Application for Extension of Registration

Project Details
Extension Application No. : RAJ-RERA-APP-PE-2025-1609 (8/11/2025)
Project Name Burhani Park-II Promoter Name MURTAZA .
Project Registration No. RAJ/P/2024/3381 Project Type Plotted
Estimated Finish Date (in online form) 20-08-2025 Project Registration Valid till
(as per registration certificate)
8/20/2025 View
No Previous Extension Availed In The Past
No Records Found.
Project Extension Details
Extension being Sought Upto 2/20/2026
Duration of extension being sought 6 Months 0 Days
Reason For Extension
Other than force majeure
Explanatory Note regarding the stage of development works in the project and reasons for not completing the development works by the estimated finish date
AS OUR 90 PERCENT WORK IS COMPLETED TILL JUNE NOW WE NEED TIME FOR RELEASE MORTGAGE PLOTS 12.5 % PROCESS OR PENDING WORK
Have you already availed extension of one year on grounds other than force majeure/Corona Pandemic
Latest Quarterly Progress Report
Form R2
Estimated Construction Cost (Table A+B) ₹ 2,30,00,000.00
Cost Incurred on Construction (Table A+B) ₹ 2,07,00,000.00
Form R3
Total Estimated Land Cost ₹ 2,76,00,000.00
Total Cost Incurred on Land ₹ 2,76,00,000.00
Total Estimated Development Cost ₹ 2,30,00,000.00
Total Cost Incurred on Development ₹ 1,96,68,552.00
Declaration cum Undertaking for Extension of Registration
I/ we do hereby solemnly declare and undertake:
That the project shall be completed by the extended project finish date, i.e.,2/20/2026 and that the desired extension (if granted) of registration of the project shall not affect/ damage the rights and interests of the allottee(s) under the agreement for sale nor will it exonerate the promoter from his obligations to the allottee(s) under the Real Estate (Regulations and Development) Act, 2016 and rules & regulations made thereunder. If, however due to this extension, any damages or losses are suffered by any allottee(s), any rights and interests of any of the allottee(s) are affected or any dispute arises, promoter of the project shall be solely responsible and liable to compensate the same and to resolve the dispute and shall also be liable for all legal and financial consequence of delay in handing over the possession vis-à-vis what is previously agreed with the allottee(s).

Registered Phase Area

Online Phase Area
18000.00
Has any partial CC/OC been obtained for the project? No

Payment Details

Actual PhaseArea Fees In (INR) ExtensionFees StandaradFees PenaltyFees Status
18000.00 ₹ 45,000.00 ₹ 45,000.00 ₹ 0.00 ₹ 0.00 Paid

Payment Slip

Print receipt
Extension Payment Slip

Contact Person Details

Contact Person Name MobileNo Email
MURTAZA 7976883317 MURTAZA2778@GMAIL.COM