Project Extension View

RERA

Application for Extension of Registration Due to Corona Pandemic(as approved in-principle by the Authority's order dated 13-05-2020)

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2020-81 (7/6/2020)
Project Name THE CREST Promoter Name FS HOUSING PRIVATE LIMITED
Project Registration No. RAJ/P/2017/056 Project Type Group Housing
Estimated Finish Date (in online form) 31-05-2020 Project Registration Valid till
(as per registration certificate)
5/31/2018 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 5/31/2021
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 5/11/2016
Permission/Approval of Building Plan Valid Till 4/30/2022 View
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Delay is on account of force majeure condition arising from Corona Pandemic (as recognized by the Authority vide its order No. F1(146)RJ/RERA/2020/848 dated 13-05-2020)
Declaration cum Undertaking for Extension of Registration

I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e., 5/31/2021 and that all the information provided in this application is true and correct.

Registered Phase Area

Online Phase Area
8098.74
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
8098.74 ₹ 40,494.00 ₹ 0.00 ₹ 40,494.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip