Application No. : RAJ-RERA-APP-SPM-2021-88 (10/25/2021)
Name of the Registered Project BRINDAVAN ENCLAVE PHASE III Project Status LAPSED
Registration Number RAJ/P/2017/530 Name of the Promoter AMAR PRATAP DEVELOPERS PRIVATE LIMITED
Name of Other Promoter(s) Project Address 11 BSM 178/1-23,24,25, 178/2-3,4,5,6,7,8,13,14,15,16,17, 178/9-13,14,15,16,17,18,19,20,21,22,23,24,25, 178/10-1,2,3,4,5,6,7,8,9,10,11,12,13,14,17,18,19,20,21,22,23,24,25, 178/17-6,7,8,9,10,11,12,13,14,15,16,17,18,19,20,21,22,23,24, 178/18-1,2,3,10, 178/25-9,10,11,12,20, 12BSM- 158/51-16,17,23,24,25, 158/52-1,2,3,4,5,6,7,8,9,12,13,14,15,16,17,18,23,24, 158/59-4,7,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23,24,25, 158/60-1,2,3,4,5,6,7,8,9,10,11,12,13,20, 178/3-,5,6,7,13,14,15,17,18,19,20,21,22,23,24, 178/4-1,2,3,4,7, 178/11-1,10,11NH 11, JAIPUR ROAD, BIKANER Bikaner Bikaner
Project Type Phase Area (in Sq. Mt.) 376693.77
Project registration vaild till (As per RC/ Form F, whichever is latest) 12/31/2021 Project registration certificate (As per RC/ Form F, whichever is latest) View
Project Modification Request
SELECT PARTICULARS Existing Online Details Proposed Modified Details Reason for Modification and in case of documents specify the documents/part which is being replaced/changed Supporting Documents and detailed application(If any)
PROJECT COST DETAIL
Land cost as per rule 5(1) 268,259,036.00 310,000,000.00 Increase in Land Cost as some expenses related to land were not taken into consideration at the time of registration.
Development cost as per rule 5(2) 173,758,033.00 240,000,000.00 Increase in Development Cost due to escalation in the cost of material used for development of project.
Declaration
I/ we do hereby solemnly declare and undertake: That the changes/updations proposed by me/us in the Project details are correct and shall not affect/ damage the rights and interests of the allottee(s) of the project. If, however, due to such modification, any damages or losses are suffered by any allottee(s) or any rights and interests of any allottee(s) are adversely affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate for the same and to resolve the dispute and shall also be liable for all other legal and financial consequences thereof
Payment Details
Payment Amount Payment Date Download Receipt
₹ 5,000.00 10/25/2021 Generate Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Rishabh Sharma (10665) Verify the fee deposited 10/25/2021 PENDING WITH PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER
2 Madan Pareek (16059) Rs. 5000/- deposited by RERA Transaction No. 15746 dated 25.10.2021. 10/26/2021 PENDING WITH NODAL OFFICER
3 Rishabh Sharma (10665) Submitted for kind perusal and approval for the change of land cost and development cost on the grounds mentioned in the "Reason for modification" tab. 10/26/2021 PENDING WITH JOINT REGISTRAR
4 Arpit Sancheti (10683) Submitted for kind perusal and approval pls. 10/27/2021 PENDING WITH REGISTRAR
5 Ramesh Sharma (9009) Submitted for perusal and approval,sir. 10/28/2021 PENDING WITH CHAIRMAN
6 NIHAL CHAND GOEL (1) approved 10/28/2021 APPLICATION APPROVED