Quarterly Progress Report Summary Details July to September, 2017

Quarterly Progress Report Summary Details July to September, 2017

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2021-970 (31/03/2021)
Name of the Registered project Ashiana Nirmay Ph. I Registration No. of the Project RAJ/P/2017/028
Name of the Promoter Ashiana Housing Limited Name of other Promoter(s) None
Project Address Khasra No./ Plot No.152 to 156,159 to 163, 355/166, 168, 169, 171 to 174, 179 , Village- Thara , Thara Village Road , Alwar - 301018 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 160
Total Area of Project(In sq. meters) 34,364.00 Phase Area (In sq. meters) 9,504.00
Registration certificate is valid upto 30-06-2018 Registration extended upto Not Applicable
II. Number and type of apartments booked ( July to September, 2017 )
Building Name : B-01,B-02
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
1BHK 51.88 7.15 20 20
2BHK+ Store 81.28 6.69 60 37
3 BHK 99.14 13.14 80 46
Total 160 103 0
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( July to September, 2017 )

TABLE - A

Building Name: B-01,B-02
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 0 100.00
2 0 Number of Basement(s) and Plinth 0 100.00
3 1 Number of Stilt Floor 0 100.00
4 13 Number of Slabs of Super Structure 0 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 0 100.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 50.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 80.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 75.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 70.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 55
2 Water Supply 0 65
3 Sewerage (chamber, lines, Septic Tank STP) 0 70
4 Storm Water Drainss 0 70
5 Landscaping & Tree Planting 0 20
6 Street Lighting 0 55
7 Community Building 0 70
8 Treatment and disposal of sewage and sullage water 0 25
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 75
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 70
13 Electrical meter room, sub-station, receiving station 0 50
Form R1: Date of issue
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( July to September, 2017 )

TABLE - A

Building Name : B-01,B-02
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 0.00 300,222,000.00
2 Cost incurred against the estimated cost 0.00 244,746,084.00
3 Work done (as Percentage of the estimated cost) % 0 82.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 0.00 55,475,916.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 0.00 107,232,707.00
2 Cost incurred against the estimated cost 0.00 71,412,000.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 0.00 67.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 0.00 35,820,707.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( July to September, 2017 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 43,716,607.00 0.00 43,716,607.00
B. Development Cost/Cost of Construction 407,454,707.00 0.00 219,117,408.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 0.00 262,834,015.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 0.00 0.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 0.00 262,834,015.00
Form R3: Date of issue
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0
4 Electrification(Transformer, Solar Energy etc) 0
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 05/01/2015
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Planned date of Insurance 01/12/2023

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
• Date of completion certificate.
29/01/2018
• Has the Completion certificate been uploaded on RERA web portal?
4. Has the Occupancy Certificate also been obtained?
• Date of occupancy Certificate.
19/02/2018
• Has the Occupancy certificate been uploaded on RERA web portal?
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 RUPALSHARMA (20647) The submission date for Quarter July to September 2017 is 16.02.2022 and accordingly the delay processing charge has been deposited. QPR maybe accepted subject to verification. Submitted for perusal and approval, Please. 2/17/2022 PENDING WITH JOINT REGISTRAR
2 Arpit Sancheti (10683) Wrong Fee receipt is attached. Kindly check. 2/18/2022 PENDING WITH JOINT DIRECTOR (I.T)
3 Mukesh Arora (11292) Issue is fixed now. 2/23/2022 PENDING WITH NODAL OFFICER
4 RUPALSHARMA (20647) QPR maybe accepted subject to verification. Submitted for perusal and approval, Please. 4/8/2022 PENDING WITH JOINT REGISTRAR
5 Arpit Sancheti (10683) QPR is accepted subject to verification. 4/11/2022 Application Approved
Nodal Officer: Rishabh Sharma, Contact: 0141-2851900, E-Mail: arp2@rajasthan.gov.in

Copyright © 2023. This is the official website of Real Estate Regulatory Authority, Rajasthan. All Rights Reserved.