Project Extension View

RERA

Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2022-933 (9/21/2022)
Project Name Saavyas Promoter Name SKG B3B LLP
Project Registration No. RAJ/P/2017/186 Project Type Group Housing
Estimated Finish Date (in online form) 29-09-2021 Project Registration Valid till
(as per registration certificate)
9/30/2020 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 9/29/2023
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 8/24/2017
Permission/Approval of Building Plan Valid Till 10/31/2022 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Due to Covid-19 and non payment of amount by the allottees.
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
In case of extension beyond one year (on grounds other than force majeure/corona pandemic)
State clearly the exceptional and compelling circumstances and reasons due to which the project could not be completed even with in the extended period of one year As per explanatory note attached. View
RWA Constituted or not
Total no. of units 312
No.of units sold booked/alloted/sold as per RC/latest QPR 264
No.of units sold booked/alloted/sold till date 275
Number of allottees, if any, who have consented or have no objection to the prposed extension being granted 0 View
No.of allottees, who need to be given a notice by the Authority to ascertain if they have any objection to the proposed extension being granted 275
Form R2
Estimated Construction Cost (Table A+B) ₹ 23,27,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 11,79,00,000.00
Form R3
Total Estimated Land Cost ₹ 5,43,00,000.00
Total Cost Incurred on Land ₹ 5,43,00,000.00
Total Estimated Development Cost ₹ 27,34,00,000.00
Total Cost Incurred on Development ₹ 23,35,18,721.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,9/29/2023 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 10/31/2022; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 9/29/2023 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
5154.06
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
5154.06 ₹ 77,320.00 ₹ 25,771.00 ₹ 51,541.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
Akshita Agarwal 9358812008 akshita@rngca.com
Comments Details
PARA Created BY Comments Date Status Document
1 Rishabh Sharma (10665) Verify the fee deposited. 9/21/2022 PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER
2 Madan Pareek (16059) Rs. 77320/- deposited by Rera Trans. No. 61 dated 21.09.2022 for extension of registration ( other than corona pandemic ). 9/23/2022 PENDING WITH NODAL OFFICER
3 Rishabh Sharma (10665) 1. Update the application w.r.t. the Authority's order dated 22.05.2020, i.e., for beyond one year; 2. Approval letter not uploaded; 3. Also mention the Explanatory note properly. Comply with the objections on or before 06.10.2022. 9/27/2022 APPLICATION OBJECTED
4 Promoter Dear Sir, We have updated the application and approval letter is attached herewith for your perusal. Also, enclosed explanatory note mentioning the reasons for the delay. Please see the same and approve the application. User updated this details. 9/27/2022 PENDING WITH NODAL OFFICER
5 Rishabh Sharma (10665) Promoter has submitted the said application for the extension in accordance with the Authority’s order dated 22.05.2020 i.e., giving the Exceptional and compelling circumstances and reasons and the contact details of 275 allottees. Therefore, application is submitted for kind perusal and decision to schedule the date of hearing so that the notices may be issued to the promoter and the allottees (as per contact details submitted by the promoter) regarding extension of registration beyond 1 year i.e. 29-09-2023 (12 months) w.r.t. the attached checklist. 9/28/2022 PENDING WITH JOINT REGISTRAR
6 Arpit Sancheti (10683) Submitted for kind perusal and further orders regarding extension pls. 9/28/2022 PENDING WITH REGISTRAR
7 Ramesh Sharma (9009) Submitted for perusal and fixing the date of hearing. 9/28/2022 PENDING WITH CHAIRMAN
8 NIHAL CHAND GOEL (1) As notices are to be issued by speed post, hearing fixed for 31.10.2022 at 1 pm. 9/28/2022 PENDING WITH REGISTRAR
9 Ramesh Sharma (9009) Notice, issued put up on date of hearing. 9/29/2022 PENDING WITH NODAL OFFICER
10 Rishabh Sharma (10665) Application is submitted for kind perusal and approval of the extension w.r.t. the attached note sheet while mentioning the special conditions in Form F as follows: 1. The promoter shall complete the work of Block A in all respects, including common areas, facilities and amenities thereof, and obtain partial completion certificate from the competent authority, latest by 30.04.2023; 2. The promoter shall prepare and provide by 30.11.2022, a detailed construction and development plan to achieve completion of all the remaining development works by 29.09.2023, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it; 3. The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 29.09.2023; 4. The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30.11.2022; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; 5. This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and 6. The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 30.11.2022. 11/18/2022 PENDING WITH JOINT REGISTRAR
11 Arpit Sancheti (10683) Submitted for kind perusal and approval pls. 11/18/2022 PENDING WITH REGISTRAR
12 Ramesh Sharma (9009) Submitted for perusal and approval,sir. 11/18/2022 PENDING WITH CHAIRMAN
13 NIHAL CHAND GOEL (1) Approved with special conditions kas follows: 1. The promoter shall complete the work of Block A in all respects, including common areas, facilities and amenities thereof, and obtain partial completion certificate from the competent authority, latest by 30.04.2023; 2. The promoter shall prepare and provide by 30.11.2022, a detailed construction and development plan to achieve completion of all the remaining development works by 29.09.2023, which will then be monitored, on quarterly basis, by the Authority or a consultant appointed by it; 3. The promoter shall complete the project in all respects, including common areas, facilities and amenities, obtain completion certificate from the competent authority, and offer possession to the allottees, as soon as possible, within the extended period of registration, i.e., latest by 29.09.2023; 4. The promoter shall submit online all the pending Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) latest by 30.11.2022; and shall submit regularly the QPRs and APRs as fall due during the extended period of registration; 5. This extension of registration is granted without any prejudice to the rights of the allottees under their respective agreements for sale or the RERA Act, including their right to demand interest/compensation for the period of delay in delivering possession of the allotted flat; and 6. The Authority may take any action against the promoter, under the RERA Act and the rules and regulations made thereunder, and may also revoke registration of the project, at any time during the extended period of registration, if any of the conditions of this extension is not complied with or if completion of the remaining development works is not found to be progressing as per the detailed construction and development plan promoter is required to submit by 30.11.2022. 11/21/2022 Application Approved