Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2021-658 (11/10/2021)
Project Name Om Residency Promoter Name Surya Builders and Developers
Project Registration No. RAJ/P/2017/420 Project Type Group Housing
Estimated Finish Date (in online form) 30-09-2019 Project Registration Valid till
(as per registration certificate)
9/30/2019 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 9/30/2020
Duration of extension being sought 12 Months 0 Days
Project Building Plan Details
First Approval Date of Building Plan 12/29/2016
Permission/Approval of Building Plan Valid Till 12/29/2023 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Due to delay in obtaining CC & impact of first & second wave of covid 19
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 16,73,525.00
Cost Incurred on Construction (Table A+B) ₹ 16,73,525.00
Form R3
Total Estimated Land Cost ₹ 93,18,187.20
Total Cost Incurred on Land ₹ 93,18,187.00
Total Estimated Development Cost ₹ 16,73,525.00
Total Cost Incurred on Development ₹ 16,73,525.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,9/30/2020 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).

Registered Phase Area

Online Phase Area
1338.82
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
1338.82 ₹ 40,164.00 ₹ 6,694.00 ₹ 26,776.00 ₹ 6,694.00 Paid

Payment Slip

Print receipt
Extension Payment Slip
Comments Details
PARA Created BY Comments Date Status Document
1 Rishabh Sharma (10665) Verify the fee deposited. 11/11/2021 PENDING WITH PENDING WITH DA/ ACCOUNTS/ LEGAL OFFICER/ LAW OFFICER
2 Madan Pareek (16059) Rs. 40164/- deposited by Rera Trans. No. 16184 dated 10.11.2021 for extension of registration ( other than corona pandemic ). 11/11/2021 PENDING WITH NODAL OFFICER
3 Rishabh Sharma (10665) In reference to your explanatory note, kindly upload the CC in the Other Documents tab. 11/11/2021 APPLICATION OBJECTED
3 Promoter In reference to our explanatory note we hereby would like to submit that CC of our project was received in September, 2021 quarter due to which we have to apply for 2 year extension of project. We will submit Completion Certificate with Extension application in which we will apply for grant of extension till 30-09-2021. We request the authority to kindly approve Extension till 30-09-2020. User updated this details. 11/12/2021 PENDING WITH NODAL OFFICER
4 Rishabh Sharma (10665) Upload the CC in the said application first, then the application will get processed. 11/12/2021 APPLICATION OBJECTED
5 Ramesh Sharma (9009) Record Pulled by REGISTRAR 12/15/2021 PENDING WITH REGISTRAR
6 Ramesh Sharma (9009) Process if correct. 12/15/2021 PENDING WITH NODAL OFFICER
7 Rishabh Sharma (10665) Promoter has applied for the extension of 1 year i.e., upto 30-09-2020 in Force Majeure condition, and in reference to their last filed QPR for the quarter July to September, 2019, 100% work has been completed. However, please peruse the para 3/N, where promoter has stated was received in September 2021, therefore if this extension got approved still promoter needs to apply for further extension. Submitted for kind perusal and decision regarding extension of registration upto 30.09.2020. 12/15/2021 PENDING WITH JOINT REGISTRAR
8 Arpit Sancheti (10683) In reference to para 7/N, submitted for further orders regarding extension pls. 12/15/2021 PENDING WITH REGISTRAR
9 Ramesh Sharma (9009) Submitted for perusal and approval,sir. 12/16/2021 PENDING WITH CHAIRMAN
10 NIHAL CHAND GOEL (1) Rest is ok, but this extension cannot be granted on grounds of Force Majeure (Corona), though the next extension may be granted on grounds of Force Majeure. So, in this application, get the reason changed to Other than Force Majeure. 12/16/2021 PENDING WITH REGISTRAR
11 Ramesh Sharma (9009) Comply with the directions of Hon'ble Chairman. 12/16/2021 PENDING WITH JOINT REGISTRAR
12 Arpit Sancheti (10683) Comply as directed. 12/16/2021 PENDING WITH NODAL OFFICER
13 Rishabh Sharma (10665) You are hereby informed that this extension cannot be granted on grounds of Force Majeure (Corona), though the next extension may be granted on grounds of Force Majeure. So, in this application, get the reason changed to Other than Force Majeure. 12/17/2021 APPLICATION OBJECTED
13 Promoter Sir, We have changed reason for extension to Other than Force Majeure. User updated this details. 12/20/2021 PENDING WITH NODAL OFFICER
14 Rishabh Sharma (10665) In reference to para 10/N, promoter has updated the "Reason for Modification" as Other than Force Majeure. Application is submitted for kind perusal and approval, please. 12/20/2021 PENDING WITH JOINT REGISTRAR
15 Arpit Sancheti (10683) In reference to para 10/N, promoter has rectified the application. Therefore, submitted for kind perusal and further orders regarding extension pls. 12/20/2021 PENDING WITH REGISTRAR
16 Ramesh Sharma (9009) Submitted for perusal and approval, Sir. 12/20/2021 PENDING WITH CHAIRMAN
17 NIHAL CHAND GOEL (1) approved 12/20/2021 Application Approved