Quarterly Progress Report Summary Details April to June, 2022

Quarterly Progress Report Summary Details April to June, 2022

I. Particulars of the Project
Application No. : RAJ-RERA-APP-QPR-2022-14706 (30/07/2022)
Name of the Registered project Ashiana Umang Phase V and Ashiana Umang Plaza Registration No. of the Project RAJ/P/2021/1430
Name of the Promoter Ashiana Housing Limited Name of other Promoter(s) None
Project Address Khasra No./ Plot No.432,433, 434,434/735,435,436,437,437/736,438,439,440,453,454,454/2,454/1,478,478/716,479,480,481,482,484,485,500,502,503,504/1, , Village- Village Jhai , Near Mahindra SEZ, Ajmer Road , Jaipur - 302026 (Rajasthan)
Type of Project Group Housing Number of Sanctioned Apartments/Plots 328
Total Area of Project(In sq. meters) 79,144.22 Phase Area (In sq. meters) 19,618.40
Registration certificate is valid upto 31-10-2024 Registration extended upto Not Applicable
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block P
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
3BHK+Store Block 1 113.17 9.34 52 5
Total 52 5 3
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block P1
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
3BHK+3T Block 1 98.33 9.25 52 5
Total 52 5 1
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block S
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Block 1 74.24 8.68 26 3
3BHK+3T Block 1 98.27 9.31 26 0
Total 52 3 3
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block S1
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Block 1 74.24 8.68 52 5
Total 52 5 2
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block S2
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Block 1 74.24 8.68 52 9
Total 52 9 5
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block S3
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
2BHK Block 1 74.24 8.68 26 4
3BHK+3T Block 1 98.27 9.31 26 1
Total 52 5 4
II. Number and type of apartments booked ( April to June, 2022 )
Building Name : Block T
Apartment Type Block Number Carpet Area (Excluding balcony / Verandah / terrace) (In sq. meters) Area of Exclusive Balcony and Verandah Total Number of Sanctioned Apartments Number of Apartments booked/ sold/ allotted at the time of registration or by the end of last quarter Cumulative Number of Apartments booked/ sold/ allotted by the end of the current quarter
Shop 1 Block 1 11.68 0.00 1 0
Shop 10 Block 1 18.93 0.00 1 0
Shop 11 Block 1 18.98 0.00 1 0
Shop 12 Block 1 18.97 0.00 1 0
Shop 13 Block 1 82.13 0.00 1 0
Shop 14 Block 1 51.71 0.00 1 0
Shop 2 Block 1 11.68 0.00 1 0
Shop 3 Block 1 28.31 0.00 1 0
Shop 4 Block 1 18.93 0.00 1 0
Shop 5 Block 1 18.98 0.00 1 0
Shop 6 Block 1 18.97 0.00 1 0
Shop 7 Block 1 11.68 0.00 1 0
Shop 8 Block 1 11.70 0.00 1 0
Shop 9 Block 1 28.33 0.00 1 0
Shop E1 Block 1 65.61 0.00 1 0
Shop E2 Block 1 10.60 0.00 1 0
Total 16 0 1
III. Number of parkings allotted
Type Total No. of Car parking Total No. of Two Wheeler parking Total No. of cycle parking Total No of Mechanical Car Parking Total No. of parking allocated at the time of registration or by the end of last quarter Cumulative No. of parking allocated by the end of current quarter
Location Car Two Wheelers Car Two Wheelers
Open Area
Stilt Floor
Basement
Any Other Floor
Total
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )

TABLE - A

Building Name: Block P
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 79 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 18 32.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 12.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block P1
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 64 93.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 18 25.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 5.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block S
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 79 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 18 26.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 10.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block S1
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 79 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 20 24.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 5.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block S2
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 79 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 21 24.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 5.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block S3
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 1 Number of Stilt Floor 100 100.00
4 14 Number of Slabs of Super Structure 79 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 18 25.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 0 0.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 0 0.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 0 10.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 0 0.00
IV. Status of the Project Construction/Development
Part 1: Architectural Progress as per Form R1 issued as at the end of current Quarter ( April to June, 2022 )
Building Name: Block T
S.No. Task/Activity Percentage of work done
In Last Quarter In Current Quarter
1 Excavation 100 100.00
2 1 Number of Basement(s) and Plinth 100 100.00
3 0 Number of Stilt Floor 0 0.00
4 3 Number of Slabs of Super Structure 100 100.00
5 Internal walls,Internal Plaster,Floorings with in Flats/Premises,Doors and Windows to each of the Flat/Permises 100 100.00
6 Sanitary Fittings with in the Flat/Presmises,Electrical Fittings with in the Flat/Presmises 100 100.00
7 Staircases, Lifts wells and Lobbies at each Floor level connecting Staircases and Lifts,Overhead and Underground Water Tanks 100 100.00
8 The External Plumbing and External Plaster, Elevation, Completion of terraces with waterproofing of the Building/Wing 100 100.00
9 Installation of lifts,Water pumps, Fire Flighting Fittings and Equipment as per CFO NOC, Electrical Fittings to Common Areas,electro,Mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate 100 100.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Common areas and Facilities/Amenities Proposed Yes/No Percentage of work done Details if any
By the end of Last Quarter By the end of Current Quarter
1 Internal Roads & Footpaths 0 0
2 Water Supply 0 0
3 Sewerage (chamber, lines, Septic Tank STP) 0 0
4 Storm Water Drainss 0 0
5 Landscaping & Tree Planting 0 0
6 Street Lighting 0 0
7 Community Building 0 0
8 Treatment and disposal of sewage and sullage water 0 0
9 Solid Waste management & Disposal 0 0
10 Water conservation, Rain water harvesting 0 0
11 Energy management 0 0
12 Fire protection and fire safety requirements 0 0
13 Electrical meter room, sub-station, receiving station 0 0
Form R1: Date of issue
28/07/2022
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )

TABLE - A

Building Name : Block P
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 123,629,969.00 123,629,969.00
2 Cost incurred against the estimated cost 39,488,922.00 62,824,147.00
3 Work done (as Percentage of the estimated cost) % 32 51.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 84,141,047.00 60,805,822.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block P1
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 110,193,085.00 110,193,085.00
2 Cost incurred against the estimated cost 30,916,714.00 46,838,702.00
3 Work done (as Percentage of the estimated cost) % 28 43.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 79,276,371.00 63,354,383.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block S
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 97,551,857.00 97,551,857.00
2 Cost incurred against the estimated cost 33,909,338.00 49,848,567.00
3 Work done (as Percentage of the estimated cost) % 35 51.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 63,642,519.00 47,703,290.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block S1
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 84,788,063.00 84,788,063.00
2 Cost incurred against the estimated cost 28,340,748.00 40,862,408.00
3 Work done (as Percentage of the estimated cost) % 33 48.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 56,447,315.00 43,925,655.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block S2
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 84,788,063.00 84,788,063.00
2 Cost incurred against the estimated cost 28,340,748.00 40,862,408.00
3 Work done (as Percentage of the estimated cost) % 33 48.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 56,447,315.00 43,925,655.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block S3
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 97,551,857.00 97,551,857.00
2 Cost incurred against the estimated cost 33,850,817.00 49,287,788.00
3 Work done (as Percentage of the estimated cost) % 35 51.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 63,701,040.00 48,264,069.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00
Part 2: Engineering Progress as per Form R2 issued as at the end of current Quarter ( April to June, 2022 )
Building Name : Block T
S.No. Task/Activity Percentage of work done
By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the building 14,267,825.00 14,267,825.00
2 Cost incurred against the estimated cost 14,267,825.00 14,267,825.00
3 Work done (as Percentage of the estimated cost) % 100 100.00
4 Balance Cost to be Incurred (Bases on Estimated Cost) 0.00 0.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

TABLE - B

Internal and External Development Works for the entire registered Phase/Project

S.No. Particulars By the end of Last Quarter By the end of Current Quarter
1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities 116,593,745.00 116,593,745.00
2 Cost incurred against the estimated cost 38,260,000.00 45,819,901.00
3 Work done in Percentage (as Percentage of the estimated Cost) % 33.00 39.00
4 Balanced Cost to be Incurred (Based on Estimated Cost) 78,333,745.00 70,773,844.00
5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost 0.00 0.00

Summary of Table A and Table B

S.No. Particulars In Last Quarter In Current Quarter
1. Total Estimated Construction Cost
2. Total Cost Incurred on Construction
3. Percentage of Cost Incurred %
Form R2: Date of issue
28/07/2022
Part 3: Financial Progress as per Form R3 issued as at the end of current Quarter ( April to June, 2022 )
Incurred Amount
S.No.. Particulars Estimated Amount
(as per online details)
By the end of Last Quarter By the end of Current Quarter
1 A. Land Cost 227,217,575.00 0.00 0.00
B. Development Cost/Cost of Construction 857,659,874.00 129,143,096.00 101,677,087.00
C. Total project cost(A+B)
In Last Quarter In Current Quarter
2S.No. Percentage of total cost incurred on land %
3 Percentage of total cost incurred on development %
4 Percentage Completion of construction work (as per Project Engineer's Certificate, R-2) %
5 Percentage of the Cost incurred on Land Cost to the Total Estimated Cost %
6 Percentage of the Cost incurred on Construction Cost to the Total Estimated Cost %
7 Amount Which can be withdrawn from the separate Account 129,143,096.00 101,677,807.00
8 Less: Amount withdrawn till date of this certificate as per books of accounts and Bank Statements 185,153,000.00 122,290,917.00
9 Net Amount Which can be withdrawn from the Separate bank account under this certificate 56,009,904.00 20,613,110.00
Form R3: Date of issue
29/07/2022
Certificate showing no linen or charge on the RERA retention Account :
Part 4: Stage wise Time Schedule of completion or Milestones of Construction (as provided in the allotment letter / Agreement for Sale as per the requirements of Section 11(3)(b) of the RERA Act)
No Record Added
V. Project Common Area Details- Development Work For Whole Project
S. No. Common Area And Facilities, Amenities Proposed Percentage Of Completion (%) Drawings uploaded in online Project details or not If no, Planned date of uploading of these drawings
1 Water Supply 0
2 Rain Water Harvesting/ Recharging 0
3 Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc) 0
4 Electrification(Transformer, Solar Energy etc) 0
5 Fire Fighting Provision 0
6 Others 0
VI. Status of Approvals
A Noc's/Permission Present Status
1



2



3



4



5
B. Revision of Building Plans
1 Date of approval of latest Building Plans already uploaded on RERA web portal 12/08/2017
2 Has there been any further Modification,Amendment or Revision, if any, issued by the competent authority with regard to the building plans already uploaded?
VII. Compliances Under the Act
1.
Insurance for the Project
Status
Under section 16 of the RERA Act, it is mandatory for the promoter to obtain insurance in respect of (i) title of the land and building as a part of the Real Estate Project and (ii) construction of the Real Estate Project.
Has the insurance been obtained?
• Has the Insurance been uploaded on RERA web portal?
• Planned date of uploading Insurance Certificate 31/12/2023

VIII. Details of Real Estate Agents (if any) engaged for the Project

Has any real estate agents been engaged for the Project?     

IX. Miscellaneous

1. Is there any change in promoter profile which is not yet updated in online promoter profile?
2. Is there any change in project details which is not yet updated in online project profile?
3. Has the Completion Certificate been obtained?
If the project not completed, is the project is likely to get completed within the estimated/extended finish date given in online project details?
4. Has the Occupancy Certificate also been obtained?
Undertaking
I/ we solemnly affirm, declare and undertake that all the details started above are true to the best of my knowledge and nothing material has been concealed there from. I am executing this undertaking to attest to the truth of all the foregoing and to apprise the RERA Authority of such facts as mentioned as well as for whatever other legal purposes this undertaking amy serve.

Payment Details
Comments Details
PARA Created BY Comments Date Status Document
1 Law Officer (27634) Accepted, subject to verification. 7/3/2023 Application Approved
Nodal Officer: Rishabh Sharma, Contact: 0141-2851900, E-Mail: arp2@rajasthan.gov.in