 90
2 Water Supply 100 100
3 Sewerage (chamber, lines, Septic Tank STP) 95 95
4 Storm Water Drainss 95 95
5 Landscaping & Tree Planting 100 100
6 Street Lighting 100 100
7 Community Building 50 60
8 Treatment and disposal of sewage and sullage water 90 90
9 Solid Waste management & Disposal 90 90
10 Water conservation, Rain water harvesting 100 100
11 Energy management 0 0
12 Fire protection and fire safety requirements 95 95
13 Electrical meter room, sub-station, receiving station 100 100
Form R1: Date of issue
31/12/2023
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( October to December, 2023 )

TABLE - A

Building Name : Dream Homz
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 308,406,000.00 308,406,000.00
2 Cost incurred against the estimated cost 264,465,424.00 280,412,093.00
3 Work done (as Percentage of the estimated cost) % 86 91.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 43,940,576.00 27,993,907.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 11,594,000.00 11,594,000.00
2 Cost incurred against the estimated cost 8,477,765.00 8,477,765.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 73.00 73.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 3,116,235.00 3,116,235.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
31/12/2023
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( October to December, 2023 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 31,030,300.00 31,030,540.00 31,030,540.00
B. Development Cost/Cost of Construction 320,000,000.00 272,943,189.00 288,889,858.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 303,973,729.00 319,920,398.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 280,472,329.00 296,503,314.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 23,501,400.00 23,417,083.00
Form R3: Date of issue
23/01/2024
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 100
2 Rain Water Harvesting/ Recharging 100
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 98
4 Electrification(Transformer, Solar Energy etc) 95
5 Fire Fighting Provision 95
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 06/12/2019
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 31/05/2024
2.
Formation of association of allottees
Status
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act.
Has the association of allottees been formed?
• Expected Date of Formation 31/05/2024
If formation/registration of association of allottees is not proposed, explain reasons thereof

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?

Allottee Details

Building : Dream Homz (Apartment : Block-B-LIG-3BHK, Block : , Carpet Area : 54.85 sq. meters) Number Of Apartments: 90,Booked: 87
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . B-203 Sold Pratibha Balani
2 . B-315 Sold Nilima Mathur
3 . B-405 Sold Arvind Tiwari
4 . B-108 Sold Susheela/ lalchand Sokriwal
5 . B-117 Sold Ranka Jha
6 . B-406 Sold Pradeep Bali
7 . B-15 Sold Dilsad
8 . B-101 Sold Manisha/Amit Nigam
9 . B-118 Sold Raju Ram
10 . B-110 Sold Naresh Kumar Sharma
11 . B-112 Sold Biju Devasia
12 . B-314 Sold Rajni Agnani
13 . B-13 Sold Mani Devi
14 . B-318 Sold Alka Law
15 . B-18 Sold Pushpa Nayar
16 . B-214 Sold Rajesh Robinson
17 . B-115 Sold Manju Chaudhari
18 . B-307 Sold Seema vashishth
19 . B-212 Sold Santosh/Sunil Jain
20 . B-309 Sold Mayank Soni
21 . B-312 Sold Renu Mathuriya
22 . B-302 Sold Kavita Kacchava
23 . B-216 Sold Vasundhara Sharma
24 . B-106 Sold Durgesh Vashishth
25 . B-205 Sold Sobin Thomas
26 . B-317 Sold Jitendra Kumar
27 . B-09 Sold Naresh Kumar Sharma
28 . B-209 Sold Anant Bhatnagar
29 . B-411 Sold Chetan singh
30 . B-17 Sold Virendra Kumar Sharma
31 . B-409 Sold Tarun Sujanani
32 . B-08 Sold Lalit Kumar
33 . B-210 Sold Mansi Sharma
34 . B-211 Sold Siddharth Sethi
35 . B-16 Sold Dinesh kumar
36 . B-113 Sold Mukesh raliya
37 . B-403 Sold Sayyed Nadeem ali
38 . B-01 Sold Sudhi Kaushik
39 . B-217 Sold Anand Mothish
40 . B-311 Sold Kesav Kakani
41 . B-414 Sold Suman Prajapat
42 . B-103 Sold Manju Devi/Ganga Devi
43 . B-402 Sold Malti Singh/Vijay Prataap
44 . B-308 Sold Sanjeev Sharma
45 . B-102 Sold Son Kanwar/Shakti Singh
46 . B-304 Sold Rajni Agnani
47 . B-03 Sold Shubha Chaudhary
48 . B-204 Sold Sandeep Rawat
49 . B-401 Sold Bharat Lalwani
50 . B-04 Sold Himmat singh rathore
51 . B-215 Sold Santosh Kumar
52 . B-207 Sold Bhupendra Kumar
53 . B-413 Sold Seema Katiyar
54 . B-105 Sold Shreekishan
55 . B-201 Sold Pankaj Sethi/Janvi Sethi
56 . B-305 Unsold
57 . B-412 Sold Leena Phulwani
58 . B-313 Sold Pooja Lakhwal
59 . B-05 Sold Sunil kumar mittal
60 . B-408 Sold Manjeet singh chouhan
61 . B-213 Sold Lakshmi Rathore
62 . B-06 Sold Sunil kumar mittal
63 . B-12 Sold Pranto Barrick
64 . B-116 Sold Durga Devi
65 . B-301 Sold Shahzad ahmed/Husna Bano
66 . B-310 Sold Alic/Sanjay Messi
67 . B-415 Sold Mukesh Jangid
68 . B-14 Unsold
69 . B-418 Sold Pratibha nayak
70 . B-410 Sold Nandkishore sharma
71 . B-07 Sold Rajendra prasad jethani
72 . B-407 Sold Aasha Vashisht
73 . B-306 Sold Garima Mathur
74 . B-02 Sold Sarjeet
75 . B-114 Sold Shiv Shankar Baria
76 . B-303 Sold Syed Chisti/Syeda Nuzhat
77 . B-206 Sold Komal Srivastava
78 . B-107 Sold Seema Rani
79 . B-417 Sold Zahid Khan
80 . B-10 Unsold
81 . B-416 Sold Madhu/Manoj Tiwari
82 . B-111 Sold Laxmi narayan Vaishnav
83 . B-202 Sold Anubhav Sharma
84 . B-316 Sold Kavin Paul
85 . B-404 Sold Sanwar lal Mangal
86 . B-11 Unsold
87 . B-104 Sold Premlata Jain/ Ashok Jain
88 . B-208 Sold Anant Bhatnagar
89 . B-109 Sold Mukesh Dara
90 . B-218 Sold Priyanka
Building : Dream Homz (Apartment : Block-D-EWS-1BHK, Block : , Carpet Area : 27.90 sq. meters) Number Of Apartments: 70,Booked: 45
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . D-310 Sold Anjali Tenduriya/Vidhur
2 . D-207 Sold Rakendra
3 . D-212 Unsold
4 . D-103 Sold Deanna Robinson
5 . D-407 Sold Manu Gupta
6 . D-104 Sold Anil Robinson
7 . D-08 Sold Daljit singh
8 . D-213 Unsold
9 . D-412 Unsold
10 . D-307 Sold Rupesh Panchal
11 . D-14 Sold Ritesh Sharma
12 . D-101 Sold Preeti Srivastava
13 . D-405 Unsold
14 . D-105 Sold Manju devi/jagdish
15 . D-11 Unsold
16 . D-413 Sold Nividita singh
17 . D-406 Unsold
18 . D-303 Sold Imran Kadri
19 . D-03 Unsold
20 . D-304 Sold Dilip singh
21 . D-402 Unsold
22 . D-308 Sold Ramavtar parashar
23 . D-04 Unsold
24 . D-13 Unsold
25 . D-309 Sold Sarita parashar
26 . D-404 Unsold
27 . D-06 Unsold
28 . D-210 Sold Chotti Devi
29 . D-02 Unsold
30 . D-302 Unsold
31 . D-410 Unsold
32 . D-312 Unsold
33 . D-401 Sold Manish Lalwani
34 . D-09 Unsold
35 . D-211 Sold Navratan Sagar
36 . D-411 Unsold
37 . D-305 Unsold
38 . D-114 Sold Lalit Singh
39 . D-206 Unsold
40 . D-408 Sold Solani gupta
41 . D-301 Sold Pranit
42 . D-12 Unsold
43 . D-214 Sold Rajendra Prasad Jethani
44 . D-202 Unsold
45 . D-112 Unsold
46 . D-414 Sold Megha Sharma
47 . D-203 Unsold
48 . D-109 Unsold
49 . D-204 Unsold
50 . D-108 Unsold
51 . D-306 Unsold
52 . D-208 Unsold
53 . D-01 Unsold
54 . D-107 Sold Manisha Modiyan
55 . D-205 Sold Harish singh
56 . D-311 Sold Rahul
57 . D-403 Unsold
58 . D-05 Unsold
59 . D-113 Unsold
60 . D-07 Sold Sheetala Prasad
61 . D-209 Unsold
62 . D-201 Sold Jawahar rajdhan
63 . D-102 Sold Ashish Srivastava
64 . D-409 Unsold
65 . D-313 Unsold
66 . D-111 Unsold
67 . D-10 Unsold
68 . D-110 Sold Amar Singh
69 . D-106 Unsold
70 . D-314 Sold Balvir/Ramesh
Building : Dream Homz (Apartment : Block-A-LIG-3BHK, Block : , Carpet Area : 54.85 sq. meters) Number Of Apartments: 95,Booked: 38
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . A-220 Unsold
2 . A-08 Unsold
3 . A-203 Unsold
4 . A-401 Unsold
5 . A-213 Sold Surendra
6 . A-13 Sold Sudharsan Swami
7 . A-14 Unsold
8 . A-305 Sold Arurendra Bagdi
9 . A-103 Unsold
10 . A-02 Unsold
11 . A-210 Sold Manohar lal chauhan
12 . A-312 Unsold
13 . A-304 Sold Kavita Kacchava
14 . A-404 Unsold
15 . A-112 Sold Sharwan Ram
16 . A-05 Unsold
17 . A-416 Unsold
18 . A-106 Unsold
19 . A-206 Unsold
20 . A-114 Unsold
21 . A-110 Sold Sagar Sharma
22 . A-316 Unsold
23 . A-204 Sold Dhirendra
24 . A-407 Unsold
25 . A-405 Unsold
26 . A-102 Unsold
27 . A-15 Unsold
28 . A-309 Sold Nuzhat qamar
29 . A-417 Unsold
30 . A-409 Unsold
31 . A-107 Sold Suryaprakash tak
32 . A-116 Unsold
33 . A-303 Sold Kapil D Asara
34 . A-410 Sold Nikhil Chaturvedi
35 . A-04 Unsold
36 . A-111 Sold Sakshi sharma
37 . A-120 Unsold
38 . A-306 Unsold
39 . A-209 Sold Vipin Kumawat
40 . A-302 Unsold
41 . A-101 Sold Arti Garg
42 . A-307 Sold Meenakshi Mehra
43 . A-115 Unsold
44 . A-118 Unsold
45 . A-308 Sold Yusuf Mohammad
46 . A-411 Sold Manoj Kumar Irani
47 . A-420 Unsold
48 . A-109 Sold Jhumari Khatun
49 . A-09 Unsold
50 . A-301 Sold Manas ramchandani
51 . A-06 Unsold
52 . A-201 Sold Kiran
53 . A-315 Unsold
54 . A-317 Unsold
55 . A-214 Unsold
56 . A-03 Unsold
57 . A-406 Unsold
58 . A-10 Unsold
59 . A-207 Sold Amar Anirudin
60 . A-01 Unsold
61 . A-413 Unsold
62 . A-318 Unsold
63 . A-311 Sold Yash Gupta
64 . A-211 Sold Vinayak khusawa
65 . A-12 Sold Ramesh Swami
66 . A-215 Unsold
67 . A-07 Unsold
68 . A-205 Sold Amit chaudhary
69 . A-314 Unsold
70 . A-419 Unsold
71 . A-202 Unsold
72 . A-208 Sold Radhakishan Panchal
73 . A-310 Sold Ratindranath Roy
74 . A-11 Unsold
75 . A-108 Sold Surendra
76 . A-104 Unsold
77 . A-412 Unsold
78 . A-408 Unsold
79 . A-418 Unsold
80 . A-216 Unsold
81 . A-414 Unsold
82 . A-119 Unsold
83 . A-402 Unsold
84 . A-403 Sold Vandana Dilip
85 . A-212 Unsold
86 . A-319 Unsold
87 . A-113 Sold Nisha
88 . A-105 Unsold
89 . A-117 Unsold
90 . A-218 Unsold
91 . A-320 Unsold
92 . A-217 Unsold
93 . A-219 Unsold
94 . A-313 Unsold
95 . A-415 Unsold
Building : Dream Homz (Apartment : Block-C-LIG-2BHK, Block : , Carpet Area : 39.89 sq. meters) Number Of Apartments: 70,Booked: 70
Sr.No. Unit/Flat Detail Booking Status Allottee Name
1 . C-04 Sold Sukhdev Sad
2 . C-214 Sold Prahlad Ram
3 . C-408 Sold Sangeeta
4 . C-314 Sold Rakesh chaurdhary
5 . C-110 Sold Kanchan
6 . C-02 Sold Nisha Morya
7 . C-312 Sold Romit Singh
8 . C-109 Sold Mahendra Singh
9 . C-413 Sold Hari Shankar
10 . C-07 Sold Sangeeta /Manu Gupta
11 . C-407 Sold Praveen Ojha
12 . C-13 Sold Raju Ram
13 . C-301 Sold Somanshu Batra
14 . C-311 Sold Ram Mohan Mangal
15 . C-10 Sold Pankaj Kumar
16 . C-105 Sold Basanti/Harish
17 . C-401 Sold Naveen Ramchandani
18 . C-106 Sold Sunita regar/Mahendra kumar
19 . C-313 Sold Mohit Gehlot
20 . C-03 Sold Shyam sunder
21 . C-111 Sold Jyoti Gupta
22 . C-103 Sold Dharmendra kumar sharma
23 . C-308 Sold Jai Singh rawat
24 . C-307 Sold Chandramohan rajoria
25 . C-104 Sold Deepak Kumar
26 . C-202 Sold Arti Namdeo
27 . C-112 Sold Yogendra sisodia
28 . C-406 Sold Rajendra
29 . C-14 Sold Kishan Chouhan
30 . C-305 Sold Punit Jain
31 . C-12 Sold Ashok Kumar Paral
32 . C-302 Sold Devanshu Batra
33 . C-113 Sold Gitu Singh
34 . C-211 Sold Rajesh Sunita Kumar
35 . C-404 Sold Dinesh Kumar kachava
36 . C-01 Sold Manisha Bairwa
37 . C-114 Sold Hukumchand/Reena
38 . C-204 Sold Dinesh Kumar
39 . C-402 Sold Vidhesh Sharma
40 . C-213 Sold Imran
41 . C-107 Sold Bindiya Sharma/Ranawat
42 . C-411 Sold Devendra site
43 . C-05 Sold Gopal
44 . C-06 Sold Madhuri/Manoj Bhabhani
45 . C-403 Sold Padam Kumar
46 . C-409 Sold Nirmala
47 . C-304 Sold Manoj Sharma
48 . C-412 Sold Gopi Kishan
49 . C-309 Sold Preeti sharma
50 . C-09 Sold Dinesh Yadav
51 . C-310 Sold Nisha Jangid
52 . C-207 Sold Indu Sharma
53 . C-108 Sold Shipra Singhal
54 . C-201 Sold Maneesha/Govind
55 . C-210 Sold Seema Mehra
56 . C-405 Sold Ayssha Sayyad
57 . C-11 Sold Giriraj Gaur
58 . C-205 Sold Abhishek Bathariya
59 . C-101 Sold Nitesh Sharma
60 . C-303 Sold Kalawathi nathulal
61 . C-410 Sold Arurendra bagdi
62 . C-206 Sold Mahaveer Prajapat
63 . C-209 Sold Nargis Bano
64 . C-212 Sold Arshad
65 . C-414 Sold Poonam singh
66 . C-08 Sold Virendra kumar sharma
67 . C-203 Sold kamlesh w/o Ratan
68 . C-102 Sold Poonam/Satya Ranjan Rout
69 . C-306 Sold Rajesh kumar sharma
70 . C-208 Sold Melvin Joseph
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Twinkle Gupta (24068) QPR MAY BE ACCEPTED, SUBJECT TO VERIFICATION 2/7/2024 Application Approved