APPLICATION FOR MODIFICATION OF PROJECT PROFILE
Particulars of the Registered Project
Application No. : RAJ-RERA-APP-SPM-2022-436 (9/20/2022)
|
|||
---|---|---|---|
Name of the Registered Project | Ananda Greens | Project Status | LAPSED |
Registration Number | RAJ/P/2018/683 | Name of the Promoter | SWARNDHARA HOUSING LLP |
Name of Other Promoter(s) | Project Address | Khasra No. 83,84 & 85Huseengpur Tapukara Tijara Alwar | |
Project Type | Plotted Development | Phase Area (in Sq. Mt.) | 15267.08 |
Project registration vaild till (As per RC/ Form F, whichever is latest) | 3/31/2021 | Project registration certificate (As per RC/ Form F, whichever is latest) | View |
Project Modification Request
SELECT | PARTICULARS | Existing Online Details | Proposed Modified Details | Reason for Modification and in case of documents specify the documents/part which is being replaced/changed | Supporting Documents and detailed application(If any) |
---|---|---|---|---|---|
PLOT DETAILS (In Case of Plotted Development) | |||||
Plot Details | View | View | TOTAL SANCTIONED UNITS ARE NOT VISIBLE ON RERA PORTAL, HENCE PROMOTER UPDATING THE SAME |
Declaration
I/ we do hereby solemnly declare and undertake: That the changes/updations proposed by me/us in the Project details are correct and shall not affect/ damage the rights and interests of the allottee(s) of the project. If, however, due to such modification, any damages or losses are suffered by any allottee(s) or any rights and interests of any allottee(s) are adversely affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate for the same and to resolve the dispute and shall also be liable for all other legal and financial consequences thereof |
Payment Details | ||||
---|---|---|---|---|
Payment Amount | Payment Date | Download Receipt |
Comments Details | |||||
---|---|---|---|---|---|
PARA | Created BY | Comments | Date | Status | Document |
1 | Rishabh Sharma (10665) | The total and Sanctioned no. of PLots in the project summary is 160, whereas in the application Plot Details are filled for 168 units. Kindly check and resubmit on or before 29.09.2022. | 9/22/2022 | APPLICATION OBJECTED | |
2 | Promoter | We have corrected the no. of units. Also we have uploaded service drawings. | 12/2/2023 | PENDING WITH NODAL OFFICER | |
3 | Rishabh Sharma (10665) | In reference to para 1/N, now the Plot Details are filled for 158 units, whereas, the total and Sanctioned no. of Plots in the project summary is 160. Kindly check and rectify the application on or before 22.12.2023. | 12/15/2023 | APPLICATION OBJECTED | |
4 | Promoter | Dear sir, we have now fill area details of all the 160 plots | 1/29/2024 | PENDING WITH NODAL OFFICER | |
5 | Rishabh Sharma (10665) | The promoter has updated the Total Plots column in the Plot Details tab. In addition, they are uploading service drawings in the same application. However, no fee is applicable for updating the plot details column since the Authority introduced it later. The promoter may update only that detail without any fee. A fee of Rs. 5,000/- is applicable to update the remaining details of the project summary. Therefore, if allowed the promoter may be directed to update the PLot Details through this application and to update the service drawings, a separate application may be submitted by him. | 2/6/2024 | PENDING WITH JOINT REGISTRAR | |
6 | Arpit Sancheti (10683) | Inform promoter accordingly. | 2/6/2024 | PENDING WITH NODAL OFFICER | |
7 | Rishabh Sharma (10665) | Only update the Plot Details through this application, for service drawings apply a separate project profile modification application. Comply with the direction on or before 13.02.2024. | 2/6/2024 | APPLICATION OBJECTED | |
8 | Ramesh Sharma (9009) | Record Pulled by REGISTRAR | 2/15/2024 | PENDING WITH REGISTRAR | |
9 | Ramesh Sharma (9009) | Promoter has not rectified the objections since 15.12.2023, and even the time given in the objection raised on 06.02.2024 has also been lapsed. Application pending since 2022. Therefore, application is submitted for rejection. | 2/15/2024 | PENDING WITH CHAIRMAN | |
10 | Chairman Rajasthan (1) | promoter has responded on 29.1.24. we may give one opportunity till 10.3.24 | 2/15/2024 | PENDING WITH REGISTRAR | |
11 | Ramesh Sharma (9009) | Comply till 10-03-2024. | 2/16/2024 | APPLICATION OBJECTED | |
12 | Promoter | Dear Sir, As per Authority’s direction, we have applied the separate application for updation of service drawings via application no. “RAJ-RERA-APP-SPM-2024-905”. So, kindly accept our humble submission and consider this application for updation of inventory details and process our application for approval. | 3/8/2024 | PENDING WITH NODAL OFFICER | |
13 | Rishabh Sharma (10665) | Application for registration of the said project was applied before 20.09.2020, i.e., the cut-off date when the IT cell introduced the Total Plots & No. of plots Booked/Allotted/Sold column in the Plot Details tab. Therefore, in this application promoter has applied for the updation of Plot details in the project profile, there are 160 units filled under the total and sanctioned no. of apartment/plot column, and the promoter has updated the same in their Plot Details column. Therefore, application is submitted for your kind perusal and approval, please. | 3/20/2024 | PENDING WITH JOINT REGISTRAR | |
14 | Ramesh Sharma (9009) | Record Pulled by REGISTRAR | 3/22/2024 | PENDING WITH REGISTRAR | |
15 | Ramesh Sharma (9009) | Submitted for approval,madam. | 3/26/2024 | PENDING WITH CHAIRMAN | |
16 | Chairman Rajasthan (1) | approved | 3/26/2024 | APPLICATION APPROVED |