Quarterly Progress Report Summary Details April to June, 2023
I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2023-19390 (31/07/2023)
|
||||
---|---|---|---|---|
Name of the Registered project | Ashiana Umang Phase V and Ashiana Umang Plaza | Registration No. of the Project | RAJ/P/2021/1430 | |
Name of the Promoter | Ashiana Housing Limited | Name of other Promoter(s) | None | |
Project Address | Khasra No./ Plot No.432,433, 434,434/735,435,436,437,437/736,438,439,440,453,454,454/2,454/1,478,478/716,479,480,481,482,484,485,500,502,503,504/1, , Village- Village Jhai , Near Mahindra SEZ, Ajmer Road , Jaipur - 302026 (Rajasthan) | |||
Type of Project | Group Housing | Number of Sanctioned Apartments/Plots | 328 | |
Total Area of Project(In sq. meters) | 79,144.22 | Phase Area (In sq. meters) | 19,618.40 | |
Registration certificate is valid upto | 31-10-2024 | Registration extended upto | Not Applicable |
II. Number and type of apartments booked ( April to June, 2023 ) | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block P | ||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block P1 | ||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | |||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block S | |||||||||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block S1 | ||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block S2 | ||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | |||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block S3 | |||||||||||||||||||||||||||||
|
II. Number and type of apartments booked ( April to June, 2023 ) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Building Name : Block T | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
III. Number of parkings allotted | ||||||||
---|---|---|---|---|---|---|---|---|
Type | Total No. of Car parking | Total No. of Two Wheeler parking | Total No. of cycle parking | Total No of Mechanical Car Parking | Total No. of parking allocated at the time of registration or by the end of last quarter | Cumulative No. of parking allocated by the end of current quarter | ||
Location | Car | Two Wheelers | Car | Two Wheelers | ||||
Open Area | ||||||||
Stilt Floor | ||||||||
Basement | ||||||||
Any Other Floor | ||||||||
Total |
IV. Status of the Project Construction/Development | ||||||||
---|---|---|---|---|---|---|---|---|
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
TABLE - A |
||||||||
Building Name: Block P | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 81 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 0 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 62 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 0 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block P1 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 82 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 0 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 62 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 0 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block S | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 88 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 70 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 76 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 37 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block S1 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 81 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 70 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 67 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 37 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block S2 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 81 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 0 | 95.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 67 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 0 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block S3 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 1 Number of Stilt Floor | 100 | 100.00 | |||||
4 | 14 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 80 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 0 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 0 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 63 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 0 | 60.00 | |||||
IV. Status of the Project Construction/Development | ||||||||
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
Building Name: Block T | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
In Last Quarter | In Current Quarter | |||||||
1 | Excavation | 100 | 100.00 | |||||
2 | 1 Number of Basement(s) and Plinth | 100 | 100.00 | |||||
3 | 0 Number of Stilt Floor | 0 | 100.00 | |||||
4 | 3 Number of Slabs of Super Structure | 100 | 100.00 | |||||
5 | Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises | 100 | 95.00 | |||||
6 | Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises | 100 | 63.00 | |||||
7 | Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks | 100 | 100.00 | |||||
8 | The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing | 100 | 70.00 | |||||
9 | Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate | 100 | 60.00 |
TABLE - B |
|||||||
---|---|---|---|---|---|---|---|
Internal and External Development Works for the entire registered Phase/Project |
|||||||
S.No. | Common areas and Facilities/Amenities | Proposed Yes/No | Percentage of work done | Details if any | |||
By the end of Last Quarter | By the end of Current Quarter | ||||||
1 | Internal Roads & Footpaths | 0 | 0 | ||||
2 | Water Supply | 4 | 50 | ||||
3 | Sewerage (chamber, lines, Septic Tank STP) | 50 | 50 | ||||
4 | Storm Water Drainss | 10 | 55 | ||||
5 | Landscaping & Tree Planting | 0 | 0 | ||||
6 | Street Lighting | 0 | 0 | ||||
7 | Community Building | 60 | 100 | ||||
8 | Treatment and disposal of sewage and sullage water | 0 | 50 | ||||
9 | Solid Waste management & Disposal | 0 | 0 | ||||
10 | Water conservation, Rain water harvesting | 20 | 45 | ||||
11 | Energy management | 0 | 0 | ||||
12 | Fire protection and fire safety requirements | 0 | 0 | ||||
13 | Electrical meter room, sub-station, receiving station | 0 | 0 | ||||
Form R1: Date of issue
17/07/2023
|
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
TABLE - A |
||||||||
Building Name : Block P | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 123,629,969.00 | 123,629,969.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 94,669,726.00 | 110,374,381.70 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 77 | 89.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 28,960,243.00 | 13,255,587.29 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block P1 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 110,193,085.00 | 110,193,085.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 85,084,569.00 | 99,039,034.17 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 77 | 86.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 25,108,516.00 | 15,564,231.92 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block S | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 101,666,712.00 | 101,666,712.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 81,266,259.00 | 90,821,830.59 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 80 | 89.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 20,400,453.00 | 10,844,881.40 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block S1 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 84,788,063.00 | 84,788,063.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 65,026,259.00 | 75,896,220.10 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 77 | 87.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 19,761,804.00 | 10,953,129.48 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block S2 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 84,788,063.00 | 84,788,063.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 65,026,259.00 | 73,475,308.00 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 77 | 85.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 19,761,804.00 | 13,374,041.57 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block S3 | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 97,551,857.00 | 97,551,857.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 64,149,697.00 | 85,641,686.74 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 66 | 84.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 33,402,160.00 | 16,025,025.26 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2023 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Building Name : Block T | ||||||||
S.No. | Task/Activity | Percentage of work done | ||||||
By the end of Last Quarter | By the end of Current Quarter | |||||||
1 | Total Estimated cost of the building | ₹ | 14,267,825.00 | 14,267,825.00 | ||||
2 | Cost incurred against the estimated cost | ₹ | 14,267,825.00 | 14,596,971.80 | ||||
3 | Work done (as Percentage of the estimated cost) | % | 100 | 96.00 | ||||
4 | Balance Cost to be Incurred (Bases on Estimated Cost) | ₹ | 0.00 | 615,110.29 | ||||
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
TABLE - B |
||||
---|---|---|---|---|
Internal and External Development Works for the entire registered Phase/Project |
||||
S.No. | Particulars | By the end of Last Quarter | By the end of Current Quarter | |
1 | Total Estimated cost of the Internal and External Development Works including amenities and Facilities | ₹ | 136,040,700.00 | 136,040,700.00 |
2 | Cost incurred against the estimated cost | ₹ | 82,235,388.00 | 105,513,736.00 |
3 | Work done in Percentage (as Percentage of the estimated Cost) | % | 60.00 | 78.00 |
4 | Balanced Cost to be Incurred (Based on Estimated Cost) | ₹ | 53,805,312.00 | 30,526,964.00 |
5 | Cost Incurred on Additional/Extra Items not included in the Estimated Cost | ₹ | 0.00 | 0.00 |
Summary of Table A and Table B |
||||
---|---|---|---|---|
S.No. | Particulars | In Last Quarter | In Current Quarter | |
1. | Total Estimated Construction Cost | ₹ | ||
2. | Total Cost Incurred on Construction | ₹ | ||
3. | Percentage of Cost Incurred | % |
Form R2: Date of issue
31/07/2023
|
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( April to June, 2023 ) | |||||
---|---|---|---|---|---|
Incurred Amount | |||||
S.No. | Particulars | Estimated Amount (as per online details) |
By the end of Last Quarter | By the end of Current Quarter | |
1 | A. Land Cost | ₹ | 227,217,575.00 | 0.00 | 227,273,524.00 |
B. Development Cost/Cost of Construction | ₹ | 857,659,874.00 | 87,469,396.00 | 788,055,956.00 | |
C. Total project cost(A+B) | ₹ |
In Last Quarter | In Current Quarter | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | Percentage of total cost incurred on land | % | ||||||||||||
3 | Percentage of total cost incurred on development | % | ||||||||||||
4 | Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) | % | ||||||||||||
5 | Percentage of the Cost incurred on Land Cost to the Total Estimated Cost | % | ||||||||||||
6 | Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost | % | ||||||||||||
7 | Amount Which can be withdrawn from the separate Account | ₹ | 87,469,396.00 | 1,015,329,480.00 | ||||||||||
8 | Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements | ₹ | 45,153,115.00 | 809,864,619.00 | ||||||||||
9 | Net Amount Which can be withdrawn from the Separate bank account under this certificate | ₹ | 42,316,281.00 | 205,464,861.00 | ||||||||||
Form R3: Date of issue
25/07/2023
|
||||||||||||||
Certificate showing no linen or charge on the RERA retention Account :
|
||||||||||||||
|
V. Project Common Area Details- Development Work For Whole Project | |||||
---|---|---|---|---|---|
S. No. | Common Area And Facilities, Amenities | Proposed | Percentage Of Completion (%) | Drawings uploaded in online Project details or not | If no, Planned date of uploading of these drawings |
1 | Water Supply | 50 |
|
||
2 | Rain Water Harvesting/ Recharging | 45 |
|
||
3 | Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) | 55 |
|
||
4 | Electrification(Transformer, Solar Energy etc) | 0 |
|
||
5 | Fire Fighting Provision | 90 |
|
||
6 | Others | 0 |
|
VI. Status of Approvals | ||||
---|---|---|---|---|
A | Noc's/Permission | Present Status | ||
1 |
|
|
||
2 |
|
|
||
3 |
|
|
||
4 |
|
|
||
5 |
|
|
||
B. | Revision of Building Plans | |||
1 | Date of approval of latest Building Plans already uploaded on RERA web portal |
29/11/2021 |
||
2 | Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded? |
|
VII. Compliances Under the Act | ||||
---|---|---|---|---|
1. | ||||
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and
(ii) construction of the Real Estate Project. Has the insurance been obtained? |
|
|||
• Has the Insurance been uploaded on RERA web portal? |
|
|||
• Planned date of uploading Insurance Certificate |
31/12/2024 |
2. | ||
---|---|---|
Since more than 50% apartments have been booked, the formation of association of allottees has become due under Section 11(4) (e) of the RERA Act. Has the association of allottees been formed? |
|
|
• Has it been registered? |
|
|
» Has the Registration Certificate of association been uploaded on RERA web portal? |
|
|
» Planned date of uploading Registration Certificate of association |
31/12/2024 |
|
If formation/registration of association of allottees is not proposed, explain reasons thereof |
VIII. Details of Real Estate Agents (if any) engaged for the Project
IX. Miscellaneous
Allottee Details
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | L2-2108 | Unsold | |
2 . | L2-13105 | Sold | Mr. Navin Tiwari & Atmika Kaushik |
3 . | L2-10107 | Sold | Mr. Jagveer Singh Bidawat & Monica Raolot Bidawat |
4 . | L2-6108 | Sold | Mr. Sanjay Singh Bhamboo & Ramniwas |
5 . | L2-4106 | Sold | Mr. Sunil Kumar Sharma |
6 . | L2-3106 | Sold | Mohd. Ahmed Hussain |
7 . | L2-1105 | Unsold | |
8 . | L2-10108 | Sold | Mrs. Bharti Juyal & Rachit Kumar Girdhar |
9 . | L2-8106 | Sold | Mr. Nikhil Kumar Sa & Neha Sa |
10 . | L2-7106 | Unsold | |
11 . | L2-5105 | Sold | Mr. Rajendra Sharma |
12 . | L2-2107 | Sold | Mrs. Ritu Pasbola & Ashish Pasbola |
13 . | L2-12108 | Sold | Mrs. Rekha Anoop Agarwal & Anoop Kumar S Agarwal |
14 . | L2-10106 | Sold | Mr. Dhiraj Wanchoo & Suveni Kaul |
15 . | L2-9106 | Sold | Mrs. Mithlesh Meena |
16 . | L2-7105 | Sold | Ms. Vibha Tomar |
17 . | L2-4107 | Sold | Mrs. Mina |
18 . | L2-8108 | Unsold | |
19 . | L2-6106 | Sold | Mrs. Sunita Lakhyani & Amit Kumar Ahuja |
20 . | L2-5106 | Unsold | |
21 . | L2-3105 | Unsold | |
22 . | L2-13106 | Unsold | |
23 . | L2-11105 | Sold | Mrs. Asha Mathur |
24 . | L2-8107 | Sold | Mrs. Neelam Bhardwaj |
25 . | L2-4108 | Sold | Mrs. Deepika Gaur |
26 . | L2-2106 | Sold | Mr. Jatin Sangivieya |
27 . | L2-1106 | Unsold | |
28 . | L2-12107 | Sold | Mr. Pramod Bhargava & Preeti Pramod Bhargava |
29 . | L2-12106 | Sold | Mrs. Alka Kumari |
30 . | L2-11106 | Sold | Mrs. Neelam Bhati & Kamal Singh Bhati |
31 . | L2-9105 | Sold | Mr. Pranay Singh |
32 . | L2-6107 | Sold | Mrs. Meena |
33 . | L2-1107 | Sold | Mrs. Jaya Jain |
34 . | L2-5108 | Sold | Mr. Ajay Kumar Mehalwal |
35 . | L2-3107 | Sold | Mr. Arun Kumar Singh & Richa Singh |
36 . | L2-7108 | Sold | Mrs. Pallavi Murarka & Ashim Kumar Sharma |
37 . | L2-7107 | Sold | Mr. Ashim Kumar Sharma & Pallavi Murarka |
38 . | L2-4105 | Sold | cMr. Vaibhav Jain |
39 . | L2-11108 | Sold | Mrs. Sonam Gupta |
40 . | L2-11107 | Sold | Mr. Amit Sihag |
41 . | L2-8105 | Sold | Mr. Sumit Aggarwal |
42 . | L2-9107 | Sold | Mrs. Shweta Khanna & Karan Khanna |
43 . | L2-6105 | Sold | Mrs. Sunita Sharma |
44 . | L2-13108 | Unsold | |
45 . | L2-13107 | Cancelled | |
46 . | L2-10105 | Sold | Mrs. Shambhavi Goswami |
47 . | L2-1108 | Sold | Mr. Rahul Baid & Jaya Jain |
48 . | L2-5107 | Sold | Mrs. Martha |
49 . | L2-2105 | Sold | Mr. Ajay Kumar & Vandana |
50 . | L2-9108 | Sold | Mrs. Preeti Athiya & Kumar Raghav Ganesan |
51 . | L2-12105 | Sold | Mr. Goverdhan Kothari |
52 . | L2-3108 | Sold | Mrs. Deepa Devi |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | L3-1090 | Sold | Mr. Atanu Mukherjee & Neha Mukherjee |
2 . | L3-590 | Sold | Mr. Nikhil Jain & Anju C |
3 . | L3-390 | Sold | Mrs. Priyanka Rai |
4 . | L3-1390 | Unsold | |
5 . | L3-1190 | Sold | Mrs. Priya Shukla & Harsh Jain |
6 . | L3-789 | Sold | Mrs. Indu Kaler |
7 . | L3-289 | Sold | Mr. Udit Gupta |
8 . | L3-1089 | Sold | Mrs. Shabda Pandey |
9 . | L3-1189 | Sold | Mrs. Shalini Sharma & Vipin Mohan Sharma |
10 . | L3-689 | Sold | Mr. Shani Pal & Mukesh Devi |
11 . | L3-690 | Sold | Mrs. Nidhi Jain |
12 . | L3-190 | Sold | Mr. Jagdish Godara |
13 . | L3-990 | Sold | Mrs. Tarini Kaushik & Shruti Kaushik |
14 . | L3-790 | Sold | Mrs. Sudha Kulkarni |
15 . | L3-389 | Sold | Mr. Naveen Kumar |
16 . | L3-290 | Sold | Mrs. Usha Sharma |
17 . | L3-889 | Sold | Mrs. Ruchi Verma |
18 . | L3-189 | Sold | Mr. Jagdish Lal Sharma |
19 . | L3-1289 | Sold | Mrs. Astha Choudhary |
20 . | L3-589 | Sold | Mr. Rahul Sharma & Krishna Lagria |
21 . | L3-1389 | Unsold | |
22 . | L3-490 | Sold | Mrs. Bhavana Khare |
23 . | L3-890 | Sold | Mr. Saurabh Yadav |
24 . | L3-989 | Sold | Mrs. Aparna Vyas & Himanshu Vyas |
25 . | L3-489 | Sold | Mr. Sundeep Jaiman |
26 . | L3-1290 | Sold | Mr. Ashish Laxminarayan Maharshi |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | M2-896 | Sold | Ms. Isha Jain |
2 . | M2-694 | Sold | Mr. Rohit Soni |
3 . | M2-594 | Sold | Mr. Aditya Saxena |
4 . | M2-393 | Unsold | |
5 . | M2-1296 | Sold | Mr. Anita Arora |
6 . | M2-1094 | Sold | Mr. Radhey Shyam Sharma |
7 . | M2-994 | Sold | Mrs. Kiran Tripathi |
8 . | M2-793 | Sold | Mrs. Manisha Yadav & Mayank Yadav |
9 . | M2-1394 | Sold | Mrs. Seema Mishra |
10 . | M2-1193 | Sold | Mr. Chandan Mishra |
11 . | M2-296 | Unsold | |
12 . | M2-1393 | Sold | Mr. Rajesh Kumar Mishra |
13 . | M2-1294 | Sold | Mrs. Shalini Sukheeja & Aditi Sukheeja |
14 . | M2-1194 | Sold | Mr. Sudhir Kumar |
15 . | M2-993 | Sold | Mrs. Neha Sharma |
16 . | M2-696 | Sold | Mr. Utkarsh Soni |
17 . | M2-494 | Sold | Mrs. Smita Sharma & Amit Sharma |
18 . | M2-394 | Sold | Mrs. Nirmala |
19 . | M2-193 | Sold | Mr. Shreepal Singh Yadav |
20 . | M2-1096 | Sold | Mrs. Rakshita Negi |
21 . | M2-894 | Sold | Mr. Amit Joshi & Ankita Sharma |
22 . | M2-794 | Sold | Mrs. Varsha Joshi |
23 . | M2-593 | Sold | Mrs. Rekha & Neeraj Kumar |
24 . | M2-496 | Sold | Mrs. Rachna Joshi |
25 . | M2-294 | Sold | Mrs. Rama Seth |
26 . | M2-194 | Sold | Mrs. Divya Pratap & Bhanu Pratap |
27 . | M2-495 | Sold | Mrs. Sunita Kumari & Sachin Kumar |
28 . | M2-795 | Sold | Mr. Ashutosh Chandra |
29 . | M2-493 | Sold | Mrs. Pooja Goyal & Vishal Goyal |
30 . | M2-1196 | Sold | Mr. Jagrit Kaushik & Harit Narayan Kaushik |
31 . | M2-695 | Sold | Mr. Mohammad Rizwan |
32 . | M2-995 | Sold | Mr. Vishal Uday |
33 . | M2-693 | Sold | Mrs. Khushboo Pandita & Peuish Dhar |
34 . | M2-1396 | Unsold | |
35 . | M2-1095 | Sold | Mrs. Garima Tank & Arun Tank |
36 . | M2-1395 | Unsold | |
37 . | M2-1093 | Sold | Mrs. Namita Agarwal |
38 . | M2-196 | Unsold | |
39 . | M2-195 | Sold | Mr. Gaurav Sharma & Hemlata Sharma |
40 . | M2-596 | Unsold | |
41 . | M2-1295 | Sold | Mr. Deepak Arora |
42 . | M2-1293 | Sold | Mr. Saphiq Ahmed |
43 . | M2-396 | Sold | Mrs. Ritu Mundhara & Ritesh Mundhara |
44 . | M2-395 | Sold | Mrs. Ritu Mundhara & Ritesh Mundhara |
45 . | M2-796 | Sold | Mr. Aditya Chandra |
46 . | M2-895 | Sold | Mr. Anil Kumar Jain |
47 . | M2-1195 | Sold | Mr. Surbhit Kaushik & Harit Narayan Kaushik |
48 . | M2-893 | Sold | Mrs. Pushpa Devi |
49 . | M2-295 | Unsold | |
50 . | M2-595 | Sold | Mr. Vinod Kumar |
51 . | M2-293 | Sold | Mr. Harpal Singh & Harwinder Kaur |
52 . | M2-996 | Sold | Ms. Deepali Somra |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | M2-11100 | Sold | Mr. Karan Singh Sisodia & Swati Chauhan |
2 . | M2-998 | Sold | Mrs. Shanu Khoda |
3 . | M2-898 | Sold | Mr. Vikram Singh Rathore & Kavita Shekhawat |
4 . | M2-697 | Sold | Mr. Digvijay Shekhawat |
5 . | M2-1398 | Sold | Mrs. Sunita Khetrapal & Karan Khetrapal |
6 . | M2-1298 | Sold | Mrs. Vaisakhi Dawra |
7 . | M2-1097 | Sold | Mr. Akshat Sharma |
8 . | M2-3100 | Sold | Mrs. Manju Lata Sharma |
9 . | M2-198 | Sold | Mr. Sanket Sinha |
10 . | M2-5100 | Sold | Mrs. Rupa Mukherjee & Amit Mukherjee |
11 . | M2-398 | Sold | Mr. Rakesh Kumar Niraj & Sangeeta Kumari |
12 . | M2-298 | Sold | Mrs. Amrita Chaudhary |
13 . | M2-1100 | Unsold | |
14 . | M2-1297 | Sold | Mr. Dinesh Kumar Sharma |
15 . | M2-9100 | Sold | Mr. Purushottm & Renu Sharma |
16 . | M2-798 | Sold | Mr. Sumit Agrawal |
17 . | M2-698 | Sold | Mrs. Nidhi Ranawat |
18 . | M2-497 | Sold | Ms. Sabeena Arif |
19 . | M2-13100 | Unsold | |
20 . | M2-1198 | Sold | Mrs. Preeti Pareek |
21 . | M2-1098 | Sold | Mrs. Raj Jyoti Sharma |
22 . | M2-897 | Sold | Mr. Vipin Indora |
23 . | M2-7100 | Sold | Mr. Phool Chand |
24 . | M2-598 | Sold | Mr. Aakash |
25 . | M2-498 | Sold | Mr. Shikhar Johari |
26 . | M2-297 | Sold | Mrs. Amrita Chaudhary |
27 . | M2-799 | Sold | Mr. Devendra Singh |
28 . | M2-1099 | Sold | Mrs. Sunayana Chaudhary |
29 . | M2-797 | Sold | Mr. Sumit Agrawal |
30 . | M2-999 | Unsold | |
31 . | M2-1299 | Sold | Mr. Chirag Makhija & Rashmi Makhija |
32 . | M2-997 | Sold | Mr. Vijay Kumar Meena |
33 . | M2-1399 | Unsold | |
34 . | M2-1397 | Sold | Mrs. Sunita Khetrapal & Karan Khetrapal |
35 . | M2-4100 | Sold | Mrs. Neha Agarwal |
36 . | M2-199 | Unsold | |
37 . | M2-499 | Sold | Mrs. Rita Sarda |
38 . | M2-197 | Sold | Mr. Bishamber Dayal Yadav |
39 . | M2-8100 | Sold | Mrs. Apurva Jain |
40 . | M2-299 | Unsold | |
41 . | M2-6100 | Sold | Mrs. Anita Lamba & Chandra Prakash |
42 . | M2-399 | Sold | Mrs. Manju Lata Sharma |
43 . | M2-699 | Sold | Mrs. Anita Lamba & Chandra Prakash |
44 . | M2-397 | Sold | Mrs. Garima Sharma & Girish Sharma |
45 . | M2-10100 | Sold | Mr. Anirudh Singh Dhillon |
46 . | M2-1199 | Sold | Mr. Abhishek Vyas & Nand Kishore Vyas |
47 . | M2-1197 | Sold | Mrs. Ranu Ajay Verma |
48 . | M2-2100 | Unsold | |
49 . | M2-599 | Unsold | |
50 . | M2-899 | Unsold | |
51 . | M2-597 | Sold | Mr. Aakash |
52 . | M2-12100 | Sold | Mrs. Meenakshi Ratra |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-04 | Sold | Mr. Sharad Nagrath & Virendra Pal Nagrath |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | T2-13110 | Sold | Mrs. Soniya Nimawat |
2 . | T2-12110 | Sold | Mrs. Kavita Udawat |
3 . | T2-10109 | Sold | Mr. Ravi Mishra & Tarjani Negi |
4 . | T2-7111 | Sold | Mr. Kalpesh Soni |
5 . | T2-3112 | Sold | Mrs. Asha Jagatramka & Richa Jagatramka |
6 . | T2-1110 | Sold | Mrs. Vinita Dhariwal |
7 . | T2-11111 | Sold | Mr. Kuldeep Tak |
8 . | T2-7112 | Sold | Mrs. Neha Kalwar & Jayant Kumar Kalwar |
9 . | T2-5110 | Sold | Mr. Vinay Kumar Sharma & Raman Sharma |
10 . | T2-4110 | Sold | Mrs. Ritu Bhargava & Mr. Neeraj Bhargava |
11 . | T2-2109 | Sold | Mrs. Mukta Kumari & Mr. Shwetabh Kumar |
12 . | T2-9112 | Sold | Mr. Maneesh Saxena & Rakhi Saxena |
13 . | T2-7110 | Sold | Mr. Anirudh Sharma |
14 . | T2-6110 | Sold | Mrs. Reena Yadav |
15 . | T2-4109 | Sold | Mr. Saurabh Bohara & Shweta Bohara |
16 . | T2-1111 | Sold | Mr. Sahil Malik & Aparna Gupta |
17 . | T2-5112 | Sold | Mohammad Shafeek |
18 . | T2-3110 | Sold | Mr. Mehar Khanna |
19 . | T2-2110 | Sold | Mrs. Raman Sharma & Vinay Kumar Sharma |
20 . | T2-13111 | Sold | Mrs. Vibha Kapoor , Rakesh Kapoor & Tarun Kapoor |
21 . | T2-13112 | Sold | Mr. Gyan Prakash Dwivedi & Dipshi Tak |
22 . | T2-11110 | Sold | Mr. Vikas Narayan Kaushik & Uma Kaushik |
23 . | T2-10110 | Sold | Mr. Sharad Maheshwari & Apeksha Rathi |
24 . | T2-8109 | Sold | Mr. Abhishek Sharma |
25 . | T2-5111 | Sold | Mr. Romit Budhwar |
26 . | T2-1112 | Sold | Mrs. Sayeeda Sultana & Mohammed Abdus Sattar Naveed |
27 . | T2-12109 | Sold | Mr. Nav Pankaj Jain |
28 . | T2-9111 | Sold | Mr. Girish Tiwari |
29 . | T2-11112 | Sold | Mr. Prakhar Sharma , Vishnu Datt Sharma & Pratima Sharma |
30 . | T2-9110 | Sold | Mr. Akhouri Bishwadeep & Abhilasha Akhouri |
31 . | T2-8110 | Sold | Mrs. Neha Gupta |
32 . | T2-6109 | Sold | Mr. Anuj Tandon |
33 . | T2-3111 | Sold | Mr. Anand Raj Singh & Pratibha Singh |
34 . | T2-11109 | Sold | Mr. Dhirendra Kumar Jha & Sudha Jha |
35 . | T2-2112 | Sold | Mr. Prashant Soni & Darpan Sharma |
36 . | T2-13109 | Sold | Mr. Rahul Nimawat |
37 . | T2-4112 | Sold | Mrs. Jaya Devi Lalwani |
38 . | T2-4111 | Sold | Mrs. Kiran Golani |
39 . | T2-1109 | Sold | Dr. Fatima Sultana & Gulab Nabi |
40 . | T2-8112 | Sold | Mrs. Karuna Goyal |
41 . | T2-8111 | Sold | Mrs. Suman Kanwar |
42 . | T2-5109 | Sold | Mr. Sanjeev Danga & Shanti Devi Danga |
43 . | T2-12112 | Sold | Mr. Utsav Sharma |
44 . | T2-6111 | Sold | Mrs. Pushpa Jindal |
45 . | T2-3109 | Sold | Mrs. Madhu Choudhary & Sudhir Chowdhary |
46 . | T2-10112 | Sold | Mr. Lalit Kumar |
47 . | T2-10111 | Sold | Mr. Dinesh Kumar & Chandramukhi |
48 . | T2-7109 | Sold | Mrs. Sangeeta Yadav |
49 . | T2-2111 | Sold | Mr. Abhishek Shukla & Deepti Dwivedi |
50 . | T2-6112 | Sold | Mr. Arun Kumar Rao & Esha Rao |
51 . | T2-12111 | Sold | Mr. Manoj Kumar Sabharwal |
52 . | T2-9109 | Sold | Mrs. Sony Akhouri , Anoushka Akhouri & Abhilasha Akhouri |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | L3-10104 | Sold | Mr. Girish Chandra Sharma & Ankit Sharma |
2 . | L3-8104 | Sold | Mrs. Deepti Sharma |
3 . | L3-4103 | Sold | Mr. Ved Prakash |
4 . | L3-12103 | Sold | Mrs. Monika Kaswan & Sumit Kumar |
5 . | L3-3104 | Sold | Mrs. Neha Chelani |
6 . | L3-11104 | Sold | Mr. Gaurav Sharma & Mukul Sharma |
7 . | L3-6104 | Sold | Mr. Gangeya Upadhyaya |
8 . | L3-4104 | Sold | Mr. Rohit Dadheech & Neha Dadheech |
9 . | L3-12104 | Sold | Mr. Abhay Lohani & Shailza Lohani |
10 . | L3-8103 | Sold | Mr. Ashwini Kumar Shukla & Gargi Shukla |
11 . | L3-7104 | Sold | Mr. Kalpesh Jain & Rajendra Jain |
12 . | L3-2104 | Sold | Mr. Ankur Singh |
13 . | L3-7103 | Unsold | |
14 . | L3-13103 | Unsold | |
15 . | L3-6103 | Unsold | |
16 . | L3-11103 | Sold | Mr. Shrey Suman Golani & Neetu Bhatia |
17 . | L3-10103 | Sold | Mr. Vivek Bothra |
18 . | L3-1104 | Sold | Mr. Vinay Aswal |
19 . | L3-1103 | Unsold | |
20 . | L3-9104 | Sold | Mrs. Geetika Sharma |
21 . | L3-5104 | Sold | Mr. Subodh Agarwal & Nidhi Garg |
22 . | L3-13104 | Sold | Mr. Kapil Chanchlani |
23 . | L3-5103 | Sold | Mr. Ved Prakash |
24 . | L3-3103 | Sold | Mr. Surjit Singh Banyal & Jyoti Banyal |
25 . | L3-9103 | Unsold | |
26 . | L3-2103 | Unsold |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | M2-1391 | Unsold | |
2 . | M2-592 | Sold | Maj. Gaurav Bhardwaj & Isha Bharti Bhardwaj |
3 . | M2-1392 | Unsold | |
4 . | M2-892 | Sold | Kamala Subhramain |
5 . | M2-692 | Sold | Mrs. Preeti Maheshwari |
6 . | M2-291 | Sold | Reena Yadav |
7 . | M2-1292 | Sold | Mrs. Ritika Kulshreshtha |
8 . | M2-1092 | Sold | Mrs. Ratan Saini |
9 . | M2-691 | Sold | Mr. Soumitra Maheshwari |
10 . | M2-191 | Unsold | |
11 . | M2-992 | Sold | Mr. Aashish Kharbanda |
12 . | M2-492 | Unsold | |
13 . | M2-292 | Sold | Mrs. Shruti Mathur |
14 . | M2-991 | Sold | Mrs. Sunistha Singh |
15 . | M2-192 | Unsold | |
16 . | M2-1091 | Sold | Mr. Anil Saini |
17 . | M2-591 | Unsold | |
18 . | M2-392 | Sold | Mr. Neeraj Aseri & Deepa Shree Bhatt |
19 . | M2-792 | Sold | Mr. Himanshu Sharda |
20 . | M2-791 | Sold | Mrs. Hina Shrivastav |
21 . | M2-891 | Sold | Kamla Subhramain |
22 . | M2-1191 | Sold | Mr. Mukesh Kumar Sharma & Deepali Sharma |
23 . | M2-491 | Unsold | |
24 . | M2-1291 | Unsold | |
25 . | M2-391 | Sold | Mr. Neeraj Aseri & Deepa Shree Bhatt |
26 . | M2-1192 | Sold | Mr. Rajesh Kumar Sharma |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | M2-4102 | Sold | Ms. Manisha Bhadoria |
2 . | M2-12102 | Sold | Mr. Pramod Kumar Tanwar |
3 . | M2-7102 | Sold | Ms. Komal Murarka |
4 . | M2-5102 | Sold | Mr. Pushpendra Kumar & Neeti Athiya |
5 . | M2-1101 | Unsold | |
6 . | M2-11102 | Sold | Mrs. Mithlesh Kumari |
7 . | M2-9102 | Sold | Mrs. Anisha Meena |
8 . | M2-5101 | Unsold | |
9 . | M2-8102 | Sold | Mrs. Vijay Sharma |
10 . | M2-3102 | Sold | Mr. Vivek Singh |
11 . | M2-1102 | Unsold | |
12 . | M2-13101 | Unsold | |
13 . | M2-13102 | Sold | Mrs. Saba Ahmad |
14 . | M2-9101 | Unsold | |
15 . | M2-2102 | Unsold | |
16 . | M2-6102 | Sold | Mr. Uttam Dhabas |
17 . | M2-6101 | Unsold | |
18 . | M2-8101 | Sold | Mr. Kailash Chand Sharma |
19 . | M2-7101 | Sold | Ms. Komal Murarka |
20 . | M2-4101 | Unsold | |
21 . | M2-10101 | Sold | Mr. Ashim Bhasin & Parul Singh |
22 . | M2-3101 | Sold | Mrs. Nidhi Singh |
23 . | M2-12101 | Sold | Mr. Neeraj Sharma |
24 . | M2-11101 | Sold | Mrs. Shakunthala Devi & Kushal Sharma |
25 . | M2-2101 | Unsold | |
26 . | M2-10102 | Sold | Mrs. Vishakha |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-08 | Sold | Mr. Surendra Singh |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-06 | Sold | Mrs. Prerna Palod |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-11 | Sold | Mr. Yogesh Sharma & Shalini Sharma |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-12 | Sold | Mr. Amit Sethi |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-05 | Sold | Mrs. Sarika Sharma |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-10 | Sold | Mr. Gajendra Kumar |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-02 | Sold | Mr. Tariq Hussain Siddiqui |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | SHOP E1 | Sold | Mrs. Prerna Palod |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-07 | Sold | Mrs. Manju Kanwar |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | SHOP E2 | Unsold |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-03 | Sold | Mr. Pawan Nagrath & Khushi Nagrath |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-14 | Unsold |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-13 | Unsold |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-01 | Sold | Mrs. Sheenu Shekhawat |
Sr.No. | Unit/Flat Detail | Booking Status | Allottee Name |
---|---|---|---|
1 . | S-09 | Sold | Mrs. Chandramukhi & Dinesh Kumar |
Undertaking | ||||
---|---|---|---|---|
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from.
I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other
legal purposes this undertaking amy serve.
|
Payment Details | ||||
---|---|---|---|---|
Comments Details | |||||
---|---|---|---|---|---|
PARA | Created BY | Comments | Date | Status | Document |
1 | Veer Bahadur Gurjar (10678) | QPR may be accepted, subject to verification | 8/19/2023 | PENDING WITH NODAL OFFICER | |
2 | Twinkle Gupta (24068) | QPR may be accepted subject to verification. | 12/7/2023 | Application Approved |