Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2024-1345 (10/15/2024)
Project Name MOJIKA ULTIMA PHASE II Promoter Name MOJIKA REAL ESTATE AND DEVELOPERS PVT LTD
Project Registration No. RAJ/P/2019/1118 Project Type Mixed
Estimated Finish Date (in online form) 30-06-2022 Project Registration Valid till
(as per registration certificate)
6/30/2022 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 6/30/2026
Duration of extension being sought 24 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 9/25/2019
Permission/Approval of Building Plan Valid Till 10/3/2023 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
That we are trying to mention the list of 86 allottees in the present application but despite of our several attempts it could not be uploaded and IT Request is pending so we attached PDF of same.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
In case of extension beyond one year (on grounds other than force majeure/corona pandemic)
State clearly the exceptional and compelling circumstances and reasons due to which the project could not be completed even with in the extended period of one year View
RWA Constituted or not
Total no. of units 528
No.of units sold booked/alloted/sold as per RC/latest QPR 86
No.of units sold booked/alloted/sold till date 86
Number of allottees, if any, who have consented or have no objection to the prposed extension being granted 0 View
No.of allottees, who need to be given a notice by the Authority to ascertain if they have any objection to the proposed extension being granted 86
Form R2
Estimated Construction Cost (Table A+B) ₹ 1,11,42,49,224.00
Cost Incurred on Construction (Table A+B) ₹ 36,00,00,000.00
Form R3
Total Estimated Land Cost ₹ 8,53,50,776.00
Total Cost Incurred on Land ₹ 3,74,75,150.00
Total Estimated Development Cost ₹ 1,11,42,49,224.00
Total Cost Incurred on Development ₹ 32,61,19,295.00
Additional Information
The reason for obtaining the extension is explained in explanatory note.
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,6/30/2026 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 10/3/2023; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 6/30/2026 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
9308.49
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
9308.49 ₹ 8,37,770.00 ₹ 1,39,628.00 ₹ 5,58,510.00 ₹ 1,39,628.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
MUDIT AGARWAL 9829369795 camuditagarwal87@gmail.com
Comments Details
PARA Created BY Comments Date Status Document
1 Veer Bahadur Gurjar (10678) Extension fees Rs.139630/- Standard fees Rs.558510/-And Penalty Rs.139630/- Total Fees Rs.837770/- Deposited by RERA Transaction No.366 Dated 15.10.2024 for extension one years phase Area 9308.49 Sq. Mt. 10/16/2024 PENDING WITH NODAL OFFICER
2 Jitendra Tripathi (10665) In application promoter requested under explanatory note "that we are trying to mention the list of 86 allottees under allottee details tab in the present application but despite of our several attempts it could not be uploaded and IT Request is pending so we attached PDF of same". so kindly resolve the same. 10/18/2024 PENDING WITH ADDITIONAL DIRECTOR (I.T)
3 Mukesh Arora (11292) No.of units sold booked/alloted/sold till date is mentioned as 38 so system allows to enter 38 allottee details only. You may object and ask promoter to make the changes accordingly. That is what we have mentioned in IT request as well. 10/18/2024 PENDING WITH NODAL OFFICER
4 Jitendra Tripathi (10665) As mentioned at Para 3/N, kindly correct allottee details. comply on or before 25.10.2024 10/22/2024 APPLICATION OBJECTED
5 Promoter Sir IT Error resolved now for your purusal User updated this details. 10/22/2024 PENDING WITH NODAL OFFICER
6 Jitendra Tripathi (10665) Promoter has submitted the said application for the extension in accordance with the Authority’s order dated 22.05.2020 i.e., giving the Exceptional and compelling circumstances and reasons and the contact details of 86 allottees (Postal address & Email ID). Therefore, application is submitted for kind perusal and decision to schedule the date of hearing so that the notices may be issued to the promoter and the allottees (as per contact details submitted by the promoter) regarding extension of registration beyond 1 year i.e. 30-06-2026 (24 months) w.r.t. attached checklist. 10/22/2024 PENDING WITH JOINT REGISTRAR
7 R.S. Kulhari (9009) Submitted for fixing the date and time of hearing of promoter and the allottees as the extension sought is beyond one year, Madam. 10/24/2024 PENDING WITH CHAIRMAN
8 Chairman Rajasthan (1) 8.11.24 at 11.30 am 10/24/2024 PENDING WITH REGISTRAR
9 R.S. Kulhari (9009) Online notices issued. Check notices and if e-mail of any allottee is not available or online notice could not be issued, send it by speed post. 10/24/2024 PENDING WITH NODAL OFFICER
10 Jitendra Tripathi (10665) Application is submitted for kind perusal and approval of the extension up to 30-06-2026 (24 months), while mentioning the special conditions in Form F, as follows: 1. Last extension is granted, No Further extension shall be given; 2. A project development & progress review will be held by Authority; 3. The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain a completion certificate from the competent authority, and offer possession to the allottees, within the extended period of registration, i.e., latest by 30-06-2026; 4. The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs); and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; 5. This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; 6. The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan submitted by the promoter; 11/8/2024 PENDING WITH JOINT REGISTRAR
11 R.S. Kulhari (9009) Submitted for kind perusal and approval, Madam. 11/8/2024 PENDING WITH CHAIRMAN
12 Chairman Rajasthan (1) extension granted with the following conditions: 1. Last extension is granted, No Further extension shall be given; 2. A project development & progress review will be held by Authority; 3. The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain a completion certificate from the competent authority, and offer possession to the allottees, within the extended period of registration, i.e., latest by 30-06-2026; 4. The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs); and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; 5. This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; 6. The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan submitted by the promoter; 11/11/2024 Application Approved