1 |
Veer Bahadur Gurjar (10678) |
Rs.5000/- Deposited by RERA Trans. No 454 Dated 05.12.2024 FOR MODIFICATION OF PROJECT DETAILS. |
12/9/2024 |
PENDING WITH DEPUTY REGISTRAR |
|
2 |
Puneet Kapoor (10671) |
Dear Applicant,
1.)Clarify as how many villa/Types number are proposed in the “Mahima's Shubh Nilay Phase-II "Villas"” as Presently in Plumbing tab in Building document section only Plumbing dwg with regard to Villa 01,02,39 and 40 are uploaded what about other Villa Numbers? Specify and Clarify; Like wise in electrical tab
2.)On working drawing apprise the Project name as registered “Mahima's Shubh Nilay Phase-II "Villas"” and upload the sheet/annexure explaining as which Villa no are applicable in Mahima's Shubh Nilay Phase-II and Floor wise as on which PDF page no which sheet is uploaded;
3.)Similarly in Structure drawings apprise the Project name as registered “Mahima's Shubh Nilay Phase-II "Villas and upload the sheet/annexure explaining as which Villa no are applicable in Mahima's Shubh Nilay Phase-II and Floor wise as on which PDF page no which structure drawing sheet is uploaded as 72 sheets have been uploaded; to understand readily;
Comply with the same by on or before 18.12.2024
|
12/11/2024 |
APPLICATION OBJECTED |
|
3 |
Promoter |
Dear Sir,
As per the objection raised by you in the online application, following details are updated in application:-
1.) There are total 123 villas in the project. The typical drawings of villas has been uploaded in both plumbing and electrical tabs.
2.) On working drawing the Project name as registered “Mahima's Shubh Nilay Phase-II "Villas"” has been apprised and the sheet/annexure stating which PDF page no regarding details pf Villa and Floor wise details has been uploaded;
3.) Similarly in Structure drawings the Project name as registered “Mahima's Shubh Nilay Phase-II "Villas"” has been apprised and the sheet/annexure stating which PDF page no regarding details pf Villa and Floor wise details has been uploaded;
Kindly consider the same for approval.
Regards
|
1/7/2025 |
PENDING WITH DEPUTY REGISTRAR |
|
4 |
Puneet Kapoor (10671) |
Dear Applicant,
1.)Drawings of villas as uploaded in both plumbing and electrical tabs is not showing the Villa no :-Mention the villa number on the respective drawing;
2.)In your reply at para no.3/N you have mentioned that there are total 123 villas in the project, however as per your sheet of villa number uploaded in tab of Architectural drawing:-last villa number mentioned by you as V-137; Also in tab of Architectural drawing/sheet uploaded specify as where is Villa no 12-14,17,51-54,88-91 respectively;
3.) in tab of Structural drawing/sheet uploaded specify as where is Villa no 12-14,17,51-54,88-91,108-111 respectively respectively;
Comply with the same by on or before 31.12.2025
|
1/24/2025 |
APPLICATION OBJECTED |
|
5 |
Promoter |
Dear Sir,
As per the objection raised by you in the online application, following details in application: -
1) The villa drawings uploaded in both the Plumbing and Electrical tabs are applicable to all villas. For this reason, specific villa number is not indicated on these drawings.
2) That numbering of villas has been done in the manner that villa numbers 12-14, 17, 51-54, and 88-91 are not considered in the project. The total number of villas in the project is 123 and their villa numbers are 01-11(11 villas), 15-16 (2 villas), 18-50 (32 villas), 55-87 (33 villas), and 92-137 (45 villas). It is pertinent to mention that villa no. 41-42 and villa no. 136-137 are combined and considered as single units/villas. Therefore, villa numbers 12-14, 17, 51-54, and 88-91 doesn’t exits and consequently their Architectural drawings have not been uploaded.
3) That numbering of villas has been done in the manner that villa numbers 12-14, 17, 51-54, and 88-91 are not considered in the project. Therefore, villa numbers 12-14, 17, 51-54, and 88-91 doesn’t exits and consequently their structural drawings have not been uploaded. Structural drawings for Villa No. 108-111 have been uploaded and can be found on pages 47-54.
Kindly consider the same for approval.
Regards |
2/1/2025 |
PENDING WITH DEPUTY REGISTRAR |
|
6 |
Puneet Kapoor (10671) |
1.)As per your Reply at para no.5/N,Point no 1 in comments section that :- The villa drawings uploaded in both the Plumbing and Electrical tabs are applicable to all villas:-If this is the fact than mention and apprise this fact on both plumbing and electrical villa drawings on each respective sheet :
Comply with the same by on or before 04.03.2025
|
2/25/2025 |
APPLICATION OBJECTED |
|
7 |
Promoter |
Dear Sir,
The villa numbers are mentioned in both the plumbing and electrical drawings for the respective villas and same has been uploaded in the relevant tabs.
Kindly consider the same for approval.
Regards |
3/25/2025 |
PENDING WITH DEPUTY REGISTRAR |
|
8 |
Puneet Kapoor (10671) |
In this application, applicant has applied so as to upload the Service drawings and Structure drawings of the Project, Therefore application is submitted for kind perusal and approval; |
3/25/2025 |
PENDING WITH JOINT REGISTRAR |
|
9 |
R.S. Kulhari (9009) |
Record Pulled by REGISTRAR |
3/27/2025 |
PENDING WITH REGISTRAR |
|
10 |
R.S. Kulhari (9009) |
Submitted for kind perusal and approval, Madam. |
3/27/2025 |
PENDING WITH CHAIRMAN |
|
11 |
Chairman Rajasthan (1) |
approved |
3/27/2025 |
APPLICATION APPROVED |
|