Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2021-535 (5/31/2021)
Project Name THE CREST Promoter Name FS HOUSING PRIVATE LIMITED
Project Registration No. RAJ/P/2017/056 Project Type Group Housing
Estimated Finish Date (in online form) 31-05-2020 Project Registration Valid till
(as per registration certificate)
5/31/2018 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 6/1/2021
Duration of extension being sought 0 Months 1 Days
Project Building Plan Details
First Approval Date of Building Plan 5/11/2016
Permission/Approval of Building Plan Valid Till 4/30/2022 View
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
Project is completed and CC issued dated 01.06.2021 so need extension for 1 day i.e till 01.06.2021
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 1,44,61,30,042.00
Cost Incurred on Construction (Table A+B) ₹ 1,12,81,35,708.25
Form R3
Total Estimated Land Cost ₹ 1,20,09,46,547.00
Total Cost Incurred on Land ₹ 1,20,26,95,272.00
Total Estimated Development Cost ₹ 1,44,61,30,042.00
Total Cost Incurred on Development ₹ 1,79,20,14,890.00
Additional Information
We have already taken extension for 3 yrs till 31.05.2021 and by this date our project has been completed but CC is issued by empanelled architect dated 01.06.2021 so we need extension of 1 day.
Other Documents
Exceptional and compelling circumstances View
completion certificate View
rwa certificate View
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,6/1/2021 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).
I/ we do hereby solemnly declare and undertake:
That as per approval given by the competent authority, building plans of the project are valid only upto 4/30/2022; therefore I/ we will obtain from the competent authority the extension of validity of approved building plans upto/ beyond 6/1/2021 and submit a copy thereof to RERA within 6 months from the date of grant of extension of registration, failing which the extension of registration granted by RERA shall stand withdrawn and I/ we shall be liable for the consequences under the provisions of the Real Estate (Regulation and Development) Act, 2016 and rules & regulations made thereunder.

Registered Phase Area

Online Phase Area
8098.74
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
8098.74 ₹ 80,988.00 ₹ 40,494.00 ₹ 0.00 ₹ 40,494.00 Paid
8098.74 ₹ 80,988.00 ₹ 40,494.00 ₹ 0.00 ₹ 40,494.00 Paid

Payment Slip

Print receipt
Extension Payment Slip Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
CA Punit Gupta 9358812010 punit@rngca.com